Tracking Gantt Chart tab of the Schedule Sheet Properties

A tracking Gantt chart allows you to compare two sets of dates for a specific activity. It allows you to track activity progress against the original plan. For example, the tracking Gantt chart allows the comparison between two sets of dates such as baseline and actuals. Users with view permissions can view a tracking Gantt chart. The tracking Gantt chart is view only. It is not interactive like the regular Gantt chart.

You can define the display of data elements on the activity bars on the Tracking Gantt chart. You can add up to three labels: to the left, on top, and to the right of each activity bar. The labels correspond with the data element fields that are available on the Properties window (activity attribute form) for each activity.

To configure Tracking Gantt chart activity bar text

1 Click the Tracking Gantt Chart tab.
2 Select data elements. You can add one label or all three. The selected data element(s) will display at the Top, Left or Right of the activity bar. The available data element options are derived from the activity form (schedule attribute form or default form).
3 Click OK.

 

 

 

 