Viewing and Modifying Activity Teams

To view and modify activity teams, use the Project Activity Team component (PROJ_ACT_TEAM).

This topic discusses how to:

Pages Used to View and Modify Activity Teams

Page Name

Definition Name

Navigation

Usage

Activity Definitions - Team

PROJ_ACT_TEAM_01

select Project Costing, then select Activity Definitions, then select Team, then select Team

View, add, and delete members of an activity team.

Assign Team from Project

PROJ_TEAM_COPY

Click Copy from Project on the Activity Definitions - Team page.

Copy selected project team members and their schedules to a single activity team.

Assign Team from Project

PROJ_TEAM_COPY

Click Copy from Activity on the Activity Definitions - Team page.

Copy selected activity team members and their schedules to a single activity team.

Assign Team from Project

PROJ_TEAM_COPY

select Project Costing, then select Activity Definitions, then select Assign Team from Project, then select Assign Team from Project

Copy selected project team members and their schedules to multiple activity teams.

Select activities for resources/requirements

PC_TEAM_ACT_SELECT

Click Next in the Assign Team from Project page. The Next button is available only on the Assign Team from Project page that you access by using the navigation path select Project Costing, then select Activity Definitions, then select Assign Team from Project.

Select the activity teams to which you want to copy the project team members that you selected on the Assign Team from Project page.

Time by Activity

PC_LABOR_ACT_TIME

Click the Reported Time Chart link on the Activity Definitions - Team page.

Review labor by activity. The system retrieves transactions from the Project Transactions Summary table (PC_SUMMARY_TBL) for transactional rows with an analysis type in the LABOR analysis group.

Time by Employee

PC_LABOR_EMP_TIME

Click inside a charted area on the Time by Activity page for a specific employee.

Review project labor by employee. The system retrieves transactions from the Project Transactions Summary table for transactional rows with an analysis type in the LABOR analysis group.

Activity Team Standard Rate Sheet

PC_ACT_TEAM_RATES

Click the Activity Team Rates link on the Activity Definitions - Team page.

View the cost and bill rates for activity team members by employee, job code, or role.

Activity Definitions - Team Page

Use the Activity Definitions - Team page (PROJ_ACT_TEAM_01) to view, add, and delete members of an activity team.

Image: Activity Definitions - Team page

This example illustrates the fields and controls on the Activity Definitions - Team page. You can find definitions for the fields and controls later on this page.

Activity Definitions - Team page

To directly add an individual employee to an activity team, add a new row in the Activity Team Members grid and enter the team member's employee ID and project role. You can add employees to the activity team only if they exist on the project team.

To remove an individual employee from an activity team, delete the corresponding row in the Activity Team Members grid. The employee is removed from the activity team but remains on the project team.

View Activity Team Rates

Click the Team Rates link to access the Activity Team Standard Rate Sheet page to view the charge rates for activity team members and unassigned positions of the activity team.

See Viewing Team Rates.

Assign Team from Project Page (to a single activity team)

Use the Assign Team from Project page (PROJ_TEAM_COPY) to copy selected project team members and their schedules to a single activity team.

Image: Assign Team from Project page (Copy from Project button)

This example illustrates the fields and controls on the Assign Team from Project page (Copy from Project button). You can find definitions for the fields and controls later on this page.

Assign Team from Project page (Copy from Project button)

To copy project team members to a single activity team, click Copy from Project on the Activity Definitions - Team page where you want to add team members.

Filter Options

When you first access this page, all eligible resources appear in the Select Team Members to Copy grid. Use the Filter Options collapsible group box to filter on various resource attributes so that you can more easily select project team members to add to an activity team.

Select Team Members to Copy

Select individual project team members that you want to copy to the activity team, or click Select All for the system to select all project team members to copy.

Copying Activity Team Members From Other Activity Teams

Use the Assign Team from Project page (PROJ_TEAM_COPY) to copy selected activity team members and their schedules to a single activity team.

Image: Assign Team from Project page (Copy from Activity button)

This example illustrates the fields and controls on the Assign Team from Project page (Copy from Activity button). You can find definitions for the fields and controls later on this page.

Assign Team from Project page (Copy from Activity button)

To copy team members from one activity team to another, click Copy from Activity on the Activity Definitions - Team page where you want to add team members.

Copying Project Team Members to Multiple Activity Teams

Use the Assign Team from Project page (PROJ_TEAM_COPY) to copy selected project team members and their schedules to multiple activity teams.

Use the menu navigation to access the Assign Team from Project page for the project. Select the project team members and schedules, and click Next to access the Select activities for resources/requirements page to complete the process of adding project team members to multiple activity teams.

Select Activities for Resources/Requirements

Use the Select activities for resources/requirements page (PC_TEAM_ACT_SELECT) to select the activity teams to which you want to copy the project team members that you selected on the Assign Team from Project page.

Image: Select activities for resources/requirements page

This example illustrates the fields and controls on the Select activities for resources/requirements page. You can find definitions for the fields and controls later on this page.

Select activities for resources/requirements page

Use this page to complete the process of adding project team members to multiple activity teams.

Time by Activity Page

Use the Time by Activity page (PC_LABOR_ACT_TIME) to review reported time by activity and team members.

The system retrieves transactions from the Project Transactions Summary table (PC_SUMMARY_TBL) for transactional rows with an analysis type in the LABOR analysis group.

Image: Time by Activity page

This example illustrates the fields and controls on the Time by Activity page. You can find definitions for the fields and controls later on this page.

Time by Activity page

You can select a different project activity, unit of measure, and type of chart, as desired, and click Draw Chart.

Click inside a charted area on the Time by Activity page for a specific employee to view a chart showing the amount of time that the employee reported on all activities for the project.