001003318
001003318: The selected resources or resources in the selected hierarchy are assigned roles. The assigned roles or roles in the hierarchy have a project calendar assignment. Assign a workspace calendar or promote the project calendars before promoting the resources. Role IDs : {0} .
Cause: A project calendar is assigned to a role that is assigned to one of the selected resources.
Resolution: Assign a workspace calendar to the project role or promote the project calendar assigned to the role.