Update an Integrated Project Actual Line Item

To update an integrated project actual line item:

  1. Create or generate a JSON object containing the following fields, including any additional fields you want to update:
    • sourceId:The unique identifier of project actual line item data in an external source, such as an ERP system.
  2. Send a request to the API using the following information:
    • Endpoint: https://localhost:7001/api/restapi/project/projectActualsLineItem/sync
    • Operation: POST
    • Example Request Body:
    { 
                  "sourceId": 1, 
                  "projectActualsLineItemCost": { 
                      "total": 200, 
                      "totalProject": 200, 
                      "totalProjectActuals": 200 
                  } 
          }
    		
  3. The API should return a response similar to the following:
    • Response Code: 204
    • Example Response Body:
    { 
                  "statusCode": 204, 
                  "primaryKeyName": "lineItemId", 
                  "primaryKeyValue": 2, 
                  "sourceId": "1" 
          }