009015018
009015018: Cannot move tasks.
Cause: This action was canceled because tasks cannot be moved onto the milestone bar or after a finish milestone. Move tasks to a valid position and try again.
Resolution: Move the task to a valid location within the project hierarchy, ensuring it is not placed on a milestone row or after a finish milestone.
Last Published Thursday, August 20, 2026