You can only perform this task when logged into the Active Primary NOAM.
Use this procedure to modify the Permissive Dialing Period (PDP) start and or end dates for one or more existing NPA splits.
- Select EAGLE XG Database > Maintenance > NPA Splits.
The EAGLE XG Database > Maintenance > NPA Splits page appears.
- Click the Modify tab.
The Modify tab appears.
- Enter the Old NPA, New NPA, and NXX fields to select the NPA to modify. To modify all NXX, leave the All selection box check marked.
- Enter the PDP Start and/or PDP End dates, as needed.
Both the PDP Start and PDP End dates can be modified for pending splits. Only the PDP End date can be modified for active splits. Neither can be modified for completed splits. The PDP End date must be greater than today’s date.
For more information about these fields please see
NPA splits elements.
- Click Modify.
The NPA splits are updated.