This section contains scenarios based on the option selected for % Complete Calculation Method being Resource updates Activity - weighted avg. of resource costs. There is only one data entry scenario for this setting.
If the entry method and option settings on the Budget and Progress Method Setup window are:
• | % Complete and Earned Progress entry method = Activity and resource % complete updates % earned |
• | % Complete Calculation Method option = Resource updates Activity - weighted avg. of resource costs |
• | % Earned Calculation Method option = Not available |
then this data entry method scenario results:
Activity or Resource |
Data Element |
Data Entry Method |
Activity |
||
|
Activity % Complete |
Calculated (Weighted Hours) and read-only. {Sum of [ (Resource Progress Quantity / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 All resources will be considered |
Earned Progress |
Calculated (read-only) Same as Activity % Complete |
|
Resource |
||
|
Progress Quantity |
Manual entry |
Earned Progress |
Calculated (read-only) Same as Progress Quantity |