Use the Percent Completion Type page to select how EnterpriseTrack should calculate the percentage complete for projects. For each initiative defined in your system, you can select a default from the following choices:
Manual Mode: Users can manually enter a number from the Project Basics page.
Effort-based (Actual vs Planned Effort for Immediate Children): Percentage complete is calculated based on the duration/actual effort and the planned effort of all top-level tasks.
Effort-based (Actual vs Planned Effort for All Children): Percentage complete is calculated based on the duration/actual effort and the planned effort of all tasks.
Count-based (Completed vs Total Count for Immediate Children): Percentage complete is calculated based on the number of completed tasks and the total number of top-level tasks.
Count-based (Completed vs Total Count for All Children): Percentage complete is calculated based on the number of completed tasks and the total number of all tasks.
To configure the percent completion type:
Click the Application Configuration tab.
Select the Percent Completion Type link.
Click the [Edit] link next to your initiative.
From the drop-down menu, select the percent completion type.