003015133
003015133: You can only select a Uncertainty Distribution for activities that are task dependent or resource dependent.
Cause: An attempt was made to select a Uncertainty Distribution for an activity that is not task dependent or resource dependent.
Resolution: Do one of the following:
Remove the Uncertainty Distribution if the activity is not task dependent or resource dependent.
Change the Type to task dependent or resource dependent and then select a Uncertainty Distribution.