This section contains scenarios based on the option selected for % Earned Calculation Method being Manual activity % earned - updates resource % earned. There is only one data entry scenario for this setting.
If the entry method and option settings on the Budget and Progress Method Setup window are:
• | % Complete and Earned Progress entry method = Activity and resource % earned updates % complete |
• | % Complete Calculation Method option = Not available |
• | % Earned Calculation Method option = Manual activity % earned - updates resource % earned |
then this data entry method scenario results:
Activity or Resource |
Data Element |
Data Entry Method |
Activity |
||
|
Activity % Complete |
Calculated (read-only) Same as Earned Progress |
Earned Progress |
Manual entry |
|
Resource |
||
|
Progress Quantity |
Calculated (read-only) Same as Earned Progress |
Earned Progress |
Calculated (read-only) (Activity-level Earned Progress * Quantity) |