Refresh allows you to undo changes to cells in selected rows, so you can save the Activity Sheet without updating those cells.
To refresh Activity Sheet rows
1 | In User Mode, navigate to Projects tab > Programs > Schedule Manager > Activity Sheets. The Activity Sheet log opens. |
2 | Select the Activity Sheet and click Open. |
3 | Select one or more rows in the sheet. |
4 | Click the Refresh button. Highlighting is removed from the selected rows. Those rows are not modified when you click Save to update the Activity Sheet. |