003015097

003015097: Activity remaining finish date before remaining start date, you cannot change at completion duration.

Cause: This occurs when changing the at completion duration sets the finish date before the start most likely by recalculating the remaining duration to a negative value.

Resolution: Ensure that remaining finish date is always after remaining start date.



Last Published Tuesday, August 19, 2025