This section contains scenarios based on the option selected for % Complete Calculation Method being Resource updates Activity - weighted avg. of resource hours.
If the entry method and option settings on the Budget and Progress Method Setup window are:
• | % Complete and Earned Progress entry method = Independently Control % complete and earned quantity |
• | % Complete Calculation Method option = Resource updates Activity - weighted avg. of resource hours |
• | % Earned Calculation Method option = Manual activity % earned and resource % earned |
then this data entry method scenario results:
Activity or Resource |
Data Element |
Data Entry Method |
Activity |
||
|
Activity % Complete |
Calculated (Weighted Hours) and (read-only). {Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Quantity)] / Sum of (Resource Quantity) } * 100 Only hard booked resources will be considered. |
Earned Progress |
Manual entry |
|
Resource |
||
|
Progress Quantity |
Manual entry |
Earned Progress |
Manual entry |
If the entry method and option settings on the Budget and Progress Method Setup window are:
• | % Complete and Earned Progress entry method = Independently Control % complete and earned quantity |
• | % Complete Calculation Method option = Resource updates Activity - weighted avg. of resource hours |
• | % Earned Calculation Method option = Manual activity % earned - updates resource % earned |
then this data entry method scenario results:
Activity or Resource |
Data Element |
Data Entry Method |
Activity |
||
|
Activity % Complete |
Calculated (Weighted Hours) and (read-only). {Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Quantity)] / Sum of (Resource Quantity) } * 100 Only hard booked resources will be considered. |
Earned Progress |
Manual entry |
|
Resource |
||
|
Progress Quantity |
Manual entry |
Earned Progress |
Calculated (Activity-level Earned Progress * Quantity) |
If the entry method and option settings on the Budget and Progress Method Setup window are:
• | % Complete and Earned Progress entry method = Independently Control % complete and earned quantity |
• | % Complete Calculation Method option = Resource updates Activity - weighted avg. of resource hours |
• | % Earned Calculation Method option = Resource updates Activity - weighted avg. of resource costs |
then this data entry method scenario results:
Activity or Resource |
Data Element |
Data Entry Method |
Activity |
||
|
Activity % Complete |
Calculated (Weighted Hours) and (read-only). {Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Quantity)] / Sum of (Resource Quantity) } * 100 Only hard booked resources will be considered. |
Earned Progress |
Calculated (Weighted Cost) {Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 |
|
Resource |
||
|
Progress Quantity |
Manual entry |
Earned Progress |
Manual entry |
This combination of settings is not available.
If the entry method and option settings on the Budget and Progress Method Setup window are:
• | % Complete and Earned Progress entry method = Independently Control % complete and earned quantity |
• | % Complete Calculation Method option = Resource updates Activity - weighted avg. of resource hours |
• | % Earned Calculation Method option = Update Activity and all resources on activity start and finish |
then this data entry method scenario results:
Activity or Resource |
Data Element |
Data Entry Method |
Activity |
||
|
Activity % Complete |
Calculated (Weighted Hours) and (read-only). {Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Quantity)] / Sum of (Resource Quantity) } * 100 Only hard booked resources will be considered. |
Earned Progress |
Calculated (Weighted Cost) {Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 |
|
Resource |
||
|
Progress Quantity |
Manual entry |
Earned Progress |
Calculated based Update Activity and all resources on activity start and finish. For example: If % earned on Actual Start = 5% and % earned on Actual Finish = 95 % then, When Actual Start is entered, Earned Progress = 5% * Quantity When Actual Finish is entered, Earned Progress = 100% * Quantity. |