Creating Overhead Codes

Previous TopicNext TopicContents

Create overhead codes for P6 Progress Reporter users to add overhead activities to their timesheets to log timesheet hours that are not associated with the project.

To create an overhead code:

  1. Click the Administer menu and select Enterprise Data.
  2. In the Enterprise Data pane, expand Global and click Overhead Codes.
  3. On the Overhead Codes page:
    1. Click  Add (Insert).
    2. In the Name field, double-click and type a unique code.
    3. In the Description field, double-click and type a unique name.
    4. Click Save (Ctrl+S).

Tips

When you specify that two approval levels are required to approve timesheets, timesheets that contain only overhead activities bypass project manager approval and are sent directly to the resource/cost manager for approval. For timesheets containing a mix of regular and overhead activities, project managers can view, but not approve, the overhead activities.

Related Topics

P6 Progress Reporter Implementation

P6 Progress Reporter Implementation Process

Configuring Resources to Use P6 Progress Reporter

Timesheets Page

Configuring P6 Progress Reporter

Working with Timesheet Periods

Accessing P6 Progress Reporter from Client Browsers for the Web Browser Version

Accessing P6 Progress Reporter from Client Browsers for the Java Web Start Version

About Timesheet Approval



Legal Notices
Copyright © 1999, 2014, Oracle and/or its affiliates. All rights reserved.

Last Published Wednesday, February 19, 2014

PDF Library