You can manually validate conditions, which is the same validation that is performed during scheduled runs. The dashboard is updated to show any changes to the gates conditions.
Note: Your Administrator can configure that Gates conditions are validated on each Gates run.
To manually run gates
In the Gates dashboard, click the Refresh button.
If a gate condition is met, it is marked as complete. If all gates conditions are have been met for a shell phase, and Automatic Advancement is set, the shell phase advances to the next phase.