This section contains scenarios based on the option selected for % Earned Calculation Method being Update Activity and all resources on activity start and finish. There is only one data entry scenario for this setting.
If the entry method and option settings on the Budget and Progress Method Setup window are:
• | % Complete and Earned Progress entry method = Activity and resource % earned updates % complete |
• | % Complete Calculation Method option = Not available |
• | % Earned Calculation Method option = Update Activity and all resources on activity start and finish |
then this data entry method scenario results:
Activity or Resource |
Data Element |
Data Entry Method |
Activity |
||
|
Activity % Complete |
Calculated (read-only) Same as Earned Progress |
Earned Progress |
Calculated (read-Only) based Update Activity and all resources on activity start and finish. For example: If % earned on Actual Start = 5% and % earned on Actual Finish = 95 % then, When Actual Start is entered, Earned Progress = 5% When Actual Finish is entered, Earned Progress = 100% |
|
Resource |
||
|
Progress Quantity |
Calculated (read-only) Same as Earned Progress |
Earned Progress |
Calculated (read Only) based Update Activity and all resources on activity start and finish. For example: If % earned on Actual Start = 5% and % earned on Actual Finish = 95 % then, When Actual Start is entered, Earned Progress = 5% * Quantity When Actual Finish is entered, Earned Progress = 100% * Quantity. |