Method is Lead resource updates Activity and other resources

This section contains scenarios based on the option selected for % Earned Calculation Method being Lead resource updates Activity and other resources. There is only one data entry scenario for this setting.

% Complete Calculation Method options are not available

If the entry method and option settings on the Budget and Progress Method Setup window are:

% Complete and Earned Progress entry method = Activity and resource % earned updates % complete
% Complete Calculation Method option = Not available
% Earned Calculation Method option = Lead resource updates Activity and other resources

then this data entry method scenario results:

Activity or Resource

Data Element

Data Entry Method

Activity

 

Activity % Complete

Calculated (read-only)

Same as Earned Progress

Earned Progress

Calculated (Weighted Hours) and read-only.

{Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100

All resources will be considered.

Resource

 

Progress Quantity

Calculated (read-only)

Same as Earned Progress

Earned Progress

Manual Entry (Only resource that is selected under dropdown).

For all other resources, Earned Progress will be calculated based on

(Leader Earned Progress / Leader Quantity) * Resource Quantity

 

 

 

 