This section contains scenarios based on the option selected for % Earned Calculation Method being Resource updates Activity - weighted avg. of resource costs. There is only one data entry scenario for this setting.
If the entry method and option settings on the Budget and Progress Method Setup window are:
• | % Complete and Earned Progress entry method = Activity and resource % earned updates % complete |
• | % Complete Calculation Method option = Not available |
• | % Earned Calculation Method option = Resource updates Activity - weighted avg. of resource costs |
then this data entry method scenario results:
Activity or Resource |
Data Element |
Data Entry Method |
Activity |
||
|
Activity % Complete |
Calculated (read-only) Same as Earned Progress |
Earned Progress |
Calculated (Weighted Hours) and read-only. {Sum of [ (Resource Earned Progress / Resource Quantity) * (Resource Amount)] / Sum of (Resource Amount) } * 100 All resources will be considered |
|
Resource |
||
|
Progress Quantity |
Calculated (read-only) Same as Earned Progress |
Earned Progress |
Manual entry |
Oracle Corporation
Primavera Unifier 9.10 • Copyright © 1998, 2012, Oracle and/or its affiliates. All rights reserved.