Executing Load Plans

Follow this procedure to execute a load plan.

Note the following points:
  • You can have separate load plans for each source, but load plans should not run in parallel

  • You can only execute a load plan if it was successfully generated. See Generating Load Plans for instructions.

  1. In the Tasks pane of Oracle BI Applications Configuration Manager, select Manage Load Plans, which appears under the Load Plans Administration heading.

    The Manage Load Plans page is displayed.

  2. In the Load Plans list, select the load plan you want to execute.
  3. In the Load Plans toolbar, click the Execute icon.

    The Execute Load Plan dialog is displayed.

  4. Specify the following information:
    Field Description

    Context

    The ODI context to be used when the load plan is run. Note that Global is the only supported context.

    Logical Agent

    The ODI logical agent to be used when the load plan is run.

    Oracle Data Integrator Work Repository

    The name of the ODI Work repository.

  5. Click OK.
  6. (Optional) Click the Show Execution Status Details icon to display detailed information about the status of the execution.