The Task Dates Tab allows you to enter the start and end dates associated with each major task, for every service provider, in all study locations.
To track the dates that major tasks start and end:
Navigate to the Task Dates Tab.
Select the service provider for which you are entering data, from the service provider drop down box.
Select the location for which you are entering data, from the Location drop down box.
For any major task for which you have begun entering work completed, enter the date that task began in the “Started” field. If you have already entered work completed, a start date has been entered automatically by the system. You can override this date with a more exact date if you wish.
In the Completed field, enter the date when the major task was completed.