This section contains the topic:
For bills of material and routings, you can have a batch quantity for products that are normally built in specific batch sizes, such as chemicals, food, or petroleum.
To obtain a correct rollup when you use a batch quantity, the accounting cost quantity, the bill of material batch size, and the routing batch size must match, as follows:
Labor and overhead costs are rolled up only if the accounting cost quantity and the routing batch size match.
Material costs are rolled up only if the accounting cost quantity and the bill of material batch size match.
The following table illustrates these possibilities.
Accounting Cost Quantity | Bill Batch Size | Routing Batch Size | Rollup |
---|---|---|---|
10,000 | 10,000 | 10,000 | Complete |
5,000 | 10,000 | 10,000 | None |
10,000 | 5,000 | 10,000 | Labor and Overhead Only |
10,000 | 10,000 | 5,000 | Material Only |
If the Simulate Cost Rollup program does not find a bill of material whose batch quantity matches the accounting cost quantity, it uses the zero batch bill. ACQ is the primary UOM.