Administration Console Online Help

Previous Next Open TOC in new window
Content starts here

Create global Work Managers


Using the Administration Console, you can create global Work Managers that are used to prioritize thread execution.

To create a global Work Manager:

  1. If you have not already done so, in the Change Center of the Administration Console, click Lock & Edit (see Use the Change Center).
  2. In the left pane of the Console, expand Environment and select Work Managers.
  3. Click New.
  4. Select the Work Manager radio button, then click Next.
  5. Enter a name for the new Work Manager and click Next.
  6. In the Available Targets list, select server instances or clusters on which you will deploy applications that reference the Work Manager.
  7. Click Finish.
  8. To activate these changes, in the Change Center of the Administration Console, click Activate Changes.
    Not all changes take effect immediately—some require a restart (see Use the Change Center).

Result

The new Work Manager appears in the Global Work Managers, Request Classes and Constraints table.

After you finish

After you have created a global Work Manager, you create at least one request class or constraint. The global Work Manager uses request classes and constraints to determine how to prioritize work. For general information on request classes and constraints, see Using Work Managers to Optimize Scheduled Work. For more information on creating global request classes using the Administration Console, see Create global request classes. For more information on creating global constraints using the Administration Console, see Create global constraints.


Back to Top