009014012

009014012: There is not enough work time between the task due date or completed date and the start date.

Cause: An attempt was made to set a task start date without enough work days in the past five years, from the due date or completed date.

Resolution: Adjust the due date, completed date, duration, or non-work days so that enough work days are available to set the start date.



Last Published Friday, July 12, 2024