Configuring Percentage Completion
Use the Percent Completion Type page to select how EnterpriseTrack should calculate the percentage complete for projects. For each initiative defined in your system, you can select a default from the following choices:
- Manual Mode: Users can manually enter a number from the Project Basics page.
- Effort-based (Actual vs Planned Effort for Immediate Children): Percentage complete is calculated based on the actual effort and the planned effort of all top-level tasks.
- Effort-based (Actual vs Planned Effort for All Children): Percentage complete is calculated based on the actual effort and the planned effort of all tasks.
- Duration-based (Actual vs Planned Duration for Immediate Children): Percentage complete is calculated based on the duration and the planned duration of all top-level tasks.
- Duration-based (Actual vs Planned Duration for All Children): Percentage complete is calculated based on the duration and the planned duration of all tasks.
- Count-based (Completed vs Total Count for Immediate Children): Percentage complete is calculated based on the number of completed tasks and the total number of top-level tasks.
- Count-based (Completed vs Total Count for All Children): Percentage complete is calculated based on the number of completed tasks and the total number of all tasks.
To configure the percent completion type:
- Click the Application Configuration tab.
- Select the Percent Completion Type link.
- Click the [Edit] link next to your initiative.
- From the drop-down menu, select the percent completion type.
- Click Update to save your changes.
Project Settings
Auto Close Parent Activity
Official Phase Start and Close Defaults
Manage Detail Section Display Preference
Specify Levels to Pre-fill
Manage Project Cycle Time Mode
Set Minimum Slacks for Critical Path