Changing Last Actual Period

You can use Entity Change Management to move the Last Actual Period.

  To change last actual time periods:

  1. Select Server, and then Entity Change Management.

  2. Open an ECM document.

  3. Select Time.

  4. Select Edit, then Add Time Change, and then select Move Actual Boundary.

  5. Select Use this scenario's data when adjusting actual periods to use data from a scenario and, in the base entity, select a scenario.