009014059
009014059: In a Finish to Start task hand-off, the successor Start Date must be after its predecessor's Due Date.
Cause: An attempt was made to create an invalid Finish to Start task hand-off.
Resolution: Remove the task hand-offs where the predecessor task's Due Date is later than the successor task's Start Date.
Last Published Friday, July 12, 2024