001003319

001003319: The selected roles or roles in the selected hierarchy are assigned resources. The assigned resources or resources in the hierarchy have a project calendar assignment. Assign a workspace calendar or promote the project calendars before promoting the roles. Resource IDs : {0} .

Cause: A project calendar is assigned to a resource that is assigned to one of the selected roles.

Resolution: Assign a workspace calendar to the project resource or promote the project calendar assigned to the resource.