Manage Finance Lock/Close Period Enforcement Settings

Previous TopicNext TopicContents

To configure the finance lock settings:

  1. Click the Application Settings tab.
  2. Select Manage Finance Lock/Close Period Enforcement Settings link.
  3. Select an initiative and click the [Edit] link next to it.
  4. Select Strict or Limited.
  5. Click the Update button to save you changes.

    Important!

    Oracle recommends not changing the enforcement mode on a live production system. When the mode is changed, it takes effect only for new projects created from that point of time. Old projects continue in the previous enforcement mode and cannot be changed.

    Notes:

The following table lists the supported options for both the Strict and Limited modes.

Supported Options

Strict

Limited

Enforcement

Always Guaranteed

Not Guaranteed. Guaranteed only when used with AET set to Effort from Finances, finances are edited in the monthly mode, and resource rates are explicitly overridden at the project level.

Enforcement is through manual process.

Resource labor rate, role, labor rate changes

Not allowed if it can affect a finance lock/close period in any project.

System does not check for violation and finance lock/close period integrity is not protected.

Currency conversion rate (exchange rate) changes

Not allowed if it can affect a finance lock/close period in any project.

System does not check for violation and finance lock/close period integrity is not protected.

Supported AETs

Effort at Resource Level (Detail), Effort from Timesheet, and Effort from Finances

All AET options

Unsupported AETs

Duration& Resource % availability, Effort at Activity Level- Equal % Distribution, Effort at Activity Level- Unequal % Distribution, and Effort at Resource Level (Summary)

None

Editing finances in yearly or aggregate (annualized) mode

Not allowed

Allowed. Finance lock may not be protected.

See Also

Application Settings

Configuring Percentage Completion

Restricting Document Sizes

Auto Close Parent Activity

Official Phase Start and Close Defaults

Measure Data Due Reminder Notification

Report Attachment Max Size

Manage Detail Section Display Preference

Specify Levels to Pre-fill

Manage Project Cycle Time Mode

Display Mode For Filter Page Sections

Manage Activity Labor Cost Capitalization Settings

Stream Ticker Refresh Interval

Setting the Max Cache Size for Listing Pages

Manage Evaluation And Fields Help

Manage User Productivity Kit

Online Help URL

Manage Estimated Time to Complete for Timesheet Settings

Manage Allowed Grace Period in Days for Activities in Timesheet

Manage General Email Defaults

Manage Static Application Settings

Viewing Account Properties

Integration Settings



Legal Notices
Copyright © 2000, 2014, Oracle and/or its affiliates. All rights reserved.

Last Published Monday, March 24, 2014