Adding and editing metric timelines

On the Timeline component, you can add multiple metric timelines. For each metric timeline, you select the view, date/time attribute, and metric to use for the display. You can also change the display order of the metric timelines.

To add and edit metric timelines:

  1. To add a new metric timeline, click Add Metric.
  2. On each metric timeline, from the view list, select the view to use for the timeline.
    View list for a metric timeline on the Timeline component

    If the view does not include at least one date/time attribute that can be used as a dimension, then it cannot be used for a timeline.

  3. To select the metric to display on the metric timeline:
    1. Click the metric name.

      Big Data Discovery displays a list of available attributes to use for the metric.


      List of attributes for a metric on a metric timeline on a Timeline component

      You can also use the search field to find a specific attribute.

    2. Click the attribute you want to use for the metric.
    3. If the metric is not a predefined metric, then use the aggregation method list to select the aggregation method to use to calculate the metric value.
      Aggregation method list for a metric timeline on the Timeline component
  4. To select the date/time attribute to use on the metric timeline:
    1. Click the attribute name.

      Big Data Discovery displays the list of available date/time attributes.


      Date/time attribute list for a metric timeline on a Timeline component

      You can also use the search field to find a specific attribute.

    2. Click the date/time attribute you want to use.
  5. To change the display order of the metric timelines, drag the timeline to the new location.
  6. To delete a metric timeline, click its delete icon.

    If there is only one metric timeline, then you cannot delete it. You can only change its configuration.