Changing the Start Date of a Project

Previous TopicNext TopicContents

To change the Project Start date:

  1. Navigate to the Project Dates page within a project by clicking on the Dates link in the Left Navigation Bar, or from the Project Module Menu (Project #) select Go To > Dates.
  2. From the Edit menu select Start Date. In the Planned Vs Actual Dates section, make the appropriate changes. You will also have to tell the system how you want these changes to affect the financial tracking and due dates.
  3. How should shifting the Start Date affect Financial Data?
  4. Should shifting the Start Date also shift Due Dates?
  5. Click Update to save the changes.

    Note: If you are unable to make changes to this page, make sure you have the required permission (Actual Project Start Can Differ from Planned Project Start). Contact your administrator for more information.

Related Topics

Working with Project Dates

Setting Phase Due Dates



Legal Notices
Copyright © 2000, 2015, Oracle and/or its affiliates. All rights reserved.

Last Published Thursday, August 27, 2015