Update the Owning Workspaces of a Reporting Cycle

Update the owning workspace of a reporting cycle to move it to another workspace that you are assigned. If you move a reporting cycle to a workspace that is higher in the workspace hierarchy, it will be available to more workspaces.

To update the owning workspace of a reporting cycle:

  1. In the object selector, select a workspace.
  2. In the sidebar, select Summary & Settings.
  3. On the Summary & Settings menu, select Dictionaries, and then select Reporting Cycles.
  4. Select a reporting cycle.
  5. Select the Context menu, and then select Change Owning Workspace.
  6. In the Select Workspace dialog box, select the new owning workspace, and select Select.
  7. Select Save.
  8. In the Summary & Settings panel, select Close.

This setting is used in the following apps:

Resources
Schedule
Scope


Last Published Monday, June 24, 2024