This chapter contains these topics:
Section 37.2, "Generic Rate/Message Records Program (P00191)"
Section 37.3, "Generic Rate/Message Records Program (P00191)"
Processing Option | Processing Options Requiring Further Description |
---|---|
REVIEW SELECTION CRITERIA: | |
1. Enter the specific Type of Data on which to inquire.
A default of blank will use the first data type within the data base. |
Processing Option | Processing Options Requiring Further Description |
---|---|
USER DEFINED CODES: | |
1. Enter the desired System Code. | |
2. Enter the desired Record Type. | |
DISPLAY INFORMATION: | |
3. Enter an '1' to display Rate Text or
Enter an '2' to display Message Text |
|
4. If displaying Message Text,
Enter an '1' for 60 column display or Enter an '2' for 80 column display |
Processing Option | Processing Options Requiring Further Description |
---|---|
USER DEFINED CODES: | |
1. Enter the desired System Code. | |
2. Enter the desired Record Type. | |
DISPLAY INFORMATION: | |
3. Enter an '1' to display Rate Text or
Enter an '2' to display Message Text |
|
4. If displaying Message Text,
Enter an '1' for 60 column display or Enter an '2' for 80 column display |
Processing Option | Processing Options Requiring Further Description |
---|---|
DEFAULT VALUES: | |
1. Enter the Unit of Measure.
If left blank, 'HR' will be used. |
Processing Option | Processing Options Requiring Further Description |
---|---|
PROCESSING CONTROL: | |
1. Enter a '1' to calculate Kanban sizes. | |
2. Enter a '1' to update Kanban Master file. | |
3. Enter a '1' to print Kanban cards. | |
4. Enter a '1' to print Kanban Exception Report. | |
SAFETY STOCK: | |
5. Enter the desired safety stock expressed as a percentage of daily production. ('15' = 15%) | |
FILTER CONTROL: | |
6. Enter the range, expressed as a percentage, above or below which the Kanban should not be changed.
('15' = plus or minus 15%) |
|
KANBAN AVERAGE DAILY DEMAND: | |
7. Enter a '1' to select summation of the MPS/MRP demands desired, or enter a '2' to select greater of MPS/MRP demands desired. If no demands are selected, the Planning Time Fence Rule for the item will be used.
a. Forecasts b. Sales Orders c. Firm Work Orders d. Planned Orders e. Rate Schedule |
|
CALCULATION: | |
8. Enter number of hours equivalent to one day. (Default is 8) | |
9. Enter the date range to use for the average daily demand calculation.
a. Beginning Date (Required) b. Ending Date (Required) |
|
USER DEFINED PROGRAM: | |
10. Enter the program name of the Kanban size calculation program. | |
BAR CODE INFORMATION: | |
11. Enter the format for bar code printing.
1 = Code 3 of 9 (Code 39) 2 = Code 128 If left blank, bar codes will not print. |