23.11

The following are no longer supported by the API as of 23.11.

Deprecated

Fields

Field Name Replacement Field Name (if any) ApiEntity Name Tag Name Comment
actualThisPeriodTotalCost   ApiEntityActivityFinancialInput Activity  
actualThisPeriodTotalCostProject   ApiEntityActivityFinancialInput Activity  
actualTotalCost   ApiEntityActivityFinancialInput Activity  
actualTotalCostProject   ApiEntityActivityFinancialInput Activity  
atCompletionTotalCost   ApiEntityActivityFinancialInput Activity  
atCompletionTotalCostProject   ApiEntityActivityFinancialInput Activity  
atCompletionVariance   ApiEntityActivityFinancialInput Activity  
atCompletionVarianceProject   ApiEntityActivityFinancialInput Activity  
budgetAtCompletion   ApiEntityActivityFinancialInput Activity  
budgetAtCompletionProject   ApiEntityActivityFinancialInput Activity  
earnedValueCost   ApiEntityActivityFinancialInput Activity  
earnedValueCostProject   ApiEntityActivityFinancialInput Activity  
estimateAtCompletionCost   ApiEntityActivityFinancialInput Activity  
estimateAtCompletionCostProject   ApiEntityActivityFinancialInput Activity  
estimateToCompletionCost   ApiEntityActivityFinancialInput Activity  
estimateToCompletionCostProject   ApiEntityActivityFinancialInput Activity  
laborCostVariance   ApiEntityActivityFinancialInput Activity  
link   ApiEntityActivityFinancialInput Activity  
materialCostVariance   ApiEntityActivityFinancialInput Activity  
nonLaborCostVariance   ApiEntityActivityFinancialInput Activity  
plannedTotalCost   ApiEntityActivityFinancialInput Activity  
plannedTotalCostProject   ApiEntityActivityFinancialInput Activity  
plannedValueCost   ApiEntityActivityFinancialInput Activity  
plannedValueCostProject   ApiEntityActivityFinancialInput Activity  
priorActualLaborCost   ApiEntityActivityFinancialInput Activity  
priorActualLaborCostProject   ApiEntityActivityFinancialInput Activity  
priorActualMaterialCost   ApiEntityActivityFinancialInput Activity  
priorActualMaterialCostProject   ApiEntityActivityFinancialInput Activity  
priorActualNonLaborCost   ApiEntityActivityFinancialInput Activity  
priorActualNonLaborCostProject   ApiEntityActivityFinancialInput Activity  
priorActualTotalCost   ApiEntityActivityFinancialInput Activity  
priorActualTotalCostProject   ApiEntityActivityFinancialInput Activity  
project   ApiEntityActivityFinancialInput Activity  
remainingTotalCost   ApiEntityActivityFinancialInput Activity  
remainingTotalCostProject   ApiEntityActivityFinancialInput Activity  
scheduleVariance   ApiEntityActivityFinancialInput Activity  
scheduleVarianceProject   ApiEntityActivityFinancialInput Activity  
totalCostVariance   ApiEntityActivityFinancialInput Activity  
updateDate   ApiEntityActivityFinancialInput Activity  
varCost   ApiEntityActivityFinancialInput Activity  
varCostProject   ApiEntityActivityFinancialInput Activity  
activityWorkManagerTaskDateStatus   ApiEntityActivityInput Activity  
activityWorkManagerTaskStatus   ApiEntityActivityInput Activity  
activityWorkManagerTaskStatusIndicator   ApiEntityActivityInput Activity  
actualDuration   ApiEntityActivityInput Activity  
atCompletionBudgetLaborUnits   ApiEntityActivityInput Activity  
completedWeight   ApiEntityActivityInput Activity  
costPerformanceIndex   ApiEntityActivityInput Activity  
costPerformanceIndexLaborUnits   ApiEntityActivityInput Activity  
costVarianceIndex   ApiEntityActivityInput Activity  
costVarianceLaborUnits   ApiEntityActivityInput Activity  
costVarianceLaborUnitsIndex   ApiEntityActivityInput Activity  
critical   ApiEntityActivityInput Activity  
currentBaselineFields   ApiEntityActivityInput Activity  
danglingFinish   ApiEntityActivityInput Activity  
danglingStart   ApiEntityActivityInput Activity  
drivingPath   ApiEntityActivityInput Activity  
durationPercentComplete   ApiEntityActivityInput Activity  
durationPercentOfPlanned   ApiEntityActivityInput Activity  
earnedValueLaborUnits   ApiEntityActivityInput Activity  
estimateAtCompletionLaborUnits   ApiEntityActivityInput Activity  
estimateToCompletionLaborUnits   ApiEntityActivityInput Activity  
ffPredecessor   ApiEntityActivityInput Activity  
freeFloat   ApiEntityActivityInput Activity  
fsPredecessor   ApiEntityActivityInput Activity  
hardConstraint   ApiEntityActivityInput Activity  
invalidProgressDate   ApiEntityActivityInput Activity  
laborUnitsCompletePercent   ApiEntityActivityInput Activity  
largeDuration   ApiEntityActivityInput Activity  
largeFloat   ApiEntityActivityInput Activity  
lateActivity   ApiEntityActivityInput Activity  
link (url)   ApiEntityActivityInput Activity  
negativeFloat   ApiEntityActivityInput Activity  
nonLaborUnitsCompletePercent   ApiEntityActivityInput Activity  
noPredecessor   ApiEntityActivityInput Activity  
noResource   ApiEntityActivityInput Activity  
noSuccessor   ApiEntityActivityInput Activity  
openEnds   ApiEntityActivityInput Activity  
originalBaselineFields   ApiEntityActivityInput Activity  
otherBaselineFields   ApiEntityActivityInput Activity  
performancePercentComplete   ApiEntityActivityInput Activity  
plannedValueLaborUnits   ApiEntityActivityInput Activity  
predecessorLag   ApiEntityActivityInput Activity  
predecessorNegativeLag   ApiEntityActivityInput Activity  
primaryResource   ApiEntityActivityInput Activity  
priorActualLaborUnits   ApiEntityActivityInput Activity  
priorActualNonLaborUnits   ApiEntityActivityInput Activity  
recordCount   ApiEntityActivityInput Activity  
remainingFloat   ApiEntityActivityInput Activity  
resourceCodeList   ApiEntityActivityInput Activity  
resourceNameList   ApiEntityActivityInput Activity  
roleCodeList   ApiEntityActivityInput Activity  
roleNameList   ApiEntityActivityInput Activity  
schedulePercentComplete   ApiEntityActivityInput Activity  
schedulePerfIndexLaborUnits   ApiEntityActivityInput Activity  
schedulePerformanceIndex   ApiEntityActivityInput Activity  
scheduleVarianceIndex   ApiEntityActivityInput Activity  
scheduleVarianceLaborUnits   ApiEntityActivityInput Activity  
scheduleVarIndexLaborUnits   ApiEntityActivityInput Activity  
scopePercentComplete   ApiEntityActivityInput Activity  
sfPredecessor   ApiEntityActivityInput Activity  
softConstraint   ApiEntityActivityInput Activity  
ssPredecessor   ApiEntityActivityInput Activity  
starred   ApiEntityActivityInput Activity  
toCompletePerformanceIndex   ApiEntityActivityInput Activity  
totalFloat   ApiEntityActivityInput Activity  
unitsPercentComplete   ApiEntityActivityInput Activity  
updateDate   ApiEntityActivityInput Activity  
userBaseline1Fields   ApiEntityActivityInput Activity  
userBaseline2Fields   ApiEntityActivityInput Activity  
userBaseline3Fields   ApiEntityActivityInput Activity  
varDuration   ApiEntityActivityInput Activity  
varFinishDate   ApiEntityActivityInput Activity  
varianceAtCompletionLaborUnits   ApiEntityActivityInput Activity  
varLaborUnits   ApiEntityActivityInput Activity  
varNonLaborUnits   ApiEntityActivityInput Activity  
varStartDate   ApiEntityActivityInput Activity  
weight   ApiEntityActivityInput Activity  
workManagerTaskCount   ApiEntityActivityInput Activity  
workManagerTaskPlannedCompleteCount   ApiEntityActivityInput Activity  
workManagerTaskPlannedNotCompleteCount   ApiEntityActivityInput Activity  
workManagerTaskPlannedOutsideCount   ApiEntityActivityInput Activity  
workManagerTaskUnplannedCount   ApiEntityActivityInput Activity  
activity(required)   ApiEntityActivityUncertaintyInput Activity  
link   ApiEntityActivityUncertaintyInput Activity  
project   ApiEntityActivityUncertaintyInput Activity  
updateDate   ApiEntityActivityUncertaintyInput Activity  
activityId   ApiEntityCodeValueActivityInput Activity  
link   ApiEntityCodeValueActivityInput Activity  
parentId   ApiEntityCodeValueActivityInput Activity  
projectCode   ApiEntityCodeValueActivityInput Activity  
projectId   ApiEntityCodeValueActivityInput Activity  
sequenceNumber   ApiEntityCodeValueActivityInput Activity  
updateDate   ApiEntityCodeValueActivityInput Activity  
activityId   ApiEntityConfiguredFieldValueInput Activity  
costValue: number   ApiEntityConfiguredFieldValueInput Activity  
costValueWorkspace1   ApiEntityConfiguredFieldValueInput Activity  
costValueWorkspace2   ApiEntityConfiguredFieldValueInput Activity  
costValueWorkspace3   ApiEntityConfiguredFieldValueInput Activity  
exceptionMessage   ApiEntityConfiguredFieldValueInput Activity  
hasException   ApiEntityConfiguredFieldValueInput Activity  
link   ApiEntityConfiguredFieldValueInput Activity  
updateDate   ApiEntityConfiguredFieldValueInput Activity  
link   ApiEntityBaselineInput Baseline  
updateDate   ApiEntityBaselineInput Baseline  
copiedFromItem   ApiEntityCBSSheetCodeInput CBS  
sequenceNumber   ApiEntityCBSSheetCodeInput CBS  
isCodeCopied   ApiEntityCBSTemplateCodeInput CBS  
isTotalRow   ApiEntityCBSTemplateCodeInput CBS  
link   ApiEntityCBSTemplateCodeInput CBS  
sequenceNumber   ApiEntityCBSTemplateCodeInput CBS  
templateRowCost   ApiEntityCBSTemplateCodeInput CBS  
updateDate   ApiEntityCBSTemplateCodeInput CBS  
columnName   ApiEntityCBSTemplateRowConfiguredFieldValueInput CBS  
costValue   ApiEntityCBSTemplateRowConfiguredFieldValueInput CBS  
costValueWorkspace1   ApiEntityCBSTemplateRowConfiguredFieldValueInput CBS  
costValueWorkspace2   ApiEntityCBSTemplateRowConfiguredFieldValueInput CBS  
costValueWorkspace3   ApiEntityCBSTemplateRowConfiguredFieldValueInput CBS  
exceptionMessage   ApiEntityCBSTemplateRowConfiguredFieldValueInput CBS  
hasException   ApiEntityCBSTemplateRowConfiguredFieldValueInput CBS  
link   ApiEntityCBSTemplateRowConfiguredFieldValueInput CBS  
updateDate   ApiEntityCBSTemplateRowConfiguredFieldValueInput CBS  
actualHoursToDate   ApiEntityCBSTemplateRowInput CBS  
approvedChangedHours   ApiEntityCBSTemplateRowInput CBS  
atCompletionHours   ApiEntityCBSTemplateRowInput CBS  
bacHours   ApiEntityCBSTemplateRowInput CBS  
baselineHours   ApiEntityCBSTemplateRowInput CBS  
cbsTemplateCodeId   ApiEntityCBSTemplateRowInput CBS  
eacHours   ApiEntityCBSTemplateRowInput CBS  
earnedHours   ApiEntityCBSTemplateRowInput CBS  
etcAdjustedHours   ApiEntityCBSTemplateRowInput CBS  
etcHours   ApiEntityCBSTemplateRowInput CBS  
installedHours   ApiEntityCBSTemplateRowInput CBS  
link   ApiEntityCBSTemplateRowInput CBS  
pendingChangedHours   ApiEntityCBSTemplateRowInput CBS  
plannedHours   ApiEntityCBSTemplateRowInput CBS  
projectActualHours   ApiEntityCBSTemplateRowInput CBS  
projectEarnedHours   ApiEntityCBSTemplateRowInput CBS  
projectHPI   ApiEntityCBSTemplateRowInput CBS  
remainingHours   ApiEntityCBSTemplateRowInput CBS  
revisedHours   ApiEntityCBSTemplateRowInput CBS  
templateItemId   ApiEntityCBSTemplateRowInput CBS  
updateDate   ApiEntityCBSTemplateRowInput CBS  
copiedFromItem   ApiEntityExternallySourcedCBSSheetCodeInput CBS  
sequenceNumber   ApiEntityExternallySourcedCBSSheetCodeInput CBS  
link   ApiEntityCBSSheetSegmentInput CBS Segment  
updateDate   ApiEntityCBSSheetSegmentInput CBS Segment  
link   ApiEntityCBSTemplateSegmentInput CBS Segment  
updateDate   ApiEntityCBSTemplateSegmentInput CBS Segment  
createDate   ApiEntityCodeValueDocumentInput Document  
createUser   ApiEntityCodeValueDocumentInput Document  
link   ApiEntityCodeValueDocumentInput Document  
sequenceNumber   ApiEntityCodeValueDocumentInput Document  
updateDate   ApiEntityCodeValueDocumentInput Document  
updateUser   ApiEntityCodeValueDocumentInput Document  
costValue   ApiEntityDocumentConfiguredFieldValueInput Document  
costValueWorkspace1   ApiEntityDocumentConfiguredFieldValueInput Document  
costValueWorkspace2   ApiEntityDocumentConfiguredFieldValueInput Document  
costValueWorkspace3   ApiEntityDocumentConfiguredFieldValueInput Document  
createDate   ApiEntityDocumentConfiguredFieldValueInput Document  
createUser   ApiEntityDocumentConfiguredFieldValueInput Document  
documentId   ApiEntityDocumentConfiguredFieldValueInput Document  
link   ApiEntityDocumentConfiguredFieldValueInput Document  
updateDate   ApiEntityDocumentConfiguredFieldValueInput Document  
updateUser   ApiEntityDocumentConfiguredFieldValueInput Document  
annotationCount   ApiEntityDocumentInput Document  
author   ApiEntityDocumentInput Document  
checkedOut   ApiEntityDocumentInput Document  
checkedOutBy   ApiEntityDocumentInput Document  
checkedOutDate   ApiEntityDocumentInput Document  
checkedOutUserId   ApiEntityDocumentInput Document  
createDate   ApiEntityDocumentInput Document  
createUser   ApiEntityDocumentInput Document  
hasChildren   ApiEntityDocumentInput Document  
isActualRoot   ApiEntityDocumentInput Document  
link   ApiEntityDocumentInput Document  
mimeType   ApiEntityDocumentInput Document  
parentType   ApiEntityDocumentInput Document  
scanStatus   ApiEntityDocumentInput Document  
size   ApiEntityDocumentInput Document  
type   ApiEntityDocumentInput Document  
updateDate   ApiEntityDocumentInput Document  
updateUser   ApiEntityDocumentInput Document  
url   ApiEntityDocumentInput Document  
version   ApiEntityDocumentInput Document  
link   ApiEntityCodeValueProgramInput Program  
updateDate   ApiEntityCodeValueProgramInput Program  
columnName   ApiEntityProgramConfiguredFieldValueInput Program  
costValue   ApiEntityProgramConfiguredFieldValueInput Program  
costValueWorkspace1   ApiEntityProgramConfiguredFieldValueInput Program  
costValueWorkspace2   ApiEntityProgramConfiguredFieldValueInput Program  
costValueWorkspace3   ApiEntityProgramConfiguredFieldValueInput Program  
exceptionMessage   ApiEntityProgramConfiguredFieldValueInput Program  
hasException   ApiEntityProgramConfiguredFieldValueInput Program  
link   ApiEntityProgramConfiguredFieldValueInput Program  
updateDate   ApiEntityProgramConfiguredFieldValueInput Program  
actualCapitalCostDistributed   ApiEntityProgramFinancialAndSettingInput Program  
actualCapitalCostDistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
actualCapitalCostDistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
actualCapitalCostDistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
actualCapitalCostPresentValueWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
actualCapitalCostPresentValueWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
actualCapitalCostPresentValueWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
actualCapitalCostUndistributed   ApiEntityProgramFinancialAndSettingInput Program  
actualCapitalCostUndistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
actualCapitalCostUndistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
actualCapitalCostUndistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
actualCostDistributed   ApiEntityProgramFinancialAndSettingInput Program  
actualCostDistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
actualCostDistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
actualCostDistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
actualCostPresentValue   ApiEntityProgramFinancialAndSettingInput Program  
actualCostPresentValueWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
actualCostPresentValueWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
actualCostPresentValueWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
actualCostUndistributed   ApiEntityProgramFinancialAndSettingInput Program  
actualCostUndistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
actualCostUndistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
actualCostUndistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
actualExpenseCostDistributed   ApiEntityProgramFinancialAndSettingInput Program  
actualExpenseCostDistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
actualExpenseCostDistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
actualExpenseCostDistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
actualExpenseCostPresentValueWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
actualExpenseCostPresentValueWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
actualExpenseCostPresentValueWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
actualExpenseCostUndistributed   ApiEntityProgramFinancialAndSettingInput Program  
actualExpenseCostUndistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
actualExpenseCostUndistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
actualExpenseCostUndistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
benefitsDistributed   ApiEntityProgramFinancialAndSettingInput Program  
benefitsDistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
benefitsDistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
benefitsDistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
benefitsOutOfSync   ApiEntityProgramFinancialAndSettingInput Program  
benefitsPresentValue   ApiEntityProgramFinancialAndSettingInput Program  
benefitsPresentValueWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
benefitsPresentValueWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
benefitsPresentValueWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
benefitsUndistributed   ApiEntityProgramFinancialAndSettingInput Program  
benefitsUndistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
benefitsUndistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
benefitsUndistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
benefitsWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
benefitsWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
benefitsWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
costVarianceWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
costVarianceWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
costVarianceWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
earnedValueCostWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
earnedValueCostWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
earnedValueCostWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
estAtCompleteCostWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
estAtCompleteCostWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
estAtCompleteCostWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
estToCompleteCostWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
estToCompleteCostWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
estToCompleteCostWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
forecastCapitalCostDistributed   ApiEntityProgramFinancialAndSettingInput Program  
forecastCapitalCostDistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
forecastCapitalCostDistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
forecastCapitalCostPresentValueWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
forecastCapitalCostPresentValueWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
forecastCapitalCostPresentValueWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
forecastCapitalCostUndistributed   ApiEntityProgramFinancialAndSettingInput Program  
forecastCapitalCostUndistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
forecastCapitalCostUndistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
forecastCapitalCostUndistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
forecastCapitalCostWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
forecastCapitalCostWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
forecastCapitalCostWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
forecastCostDistributed   ApiEntityProgramFinancialAndSettingInput Program  
forecastCostDistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
forecastCostDistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
forecastCostDistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
forecastCostPresentValue   ApiEntityProgramFinancialAndSettingInput Program  
forecastCostPresentValueWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
forecastCostPresentValueWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
forecastCostPresentValueWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
forecastCostUndistributed   ApiEntityProgramFinancialAndSettingInput Program  
forecastCostUndistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
forecastCostUndistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
forecastCostUndistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
forecastCostWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
forecastCostWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
forecastCostWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
forecastExpenseCostDistributed   ApiEntityProgramFinancialAndSettingInput Program  
forecastExpenseCostDistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
forecastExpenseCostDistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
forecastExpenseCostDistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
forecastExpenseCostPresentValueWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
forecastExpenseCostPresentValueWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
forecastExpenseCostPresentValueWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
forecastExpenseCostUndistributed   ApiEntityProgramFinancialAndSettingInput Program  
forecastExpenseCostUndistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
forecastExpenseCostUndistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
forecastExpenseCostUndistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
forecastExpenseCostWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
forecastExpenseCostWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
forecastExpenseCostWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
forecastOutOfSync   ApiEntityProgramFinancialAndSettingInput Program  
netPresentValueWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
netPresentValueWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
netPresentValueWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetCapitalDistributed   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetCapitalDistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetCapitalDistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetCapitalDistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetCapitalPresentValueWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetCapitalPresentValueWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetCapitalPresentValueWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetCapitalUndistributed   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetCapitalUndistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetCapitalUndistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetCapitalUndistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetCapitalWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetCapitalWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetCapitalWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetDistributed   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetDistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetDistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetDistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetExpenseDistributed   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetExpenseDistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetExpenseDistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetExpenseDistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetExpensePresentValueWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetExpensePresentValueWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetExpensePresentValueWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetExpenseUndistributed   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetExpenseUndistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetExpenseUndistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetExpenseUndistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetExpenseWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetExpenseWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetExpenseWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetOutOfSync   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetPresentValue   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetPresentValueWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetPresentValueWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetPresentValueWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetUndistributed   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetUndistributedWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetUndistributedWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetUndistributedWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
plannedBudgetWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
plannedValueCostWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
plannedValueCostWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
plannedValueCostWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
scheduleVarianceWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
scheduleVarianceWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
scheduleVarianceWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
spendCapitalCostWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
spendCapitalCostWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
spendCapitalCostWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
spendCostWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
spendCostWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
spendCostWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
spendExpenseCostWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
spendExpenseCostWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
spendExpenseCostWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
spendForecastVar   ApiEntityProgramFinancialAndSettingInput Program  
spendForecastVarWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
spendForecastVarWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
spendForecastVarWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
spendPlannedVariance   ApiEntityProgramFinancialAndSettingInput Program  
spendPlannedVarianceWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
spendPlannedVarianceWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
spendPlannedVarianceWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
spendsOutOfSync   ApiEntityProgramFinancialAndSettingInput Program  
updateDate   ApiEntityProgramFinancialAndSettingInput Program  
yearEndForecastCost   ApiEntityProgramFinancialAndSettingInput Program  
yearEndForecastCostWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
yearEndForecastCostWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
yearEndForecastCostWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
ytdSpendCost   ApiEntityProgramFinancialAndSettingInput Program  
ytdSpendCostWorkspace1   ApiEntityProgramFinancialAndSettingInput Program  
ytdSpendCostWorkspace2   ApiEntityProgramFinancialAndSettingInput Program  
ytdSpendCostWorkspace3   ApiEntityProgramFinancialAndSettingInput Program  
link   ApiEntityProgramFinancialAndSettingInput Program  
actualCapitalCostDistributed   ApiEntityProgramFinancialInput Program  
actualCapitalCostPresentValue   ApiEntityProgramFinancialInput Program  
actualCapitalCostUndistributed   ApiEntityProgramFinancialInput Program  
actualCostDistributed   ApiEntityProgramFinancialInput Program  
actualCostPresentValue   ApiEntityProgramFinancialInput Program  
actualCostUndistributed   ApiEntityProgramFinancialInput Program  
actualExpenseCostDistributed   ApiEntityProgramFinancialInput Program  
actualExpenseCostPresentValue   ApiEntityProgramFinancialInput Program  
actualExpenseCostUndistributed   ApiEntityProgramFinancialInput Program  
benefits   ApiEntityProgramFinancialInput Program  
benefitsDistributed   ApiEntityProgramFinancialInput Program  
benefitsOutOfSync   ApiEntityProgramFinancialInput Program  
benefitsPresentValue   ApiEntityProgramFinancialInput Program  
benefitsUndistributed   ApiEntityProgramFinancialInput Program  
costVariance   ApiEntityProgramFinancialInput Program  
earnedValueCost   ApiEntityProgramFinancialInput Program  
estAtCompleteCost   ApiEntityProgramFinancialInput Program  
estToCompleteCost   ApiEntityProgramFinancialInput Program  
forecastCapitalCost   ApiEntityProgramFinancialInput Program  
forecastCapitalCostDistributed   ApiEntityProgramFinancialInput Program  
forecastCapitalCostPresentValue   ApiEntityProgramFinancialInput Program  
forecastCapitalCostUndistributed   ApiEntityProgramFinancialInput Program  
forecastCost   ApiEntityProgramFinancialInput Program  
forecastCostDistributed   ApiEntityProgramFinancialInput Program  
forecastCostPresentValue   ApiEntityProgramFinancialInput Program  
forecastCostUndistributed   ApiEntityProgramFinancialInput Program  
forecastExpenseCost   ApiEntityProgramFinancialInput Program  
forecastExpenseCostDistributed   ApiEntityProgramFinancialInput Program  
forecastExpenseCostPresentValue   ApiEntityProgramFinancialInput Program  
forecastExpenseCostUndistributed   ApiEntityProgramFinancialInput Program  
forecastOutOfSync   ApiEntityProgramFinancialInput Program  
link   ApiEntityProgramFinancialInput Program  
netPresentValue   ApiEntityProgramFinancialInput Program  
plannedBudget   ApiEntityProgramFinancialInput Program  
plannedBudgetCapital   ApiEntityProgramFinancialInput Program  
plannedBudgetCapitalDistributed   ApiEntityProgramFinancialInput Program  
plannedBudgetCapitalPresentValue   ApiEntityProgramFinancialInput Program  
plannedBudgetCapitalUndistributed   ApiEntityProgramFinancialInput Program  
plannedBudgetDistributed   ApiEntityProgramFinancialInput Program  
plannedBudgetExpense   ApiEntityProgramFinancialInput Program  
plannedBudgetExpenseDistributed   ApiEntityProgramFinancialInput Program  
plannedBudgetExpensePresentValue   ApiEntityProgramFinancialInput Program  
plannedBudgetExpenseUndistributed   ApiEntityProgramFinancialInput Program  
plannedBudgetOutOfSync   ApiEntityProgramFinancialInput Program  
plannedBudgetPresentValue   ApiEntityProgramFinancialInput Program  
plannedBudgetUndistributed   ApiEntityProgramFinancialInput Program  
plannedValueCost   ApiEntityProgramFinancialInput Program  
programId   ApiEntityProgramFinancialInput Program  
scheduleVariance   ApiEntityProgramFinancialInput Program  
spendCapitalCost   ApiEntityProgramFinancialInput Program  
spendCost   ApiEntityProgramFinancialInput Program  
spendExpenseCost   ApiEntityProgramFinancialInput Program  
spendForecastVar   ApiEntityProgramFinancialInput Program  
spendPlannedVariance   ApiEntityProgramFinancialInput Program  
spendsOutOfSync   ApiEntityProgramFinancialInput Program  
updateDate   ApiEntityProgramFinancialInput Program  
yearEndForecastCost   ApiEntityProgramFinancialInput Program  
ytdSpendCost   ApiEntityProgramFinancialInput Program  
createDate   ApiEntityProgramInput Program  
createUser   ApiEntityProgramInput Program  
evaluationMatrixId   ApiEntityProgramInput Program  
evaluationScore   ApiEntityProgramInput Program  
lastProgramEvaluationDate   ApiEntityProgramInput Program  
link   ApiEntityProgramInput Program  
statusDate   ApiEntityProgramInput Program  
updateDate   ApiEntityProgramInput Program  
updateUser   ApiEntityProgramInput Program  
link   ApiEntityProgramLinkedObjectInput Program  
updateDate   ApiEntityProgramLinkedObjectInput Program  
benefits   ApiEntityProgramPhaseFinancialInput Program  
forecastCapitalCost   ApiEntityProgramPhaseFinancialInput Program  
forecastCost   ApiEntityProgramPhaseFinancialInput Program  
forecastExpenseCost   ApiEntityProgramPhaseFinancialInput Program  
link   ApiEntityProgramPhaseFinancialInput Program  
plannedBudget   ApiEntityProgramPhaseFinancialInput Program  
plannedBudgetCapital   ApiEntityProgramPhaseFinancialInput Program  
plannedBudgetExpense   ApiEntityProgramPhaseFinancialInput Program  
programId   ApiEntityProgramPhaseFinancialInput Program  
spendCapitalCost   ApiEntityProgramPhaseFinancialInput Program  
spendCost   ApiEntityProgramPhaseFinancialInput Program  
spendExpenseCost   ApiEntityProgramPhaseFinancialInput Program  
spendForecastVar   ApiEntityProgramPhaseFinancialInput Program  
spendPlannedVariance   ApiEntityProgramPhaseFinancialInput Program  
updateDate   ApiEntityProgramPhaseFinancialInput Program  
yearEndForecastCost   ApiEntityProgramPhaseFinancialInput Program  
ytdSpendCost   ApiEntityProgramPhaseFinancialInput Program  
link   ApiEntityProgramSettingsInput Program  
updateDate   ApiEntityProgramSettingsInput Program  
approveByUserId   ApiEntityProgramBudgetInput Program Budget  
approveByUserName   ApiEntityProgramBudgetInput Program Budget  
approveDate   ApiEntityProgramBudgetInput Program Budget  
budgetStatus   ApiEntityProgramBudgetInput Program Budget  
lastModifiedById   ApiEntityProgramBudgetInput Program Budget  
programBudgetId   ApiEntityProgramBudgetInput Program Budget  
rejectByUserId   ApiEntityProgramBudgetInput Program Budget  
rejectByUserName   ApiEntityProgramBudgetInput Program Budget  
rejectDate   ApiEntityProgramBudgetInput Program Budget  
submitByUserId   ApiEntityProgramBudgetInput Program Budget  
submitByUserName   ApiEntityProgramBudgetInput Program Budget  
submitDate   ApiEntityProgramBudgetInput Program Budget  
withdrawApprovalByUserId   ApiEntityProgramBudgetInput Program Budget  
withdrawApprovalByUserName   ApiEntityProgramBudgetInput Program Budget  
withdrawApprovalDate   ApiEntityProgramBudgetInput Program Budget  
columnName   ApiEntityProgramBudgetChangeConfiguredFieldValueInput Program Budget Change  
costValue   ApiEntityProgramBudgetChangeConfiguredFieldValueInput Program Budget Change  
costValueWorkspace1   ApiEntityProgramBudgetChangeConfiguredFieldValueInput Program Budget Change  
costValueWorkspace2   ApiEntityProgramBudgetChangeConfiguredFieldValueInput Program Budget Change  
costValueWorkspace3   ApiEntityProgramBudgetChangeConfiguredFieldValueInput Program Budget Change  
exceptionMessage   ApiEntityProgramBudgetChangeConfiguredFieldValueInput Program Budget Change  
hasException   ApiEntityProgramBudgetChangeConfiguredFieldValueInput Program Budget Change  
link   ApiEntityProgramBudgetChangeConfiguredFieldValueInput Program Budget Change  
programBudgetChangeId   ApiEntityProgramBudgetChangeConfiguredFieldValueInput Program Budget Change  
updateDate   ApiEntityProgramBudgetChangeConfiguredFieldValueInput Program Budget Change  
columnName   ApiEntityProgramBudgetTransactionConfiguredFieldValueInput Program Budget Change, Program Budget Transfer  
costValue   ApiEntityProgramBudgetTransactionConfiguredFieldValueInput Program Budget Change, Program Budget Transfer  
costValueWorkspace1   ApiEntityProgramBudgetTransactionConfiguredFieldValueInput Program Budget Change, Program Budget Transfer  
costValueWorkspace2   ApiEntityProgramBudgetTransactionConfiguredFieldValueInput Program Budget Change, Program Budget Transfer  
costValueWorkspace3   ApiEntityProgramBudgetTransactionConfiguredFieldValueInput Program Budget Change, Program Budget Transfer  
exceptionMessage   ApiEntityProgramBudgetTransactionConfiguredFieldValueInput Program Budget Change, Program Budget Transfer  
hasException   ApiEntityProgramBudgetTransactionConfiguredFieldValueInput Program Budget Change, Program Budget Transfer  
link   ApiEntityProgramBudgetTransactionConfiguredFieldValueInput Program Budget Change, Program Budget Transfer  
programBudgetTransactionId   ApiEntityProgramBudgetTransactionConfiguredFieldValueInput Program Budget Change, Program Budget Transfer  
updateDate   ApiEntityProgramBudgetTransactionConfiguredFieldValueInput Program Budget Change, Program Budget Transfer  
columnName   ApiEntityProgramBudgetItemConfiguredFieldValueInput Program Budget Item  
costValue   ApiEntityProgramBudgetItemConfiguredFieldValueInput Program Budget Item  
costValueWorkspace1   ApiEntityProgramBudgetItemConfiguredFieldValueInput Program Budget Item  
costValueWorkspace2   ApiEntityProgramBudgetItemConfiguredFieldValueInput Program Budget Item  
costValueWorkspace3   ApiEntityProgramBudgetItemConfiguredFieldValueInput Program Budget Item  
hasException   ApiEntityProgramBudgetItemConfiguredFieldValueInput Program Budget Item  
link   ApiEntityProgramBudgetItemConfiguredFieldValueInput Program Budget Item  
programBudgetItemId   ApiEntityProgramBudgetItemConfiguredFieldValueInput Program Budget Item  
updateDate   ApiEntityProgramBudgetItemConfiguredFieldValueInput Program Budget Item  
exceptionMessage   ApiEntityScopeItemAssignmentConfiguredFieldValueInput Program Budget Item  
columnName   ApiEntityProgramBudgetTransferConfiguredFieldValueInput Program Budget Transfer  
costValue   ApiEntityProgramBudgetTransferConfiguredFieldValueInput Program Budget Transfer  
costValueWorkspace1   ApiEntityProgramBudgetTransferConfiguredFieldValueInput Program Budget Transfer  
costValueWorkspace2   ApiEntityProgramBudgetTransferConfiguredFieldValueInput Program Budget Transfer  
costValueWorkspace3   ApiEntityProgramBudgetTransferConfiguredFieldValueInput Program Budget Transfer  
exceptionMessage   ApiEntityProgramBudgetTransferConfiguredFieldValueInput Program Budget Transfer  
hasException   ApiEntityProgramBudgetTransferConfiguredFieldValueInput Program Budget Transfer  
link   ApiEntityProgramBudgetTransferConfiguredFieldValueInput Program Budget Transfer  
programBudgetTransferId   ApiEntityProgramBudgetTransferConfiguredFieldValueInput Program Budget Transfer  
updateDate   ApiEntityProgramBudgetTransferConfiguredFieldValueInput Program Budget Transfer  
programBudgetItemName   ApiEntityProgramBudgetTransferTransactionInput Program Budget Transfer  
transferFromCBSId   ApiEntityProgramBudgetTransferTransactionInput Program Budget Transfer  
transferFromCostCategoryId   ApiEntityProgramBudgetTransferTransactionInput Program Budget Transfer  
transferToCBSId   ApiEntityProgramBudgetTransferTransactionInput Program Budget Transfer  
transferToCostCategoryId   ApiEntityProgramBudgetTransferTransactionInput Program Budget Transfer  
link   ApiEntityCodeValueProgramRiskInput Program Risk  
updateDate   ApiEntityCodeValueProgramRiskInput Program Risk  
costValue   ApiEntityProgramRiskConfiguredFieldValueInput Program Risk  
costValueWorkspace1   ApiEntityProgramRiskConfiguredFieldValueInput Program Risk  
costValueWorkspace2   ApiEntityProgramRiskConfiguredFieldValueInput Program Risk  
costValueWorkspace3   ApiEntityProgramRiskConfiguredFieldValueInput Program Risk  
exceptionMessage   ApiEntityProgramRiskConfiguredFieldValueInput Program Risk  
hasException   ApiEntityProgramRiskConfiguredFieldValueInput Program Risk  
link   ApiEntityProgramRiskConfiguredFieldValueInput Program Risk  
updateDate   ApiEntityProgramRiskConfiguredFieldValueInput Program Risk  
actualCostImpact   ApiEntityProgramRiskFinancialInput Program Risk  
actualResponseCostProject   ApiEntityProgramRiskFinancialInput Program Risk  
atCompletionTotalResponseCost   ApiEntityProgramRiskFinancialInput Program Risk  
link   ApiEntityProgramRiskFinancialInput Program Risk  
postActualResponseCost   ApiEntityProgramRiskFinancialInput Program Risk  
postAtCompletionTotalResponseCost   ApiEntityProgramRiskFinancialInput Program Risk  
postExposureCost   ApiEntityProgramRiskFinancialInput Program Risk  
postExposureCostProject   ApiEntityProgramRiskFinancialInput Program Risk  
postQuantifiedCostThreshold   ApiEntityProgramRiskFinancialInput Program Risk  
postRemainingTotalResponseCost   ApiEntityProgramRiskFinancialInput Program Risk  
postResponseExposureWorkspace1   ApiEntityProgramRiskFinancialInput Program Risk  
postResponseExposureWorkspace2   ApiEntityProgramRiskFinancialInput Program Risk  
postResponseExposureWorkspace3   ApiEntityProgramRiskFinancialInput Program Risk  
preActualResponseCost   ApiEntityProgramRiskFinancialInput Program Risk  
preAtCompletionTotalResponseCost   ApiEntityProgramRiskFinancialInput Program Risk  
preExposureCost   ApiEntityProgramRiskFinancialInput Program Risk  
preExposureCostProject   ApiEntityProgramRiskFinancialInput Program Risk  
preQuantifiedCostThreshold   ApiEntityProgramRiskFinancialInput Program Risk  
preRemainingTotalResponseCost   ApiEntityProgramRiskFinancialInput Program Risk  
preResponseExposureWorkspace1   ApiEntityProgramRiskFinancialInput Program Risk  
preResponseExposureWorkspace2   ApiEntityProgramRiskFinancialInput Program Risk  
preResponseExposureWorkspace3   ApiEntityProgramRiskFinancialInput Program Risk  
remainingTotalResponseCost   ApiEntityProgramRiskFinancialInput Program Risk  
updateDate   ApiEntityProgramRiskFinancialInput Program Risk  
link   ApiEntityProgramRiskImpactInput Program Risk  
riskCode   ApiEntityProgramRiskImpactInput Program Risk  
updateDate   ApiEntityProgramRiskImpactInput Program Risk  
workspaceCode   ApiEntityProgramRiskImpactInput Program Risk  
link   ApiEntityProgramRiskInput Program Risk  
postResponseMeanDelay   ApiEntityProgramRiskInput Program Risk  
postScore   ApiEntityProgramRiskInput Program Risk  
preResponseMeanDelay   ApiEntityProgramRiskInput Program Risk  
quantifiedPostResponseProbabilityThreshold   ApiEntityProgramRiskInput Program Risk  
quantifiedPostResponseScheduleThreshold   ApiEntityProgramRiskInput Program Risk  
quantifiedProbabilityThreshold   ApiEntityProgramRiskInput Program Risk  
quantifiedScheduleThreshold   ApiEntityProgramRiskInput Program Risk  
riskSourceType   ApiEntityProgramRiskInput Program Risk  
score   ApiEntityProgramRiskInput Program Risk  
updateDate   ApiEntityProgramRiskInput Program Risk  
link   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
postResponseMaximumProject   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
postResponseMaximumWorkspace1   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
postResponseMaximumWorkspace2   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
postResponseMaximumWorkspace3   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
postResponseMinimumProject   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
postResponseMinimumWorkspace1   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
postResponseMinimumWorkspace2   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
postResponseMinimumWorkspace3   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
postResponseMostLikelyProject   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
postResponseMostLikelyWorkspace1   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
postResponseMostLikelyWorkspace2   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
postResponseMostLikelyWorkspace3   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
preResponseMaximumProject   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
preResponseMaximumWorkspace1   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
preResponseMaximumWorkspace2   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
preResponseMaximumWorkspace3   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
preResponseMinimumProject   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
preResponseMinimumWorkspace1   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
preResponseMinimumWorkspace2   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
preResponseMinimumWorkspace3   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
preResponseMostLikelyProject   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
preResponseMostLikelyWorkspace1   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
preResponseMostLikelyWorkspace2   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
preResponseMostLikelyWorkspace3   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
updateDate   ApiEntityProgramRiskQuantifiedCostImpactInput Program Risk  
link   ApiEntityProgramRiskQuantifiedOtherImpactInput Program Risk  
updateDate   ApiEntityProgramRiskQuantifiedOtherImpactInput Program Risk  
atCompletionTotalCost   ApiEntityProgramRiskMitigationFinancialInput Program Risk Mitigation  
link   ApiEntityProgramRiskMitigationFinancialInput Program Risk Mitigation  
postResponseActualCost   ApiEntityProgramRiskMitigationFinancialInput Program Risk Mitigation  
postResponseAtCompletionTotalCost   ApiEntityProgramRiskMitigationFinancialInput Program Risk Mitigation  
postResponseRemainingTotalCost   ApiEntityProgramRiskMitigationFinancialInput Program Risk Mitigation  
preResponseActualCost   ApiEntityProgramRiskMitigationFinancialInput Program Risk Mitigation  
preResponseAtCompletionCost   ApiEntityProgramRiskMitigationFinancialInput Program Risk Mitigation  
preResponseRemainingTotalCost   ApiEntityProgramRiskMitigationFinancialInput Program Risk Mitigation  
updateDate   ApiEntityProgramRiskMitigationFinancialInput Program Risk Mitigation  
link   ApiEntityProgramRiskMitigationInput Program Risk Mitigation  
updateDate   ApiEntityProgramRiskMitigationInput Program Risk Mitigation  
columnName   ApiEntityBudgetChangeConfiguredFieldValueInput Project Budget Change  
costValue   ApiEntityBudgetChangeConfiguredFieldValueInput Project Budget Change  
costValueWorkspace1   ApiEntityBudgetChangeConfiguredFieldValueInput Project Budget Change  
costValueWorkspace2   ApiEntityBudgetChangeConfiguredFieldValueInput Project Budget Change  
costValueWorkspace3   ApiEntityBudgetChangeConfiguredFieldValueInput Project Budget Change  
exceptionMessage   ApiEntityBudgetChangeConfiguredFieldValueInput Project Budget Change  
hasException   ApiEntityBudgetChangeConfiguredFieldValueInput Project Budget Change  
link   ApiEntityBudgetChangeConfiguredFieldValueInput Project Budget Change  
updateDate   ApiEntityBudgetChangeConfiguredFieldValueInput Project Budget Change  
approveByUserId   ApiEntityBudgetChangeInput Project Budget Change  
approveByUserName   ApiEntityBudgetChangeInput Project Budget Change  
approveDate   ApiEntityBudgetChangeInput Project Budget Change  
budgetChangeCost   ApiEntityBudgetChangeInput Project Budget Change  
lastModifiedById   ApiEntityBudgetChangeInput Project Budget Change  
link   ApiEntityBudgetChangeInput Project Budget Change  
rejectByUserId   ApiEntityBudgetChangeInput Project Budget Change  
rejectByUserName   ApiEntityBudgetChangeInput Project Budget Change  
rejectDate   ApiEntityBudgetChangeInput Project Budget Change  
submitByUserId   ApiEntityBudgetChangeInput Project Budget Change  
submitByUserName   ApiEntityBudgetChangeInput Project Budget Change  
submitDate   ApiEntityBudgetChangeInput Project Budget Change  
updateDate   ApiEntityBudgetChangeInput Project Budget Change  
withdrawApprovalByUserId   ApiEntityBudgetChangeInput Project Budget Change  
withdrawApprovalByUserName   ApiEntityBudgetChangeInput Project Budget Change  
withdrawApprovalDate   ApiEntityBudgetChangeInput Project Budget Change  
approveDate   ApiEntityBudgetChangeTransactionInput Project Budget Change  
budgetHours   ApiEntityBudgetChangeTransactionInput Project Budget Change  
changeMode   ApiEntityBudgetChangeTransactionInput Project Budget Change  
itemCodeSuffix   ApiEntityBudgetChangeTransactionInput Project Budget Change  
transactionType   ApiEntityBudgetChangeTransactionInput Project Budget Change  
columnName   ApiEntityBudgetTransactionConfiguredFieldValueInput Project Budget Change, Project Budget Transfer  
costValue   ApiEntityBudgetTransactionConfiguredFieldValueInput Project Budget Change, Project Budget Transfer  
costValueWorkspace1   ApiEntityBudgetTransactionConfiguredFieldValueInput Project Budget Change, Project Budget Transfer  
costValueWorkspace2   ApiEntityBudgetTransactionConfiguredFieldValueInput Project Budget Change, Project Budget Transfer  
costValueWorkspace3   ApiEntityBudgetTransactionConfiguredFieldValueInput Project Budget Change, Project Budget Transfer  
exceptionMessage   ApiEntityBudgetTransactionConfiguredFieldValueInput Project Budget Change, Project Budget Transfer  
hasException   ApiEntityBudgetTransactionConfiguredFieldValueInput Project Budget Change, Project Budget Transfer  
link   ApiEntityBudgetTransactionConfiguredFieldValueInput Project Budget Change, Project Budget Transfer  
updateDate   ApiEntityBudgetTransactionConfiguredFieldValueInput Project Budget Change, Project Budget Transfer  
amountCost   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
amountCostWorkspace1   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
amountCostWorkspace2   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
amountCostWorkspace3   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
currentCost   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
currentCostProject   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
currentCostWorkspace1   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
currentCostWorkspace2   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
currentCostWorkspace3   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
laborRate   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
laborRateWorkspace1   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
laborRateWorkspace2   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
laborRateWorkspace3   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
link   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
unitRate   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
unitRateWorkspace1   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
unitRateWorkspace2   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
unitRateWorkspace3   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
updateDate   ApiEntityBudgetTransactionCostInput Project Budget Change, Project Budget Transfer  
columnName   ApiEntityBudgetItemConfiguredFieldValueInput Project Budget Item  
costValue   ApiEntityBudgetItemConfiguredFieldValueInput Project Budget Item  
costValueWorkspace1   ApiEntityBudgetItemConfiguredFieldValueInput Project Budget Item  
costValueWorkspace2   ApiEntityBudgetItemConfiguredFieldValueInput Project Budget Item  
costValueWorkspace3   ApiEntityBudgetItemConfiguredFieldValueInput Project Budget Item  
exceptionMessage   ApiEntityBudgetItemConfiguredFieldValueInput Project Budget Item  
hasException   ApiEntityBudgetItemConfiguredFieldValueInput Project Budget Item  
link   ApiEntityBudgetItemConfiguredFieldValueInput Project Budget Item  
updateDate   ApiEntityBudgetItemConfiguredFieldValueInput Project Budget Item  
currentCost   ApiEntityBudgetItemCostInput Project Budget Item  
currentCostProject   ApiEntityBudgetItemCostInput Project Budget Item  
currentCostWorkspace1   ApiEntityBudgetItemCostInput Project Budget Item  
currentCostWorkspace2   ApiEntityBudgetItemCostInput Project Budget Item  
currentCostWorkspace3   ApiEntityBudgetItemCostInput Project Budget Item  
laborRate   ApiEntityBudgetItemCostInput Project Budget Item  
laborRateWorkspace1   ApiEntityBudgetItemCostInput Project Budget Item  
laborRateWorkspace2   ApiEntityBudgetItemCostInput Project Budget Item  
laborRateWorkspace3   ApiEntityBudgetItemCostInput Project Budget Item  
link   ApiEntityBudgetItemCostInput Project Budget Item  
originalCost   ApiEntityBudgetItemCostInput Project Budget Item  
originalCostWorkspace1   ApiEntityBudgetItemCostInput Project Budget Item  
originalCostWorkspace2   ApiEntityBudgetItemCostInput Project Budget Item  
originalCostWorkspace3   ApiEntityBudgetItemCostInput Project Budget Item  
unitRate   ApiEntityBudgetItemCostInput Project Budget Item  
unitRateWorkspace1   ApiEntityBudgetItemCostInput Project Budget Item  
unitRateWorkspace2   ApiEntityBudgetItemCostInput Project Budget Item  
unitRateWorkspace3   ApiEntityBudgetItemCostInput Project Budget Item  
updateDate   ApiEntityBudgetItemCostInput Project Budget Item  
budgetChangeId   ApiEntityBudgetItemInput Project Budget Item  
budgetHours   ApiEntityBudgetItemInput Project Budget Item  
itemSuffix   ApiEntityBudgetItemInput Project Budget Item  
approveByUserId   ApiEntityBudgetTransferInput Project Budget Transfer  
approveByUserName   ApiEntityBudgetTransferInput Project Budget Transfer  
approveDate   ApiEntityBudgetTransferInput Project Budget Transfer  
itemPrefix   ApiEntityBudgetTransferInput Project Budget Transfer  
itemSuffix   ApiEntityBudgetTransferInput Project Budget Transfer  
lastModifiedById   ApiEntityBudgetTransferInput Project Budget Transfer  
link   ApiEntityBudgetTransferInput Project Budget Transfer  
rejectByUserId   ApiEntityBudgetTransferInput Project Budget Transfer  
rejectByUserName   ApiEntityBudgetTransferInput Project Budget Transfer  
rejectDate   ApiEntityBudgetTransferInput Project Budget Transfer  
submitByUserId   ApiEntityBudgetTransferInput Project Budget Transfer  
submitByUserName   ApiEntityBudgetTransferInput Project Budget Transfer  
submitDate   ApiEntityBudgetTransferInput Project Budget Transfer  
updateDate   ApiEntityBudgetTransferInput Project Budget Transfer  
withdrawApprovalByUserId   ApiEntityBudgetTransferInput Project Budget Transfer  
withdrawApprovalByUserName   ApiEntityBudgetTransferInput Project Budget Transfer  
withdrawApprovalDate   ApiEntityBudgetTransferInput Project Budget Transfer  
approveDate   ApiEntityBudgetTransferTransactionInput Project Budget Transfer  
budgetCbsSheetCodeId   ApiEntityBudgetTransferTransactionInput Project Budget Transfer  
budgetCostCategoryId   ApiEntityBudgetTransferTransactionInput Project Budget Transfer  
budgetHours   ApiEntityBudgetTransferTransactionInput Project Budget Transfer  
budgetItemName   ApiEntityBudgetTransferTransactionInput Project Budget Transfer  
itemCodeSuffix   ApiEntityBudgetTransferTransactionInput Project Budget Transfer  
transferFromCBSId   ApiEntityBudgetTransferTransactionInput Project Budget Transfer  
transferFromCostCategoryId   ApiEntityBudgetTransferTransactionInput Project Budget Transfer  
transferToCBSId   ApiEntityBudgetTransferTransactionInput Project Budget Transfer  
transferToCostCategoryId   ApiEntityBudgetTransferTransactionInput Project Budget Transfer  
link   ApiEntityProjectResourceWorkRateCostInput Project Resource Work Rate  
pricePerUnit1   ApiEntityProjectResourceWorkRateCostInput Project Resource Work Rate  
pricePerUnit2   ApiEntityProjectResourceWorkRateCostInput Project Resource Work Rate  
pricePerUnit3   ApiEntityProjectResourceWorkRateCostInput Project Resource Work Rate  
pricePerUnit4   ApiEntityProjectResourceWorkRateCostInput Project Resource Work Rate  
pricePerUnit5   ApiEntityProjectResourceWorkRateCostInput Project Resource Work Rate  
projectResourceWorkRateId   ApiEntityProjectResourceWorkRateCostInput Project Resource Work Rate  
updateDate   ApiEntityProjectResourceWorkRateCostInput Project Resource Work Rate  
link   ApiEntityProjectResourceWorkRateInput Project Resource Work Rate  
updateDate   ApiEntityProjectResourceWorkRateInput Project Resource Work Rate  
link   ApiEntityCodeValueRiskInput Project Risk  
updateDate   ApiEntityCodeValueRiskInput Project Risk  
cbsCodes   ApiEntityProjectRisk Project Risk  
costValue   ApiEntityProjectRiskConfiguredFieldValueInput Project Risk  
costValueWorkspace1   ApiEntityProjectRiskConfiguredFieldValueInput Project Risk  
costValueWorkspace2   ApiEntityProjectRiskConfiguredFieldValueInput Project Risk  
costValueWorkspace3   ApiEntityProjectRiskConfiguredFieldValueInput Project Risk  
exceptionMessage   ApiEntityProjectRiskConfiguredFieldValueInput Project Risk  
hasException   ApiEntityProjectRiskConfiguredFieldValueInput Project Risk  
link   ApiEntityProjectRiskConfiguredFieldValueInput Project Risk  
updateDate   ApiEntityProjectRiskConfiguredFieldValueInput Project Risk  
actualCostImpact   ApiEntityProjectRiskFinancialInput Project Risk  
actualResponseCostProject   ApiEntityProjectRiskFinancialInput Project Risk  
atCompletionTotalResponseCost   ApiEntityProjectRiskFinancialInput Project Risk  
link   ApiEntityProjectRiskFinancialInput Project Risk  
postActualResponseCost   ApiEntityProjectRiskFinancialInput Project Risk  
postAtCompletionTotalResponseCost   ApiEntityProjectRiskFinancialInput Project Risk  
postExposureCost   ApiEntityProjectRiskFinancialInput Project Risk  
postExposureCostProject   ApiEntityProjectRiskFinancialInput Project Risk  
postQuantifiedCostThreshold   ApiEntityProjectRiskFinancialInput Project Risk  
postRemainingTotalResponseCost   ApiEntityProjectRiskFinancialInput Project Risk  
postResponseExposureWorkspace1   ApiEntityProjectRiskFinancialInput Project Risk  
postResponseExposureWorkspace2   ApiEntityProjectRiskFinancialInput Project Risk  
postResponseExposureWorkspace3   ApiEntityProjectRiskFinancialInput Project Risk  
preActualResponseCost   ApiEntityProjectRiskFinancialInput Project Risk  
preAtCompletionTotalResponseCost   ApiEntityProjectRiskFinancialInput Project Risk  
preExposureCost   ApiEntityProjectRiskFinancialInput Project Risk  
preExposureCostProject   ApiEntityProjectRiskFinancialInput Project Risk  
preQuantifiedCostThreshold   ApiEntityProjectRiskFinancialInput Project Risk  
preRemainingTotalResponseCost   ApiEntityProjectRiskFinancialInput Project Risk  
preResponseExposureWorkspace1   ApiEntityProjectRiskFinancialInput Project Risk  
preResponseExposureWorkspace2   ApiEntityProjectRiskFinancialInput Project Risk  
preResponseExposureWorkspace3   ApiEntityProjectRiskFinancialInput Project Risk  
remainingTotalResponseCost   ApiEntityProjectRiskFinancialInput Project Risk  
updateDate   ApiEntityProjectRiskFinancialInput Project Risk  
activityImpactQuantified   ApiEntityProjectRiskInput Project Risk  
exposureFinishDate   ApiEntityProjectRiskInput Project Risk  
exposureStartDate   ApiEntityProjectRiskInput Project Risk  
link   ApiEntityProjectRiskInput Project Risk  
postResponseMeanCostImpact   ApiEntityProjectRiskInput Project Risk  
postResponseMeanDelay   ApiEntityProjectRiskInput Project Risk  
postResponsePessimisticCostDeltaAbs   ApiEntityProjectRiskInput Project Risk  
postResponsePessimisticFinishDeltaAbs   ApiEntityProjectRiskInput Project Risk  
postScore   ApiEntityProjectRiskInput Project Risk  
preResponseMeanCostImpact   ApiEntityProjectRiskInput Project Risk  
preResponseMeanDelay   ApiEntityProjectRiskInput Project Risk  
preResponsePessimisticCostDeltaAbs   ApiEntityProjectRiskInput Project Risk  
preResponsePessimisticFinishDeltaAbs   ApiEntityProjectRiskInput Project Risk  
quantifiedPostResponseProbabilityThreshold   ApiEntityProjectRiskInput Project Risk  
quantifiedPostResponseScheduleThreshold   ApiEntityProjectRiskInput Project Risk  
quantifiedProbabilityThreshold   ApiEntityProjectRiskInput Project Risk  
quantifiedScheduleThreshold   ApiEntityProjectRiskInput Project Risk  
riskSourceType   ApiEntityProjectRiskInput Project Risk  
score   ApiEntityProjectRiskInput Project Risk  
updateDate   ApiEntityProjectRiskInput Project Risk  
link   ApiEntityRiskImpactInput Project Risk  
projectCode   ApiEntityRiskImpactInput Project Risk  
riskCode   ApiEntityRiskImpactInput Project Risk  
updateDate   ApiEntityRiskImpactInput Project Risk  
workspaceCode   ApiEntityRiskImpactInput Project Risk  
link   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
postResponseMaximumProject   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
postResponseMaximumWorkspace1   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
postResponseMaximumWorkspace2   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
postResponseMaximumWorkspace3   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
postResponseMinimumProject   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
postResponseMinimumWorkspace1   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
postResponseMinimumWorkspace2   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
postResponseMinimumWorkspace3   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
postResponseMostLikelyProject   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
postResponseMostLikelyWorkspace1   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
postResponseMostLikelyWorkspace2   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
postResponseMostLikelyWorkspace3   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
preResponseMaximumProject   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
preResponseMaximumWorkspace1   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
preResponseMaximumWorkspace2   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
preResponseMaximumWorkspace3   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
preResponseMinimumProject   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
preResponseMinimumWorkspace1   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
preResponseMinimumWorkspace2   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
preResponseMinimumWorkspace3   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
preResponseMostLikelyProject   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
preResponseMostLikelyWorkspace1   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
preResponseMostLikelyWorkspace2   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
preResponseMostLikelyWorkspace3   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
updateDate   ApiEntityRiskQuantifiedCostImpactInput Project Risk  
link   ApiEntityRiskQuantifiedOtherImpactInput Project Risk  
updateDate   ApiEntityRiskQuantifiedOtherImpactInput Project Risk  
atCompletionTotalCost   ApiEntityRiskMitigationFinancialInput Project Risk Mitigation  
link   ApiEntityRiskMitigationFinancialInput Project Risk Mitigation  
postResponseActualCost   ApiEntityRiskMitigationFinancialInput Project Risk Mitigation  
postResponseAtCompletionTotalCost   ApiEntityRiskMitigationFinancialInput Project Risk Mitigation  
postResponseRemainingTotalCost   ApiEntityRiskMitigationFinancialInput Project Risk Mitigation  
preResponseActualCost   ApiEntityRiskMitigationFinancialInput Project Risk Mitigation  
preResponseAtCompletionCost   ApiEntityRiskMitigationFinancialInput Project Risk Mitigation  
preResponseRemainingTotalCost   ApiEntityRiskMitigationFinancialInput Project Risk Mitigation  
updateDate   ApiEntityRiskMitigationFinancialInput Project Risk Mitigation  
link   ApiEntityRiskMitigationInput Project Risk Mitigation  
projectName   ApiEntityRiskMitigationInput Project Risk Mitigation  
updateDate   ApiEntityRiskMitigationInput Project Risk Mitigation  
link   ApiEntityCodeValueScopeItemInput Scope Item  
sequenceNumber   ApiEntityCodeValueScopeItemInput Scope Item  
updateDate   ApiEntityCodeValueScopeItemInput Scope Item  
cbsCodes   ApiEntityScopeItem Scope Item  
pbsCodeHierarchy   ApiEntityScopeItem Scope Item  
columnName   ApiEntityScopeItemConfiguredFieldValueInput Scope Item  
costValue   ApiEntityScopeItemConfiguredFieldValueInput Scope Item  
costValueWorkspace1   ApiEntityScopeItemConfiguredFieldValueInput Scope Item  
costValueWorkspace2   ApiEntityScopeItemConfiguredFieldValueInput Scope Item  
costValueWorkspace3   ApiEntityScopeItemConfiguredFieldValueInput Scope Item  
exceptionMessage   ApiEntityScopeItemConfiguredFieldValueInput Scope Item  
hasException   ApiEntityScopeItemConfiguredFieldValueInput Scope Item  
link   ApiEntityScopeItemConfiguredFieldValueInput Scope Item  
updateDate   ApiEntityScopeItemConfiguredFieldValueInput Scope Item  
costCategoryType   ApiEntityScopeItemInput Scope Item  
link   ApiEntityScopeItemInput Scope Item  
pbsCode   ApiEntityScopeItemInput Scope Item  
updateDate   ApiEntityScopeItemInput Scope Item  
link   ApiEntityCodeValueScopeItemAssignmentInput Scope Item Assignment  
sequenceNumber   ApiEntityCodeValueScopeItemAssignmentInput Scope Item Assignment  
updateDate   ApiEntityCodeValueScopeItemAssignmentInput Scope Item Assignment  
cbsCodes   ApiEntityScopeItemAssignment Scope Item Assignment  
columnName   ApiEntityScopeItemAssignmentConfiguredFieldValueInput Scope Item Assignment  
costValue   ApiEntityScopeItemAssignmentConfiguredFieldValueInput Scope Item Assignment  
costValueWorkspace1   ApiEntityScopeItemAssignmentConfiguredFieldValueInput Scope Item Assignment  
costValueWorkspace2   ApiEntityScopeItemAssignmentConfiguredFieldValueInput Scope Item Assignment  
costValueWorkspace3   ApiEntityScopeItemAssignmentConfiguredFieldValueInput Scope Item Assignment  
exceptionMessage   ApiEntityScopeItemAssignmentConfiguredFieldValueInput Scope Item Assignment  
hasException   ApiEntityScopeItemAssignmentConfiguredFieldValueInput Scope Item Assignment  
link   ApiEntityScopeItemAssignmentConfiguredFieldValueInput Scope Item Assignment  
updateDate   ApiEntityScopeItemAssignmentConfiguredFieldValueInput Scope Item Assignment  
actualCostToDate   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
adjustedCost   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
approvedChangedCost   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
atCompletionCost   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
bacCost   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
baselineCost   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
currentRate   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
eacCost   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
earnedCost   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
etcCost   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
installedCost   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
link   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
pendingChangedCost   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
plannedCost   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
rate   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
remainingCost   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
revisedCost   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
updateDate   ApiEntityScopeItemAssignmentCostInput Scope Item Assignment  
costCategoryType   ApiEntityScopeItemAssignmentInput Scope Item Assignment  
link   ApiEntityScopeItemAssignmentInput Scope Item Assignment  
updateDate   ApiEntityScopeItemAssignmentInput Scope Item Assignment  
link   ApiEntityScopeItemAssignmentMilestoneInput Scope Item Assignment  
updateDate   ApiEntityScopeItemAssignmentMilestoneInput Scope Item Assignment  
defaultCurrencyExchangeRate   ApiEntityWorkspaceCurrencySettingInput Workspace  
link   ApiEntityWorkspaceCurrencySettingInput Workspace  
updateDate   ApiEntityWorkspaceCurrencySettingInput Workspace  
workspaceCurrency1ExchangeRate   ApiEntityWorkspaceCurrencySettingInput Workspace  
workspaceCurrency1Id   ApiEntityWorkspaceCurrencySettingInput Workspace  
workspaceCurrency2ExchangeRate   ApiEntityWorkspaceCurrencySettingInput Workspace  
workspaceCurrency2Id   ApiEntityWorkspaceCurrencySettingInput Workspace  
workspaceCurrency3ExchangeRate   ApiEntityWorkspaceCurrencySettingInput Workspace  
workspaceCurrency3Id   ApiEntityWorkspaceCurrencySettingInput Workspace  
workspaceId   ApiEntityWorkspaceCurrencySettingInput Workspace  
image   ApiEntityWorkspaceInput Workspace  
isProduction   ApiEntityWorkspaceInput Workspace  
isSysGenerated   ApiEntityWorkspaceInput Workspace  
link   ApiEntityWorkspaceInput Workspace  
securityGuid   ApiEntityWorkspaceInput Workspace  
sequenceNumber   ApiEntityWorkspaceInput Workspace  
updateDate   ApiEntityWorkspaceInput Workspace  
workspaceAutonumSettings   ApiEntityWorkspaceInput Workspace  
link   ApiEntityWorkspaceSettingInput Workspace  
updateDate   ApiEntityWorkspaceSettingInput Workspace  
workspaceId   ApiEntityWorkspaceSettingInput Workspace