ENABLE CXL RULES IN WEEKS Application Setting

Group.  Reservations

Type.  Parameters

Application.

ORS (property)

PMS

Description. When enabled, users can configure cancellation rules in either days or weeks, where the days value must be a multiplier of 7 days (to be converted to a week value). When enabled, GDS systems connected to Opera will receive the CXL rule message with xxW (where x is the number of days) value when the number of days exceeds 99 Days.

Internal Name. ENABLE_CXL_RULES_IN_WEEKS

Property Determination. When OPMS and ORS are interfaced, this parameter must be enabled in both OPMS and ORS to ensure synchronization. When enabling this parameter, the user will be prompted if cancellation rules exist where the number of days before arrival is greater than 99 and not divisible by 7. If the user selects Yes to the prompt, the number of days before arrival will be rounded down for these cancellation rules in order to make them divisible by 7.

Activation / Inactivation Rules. 

<none>

Available Values.

Y - Yes

N - No

Add On Licenses/Country Specifics.

The OPG_XXX Opera GDS license code (global for ORS and property level for PMS) must be active.

Other Application Settings.

The CASHIERING>CANCELLATION HANDLING application parameter must be set to Y.

Affected Areas

Menus / Screens / Fields.

Setup>Configuration>Reservations>Codes>Cancellation Rules>New/Edit

Reports & Report Forms.

<none>

Permissions.

<none>

Notes.

<none>