View All Monte Carlo Project Iteration Values by Parent Codes
get
/api/restapi/monteCarloProjectIterationValues/parentCode
Send a request to this endpoint to view all Monte Carlo Project Iteration Values under parent with codes matching the code fields in query parameters.
Request
Query Parameters
-
projectCode(required): string
The user-specified identifier of a project.
This is a required field. -
scenario(required): string
The type of risk analysis run on a project.
- PRE_MITIGATED : A quantitative risk analysis that doesn't take into account the impact of defined risk response plans.
- POST_MITIGATED : A quantitative risk analysis that takes into account the impact of defined risk response plans.
- BOTH : A quantitative risk analysis that uses both pre and post mitigated contexts.
This is a required field.Allowed Values:[ "PRE_MITIGATED", "POST_MITIGATED", "BOTH" ]
-
workspaceCode(required): string
The user-specified identifier of a workspace.
This is a required field.
There's no request body for this operation.
Back to TopResponse
Supported Media Types
- application/json
200 Response
Successful operation
Root Schema : List<ApiEntityMonteCarloProjectIterationValue>
Type:
array
Title:
Show Source
List<ApiEntityMonteCarloProjectIterationValue>
-
Array of:
object ApiEntityMonteCarloProjectIterationValue
Title:
ApiEntityMonteCarloProjectIterationValue
Nested Schema : ApiEntityMonteCarloProjectIterationValue
Type:
object
Title:
Show Source
ApiEntityMonteCarloProjectIterationValue
-
atCompletionTotalCost: number
(double)
The project at completion total cost for the iteration. Stored for the first 50 iterations only.
-
earlyFinishDate: string
(date-time)
The project finish date for the iteration. Stored for all iterations.
-
earlyStartDate: string
(date-time)
The project start date for the iteration. Stored for all iterations.
-
impactBarStartDate: string
(date-time)
The start date that the project impact bar starts on. Stored for the first 50 iterations only.
-
impactingRisks: stringMaximum Length:3855
Deprecated. As of 24.3, replaced by 'risksImpactingProject'.The project risks that impacted the project for the iteration. Stored for the first 50 iterations only. -
iterationBlock: integer
(int64)
The iteration block number.
-
iterationNumber: integer
(int64)
The iteration sequence number.
-
link: string
(url)
Read Only:
true
The self-link to the object. This field is populated only in the responses generated by the batch create APIs. -
monteCarloScenario: string
Allowed Values:
[ "PRE_MITIGATED", "POST_MITIGATED" ]
The type of risk analysis run on a project.- PRE_MITIGATED : A quantitative risk analysis that doesn't take into account the impact of defined risk response plans.
- POST_MITIGATED : A quantitative risk analysis that takes into account the impact of defined risk response plans.
-
projectCode: string
Minimum Length:
1
Maximum Length:60
The unique identifier for a project set by the user who created the project. -
projectDirectRemainingDuration: number
(double)
The project direct remaining duration due to project risks for the iteration. Stored for all iterations.
-
projectId: integer
(int64)
The system-generated unique identifier of the project.
-
projectScenarioId: integer
(int64)
The system-generated unique identifier of the project scenario.
-
projectTotalDirectAtCompletionCost: number
(double)
The project direct at completion cost due to project risks for the iteration. Stored for all iterations.
-
projectTotalDirectRemainingCost: number
(double)
The project direct remaining cost due to project risks for the iteration. Stored for all iterations.
-
remainingCost: number
(double)
The project total remaining duration for the iteration. Stored for all iterations.
-
remainingDuration: number
(double)
The project remaining duration for the iteration. Stored for all iterations.
-
removedItemId: integer
(int64)
The system-generated identifier of the removed object.
-
removedItemType: string
Allowed Values:
[ "ACTIVITY_UNCERTAINTY", "NONE", "RISK" ]
The type of removed item. -
riskCostImpactProject: number
(double)
The total for the iteration of all of the project-level risk cost impacts. Stored for the first 50 iterations only.
-
riskCostImpactTotal: number
(double)
The total for the iteration of all the project-level and activity level risk cost impacts. Stored for the first 50 iterations only.
-
risksImpactingProject: string
Maximum Length:
0
The project risks that impacted the project for the iteration. Stored for the first 50 iterations only. -
uncertaintyDelay: number
(double)
The project mean schedule delay for the iteration. Stored for all iterations.
-
workspaceCode: string
Minimum Length:
0
Maximum Length:60
The user-specified identifier of a workspace.
204 Response
Successful operation with no content.
404 Response
The Monte Carlo Project Iteration Values do not exist, or you do not have access to them.