001003276
001003276: The timesheet cannot be approved. Some of the resource assignments could not be created as user's resource does not exist in the project or project's workspace
Cause: An attempt was made to create resource assignments for a resource that does not exist in project or project's owning workspace
Resolution: Pull down/promote the resource to project and try again
Last Published Tuesday, August 19, 2025