Updating Task Progress

After you have marked a task as started, you can update its progress in fields specified by your project manager.

To update a task:

  1. On the Task List, tap the task you want to update.
  2. Tap the field you want to update and adjust its value using the spinning time controls. You cannot edit fields with gray text.
  3. Tap Save.

    Note:

    • Tasks marked with an asterisk (*) on the Task List have been modified, but their changes have not been saved.
    • Time Left is automatically updated once you update Time Spent. Manually update Time Left if the amount of time remaining on the task differs from Time Left minus Time Spent. You cannot set the Finished date to a future date.