Update an Integrated Budget Item
To update an integrated budget item:
- Create or generate a JSON object containing the following fields, including any additional fields you want to update:
- sourceId: The unique identifier of budget item data in an external source, such as an ERP system.
- Send a request to the API using the following information:
-
Endpoint:
<>/budgetItem/sync
-
Operation:
POST
- Example Request Body:
{ "sourceId": 1, "budgetItemCost": { "originalCost": 300, "currentCost": 700, "originalCostProject": 300, "currentCostProject": 700 } }
-
Endpoint:
- The API should return a response similar to the following:
-
Response Code:
204
- Example Response Body:
{ "statusCode": 204, "primaryKeyName": "budgetItemId", "primaryKeyValue": 8001, "sourceId": "1" }
-
Response Code: