25.2

The following updates were made for 25.2.

Added

Fields

Field Name ApiEntity Name Tag Name Comments
riskFactorCostImpactOption ApiEntityProjectRisk Project Risk  
riskFactorCostImpactOption ApiEntityProjectRiskInput Project Risk  
remainingLaborCost ApiEntityMonteCarloActivityDeterministicFinancialValues Monte Carlo Activity Deterministic Values  
remainingNonLaborCost ApiEntityMonteCarloActivityDeterministicFinancialValues Monte Carlo Activity Deterministic Values  
remainingMaterialCost ApiEntityMonteCarloActivityDeterministicFinancialValues Monte Carlo Activity Deterministic Values  
remainingDurationWithUncertainty ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
totalScheduleRiskFactor ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
riskFactorScheduleImpact ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
totalScheduleCostImpact ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
riskFactorScheduleCostImpact ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
riskFactorCostImpact ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
remainingLaborCostBeforeRiskFactor ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
remainingNonLaborCostBeforeRiskFactor ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
remainingMaterialsCostBeforeRiskFactor ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
totalLaborCostRiskFactor ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
totalNonLaborCostRiskFactor ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
totalMaterialsCostRiskFactor ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
remainingLaborCost ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
remainingNonLaborCost ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
remainingMaterialsCost ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
remainingLaborCostImpact ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
remainingNonLaborCostImpact ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  
remainingMaterialsCostImpact ApiEntityMonteCarloActivityIterationValue Monte Carlo Activity Iteration Values  

Endpoints

Endpoint HTTP Method Tag Name ApiEntity Name Comments
/cbs/recalculate/program/{programId} POST CBS, Program, Action    

Modified

Fields

Field Name ApiEntity Name Tag Name Comment
riskType ApiEntityProgramRisk Program Risk RISK_FACTOR was added to the list of allowed values for the field.
riskType ApiEntityProgramRiskInput Program Risk RISK_FACTOR was added to the list of allowed values for the field.
riskType ApiEntityProjectRisk Project Risk RISK_FACTOR was added to the list of allowed values for the field.
riskType ApiEntityProjectRiskInput Project Risk RISK_FACTOR was added to the list of allowed values for the field.