003015133

003015133: You can only select a Uncertainty Distribution for activities that are task dependent or resource dependent.

Cause: An attempt was made to select a Uncertainty Distribution for an activity that is not task dependent or resource dependent.

Resolution: Do one of the following:

Remove the Uncertainty Distribution if the activity is not task dependent or resource dependent.

Change the Type to task dependent or resource dependent and then select a Uncertainty Distribution.



Last Published Friday, July 12, 2024