013000033: The Program Planned Start Date or Program Planned Finish Date values cannot be updated when the Program Planned Budget source is set to Project Roll-up.
Cause: You cannot update cost curve dates that are calculated as project roll-ups. Only cost curves with a Source value of Manual can be updated.
Resolution: Revert the date back to its original value, or cancel all changes to the form.