Data Dictionary
Data Dictionary
This data dictionary defines fields used in Oracle Primavera Cloud.
Some data dictionary terms contain a set of parentheses. In these parentheses are specific terms used to set the context for the rest of the definition. For example, Schedule Percent Complete (Activity) defines the activity level Schedule Percent Complete value while Schedule Percent Complete (Schedule) defines the value at the project level grouping band.
% Complete (Payment Application)
% Complete
The percentage of the total amount of money budgeted in the contract.
% Retained (Payment Application)
% Retained
Retainage percentage. This is the percentage of the payment that is to be withheld until all work on the contract is complete.
(Pre-Response Risk Removal Pessimistic) Cost Impact (Risk Analysis)
(Pre-Response Risk Removal Pessimistic) Cost Impact
The cost difference between the Pre-Response and Post-Response remaining cost values.
(Pre-Response Risk Removal Pessimistic) Finish Impact (Risk Analysis)
(Pre-Response Risk Removal Pessimistic) Finish Impact
The duration difference between the pre-response and post-response pessimistic finish dates.
Accepted By (Potential Change Order)
Accepted By
The user who accepted a reply to the question.
Action (Contract)
Action
The action that changed the status of the record.
Action (Contracts and Commitments Change)
Action
The action that changed the status of the record.
Activity Count (Project)
Activity Count
The total number of activities in the project.
Activity Percent Complete (Activity)
Activity Percent Complete
The percentage of the activity that has been completed.
This value is based on the formula for the selected Percent Complete Type. The Percent Complete Type can be Physical, Duration, Units, or Scope.
Physical: The user records the percent complete manually.
Duration: Calculated as (Planned Duration minus Remaining Duration) divided by Planned Duration, multiplied by 100.
Units: Calculated as (Actual Labor Units plus Actual Nonlabor Units) divided by (Actual Labor Units plus Actual Nonlabor Units plus Remaining Labor Units plus Remaining Nonlabor Units), multiplied by 100.
Scope: Calculated as Installed Quantity divided by At Completion Quantity, multiplied by 100.
Activity Percent Complete (Work Package)
Activity Percent Complete
The percentage complete for all activities assigned to the work package.
Activity Weight Method (Work Package)
Activity Weight Method
The method used to calculate Activity Percent Complete. Methods are Duration, Labor Units, Non Labor Units, and Manual.
Duration: Planned Duration, also known as Original Duration, is used for Weight.
Labor Units: At Completion Labor Units is used for Weight.
Non Labor Units: At Completion NonLabor Units is used for Weight.
Manual: Weight is added manually.
Actual Cost - Deterministic (Risk Analysis)
Actual Cost - Deterministic
The project actual cost at the time the risk analysis as run.
Actual Cost (Activity Assignment)
Actual Cost
The actual cost for the resource assignment on the activity.
Actual Cost (Risk Analysis)
Actual Cost
The activity actual cost at the time the risk analysis was run.
Actual Cost from P6 (Project Budget)
Actual Cost from P6
Total costs accrued on a project within a given time period.
The Actual Cost data for the project's life cycle is pulled from the P6 EPPM schedule.
Actual Cost data is only available when the application is connected with P6 EPPM and is not editable. This value is based on the base currency with specified exchange rate.
Actual Cost Impact (Risk)
Actual Cost Impact
The actual cost impact due to the risk occurring.
Actual Cost to Date (Scope Assignment)
Actual Cost to Date
The actual costs incurred on the scope assignment. This tracks the VOWD (Value of Work Done).
Actual Cost to Date (Work Package)
Actual Cost to Date
The actual costs incurred on the scope assignment. This tracks the VOWD (Value of Work Done).
This is the cumulative value for all scope assignments in the work package.
Actual Duration (Activity Assignment)
Actual Duration
The total working time from the assignment actual start date to the actual finish date for completed assignments, or the total working time from the actual start date to the data date for in-progress assignments.
Actual Duration (Activity)
Actual Duration
The total working time from the activity Actual Start date to the Actual Finish date for completed activities, or the total working time from the Actual Start date to the data date for in-progress activities.
The actual working time is computed using the activity's calendar.
Actual Duration (Project)
Actual Duration
The Actual Duration represents the total working time between the project Actual Start and Actual Finish for a project.
This value can be imported. The Actual Duration field is not editable.
Actual Duration (Risk Analysis)
Actual Duration
The project actual duration at the time the risk analysis was run.
Actual Duration
The activity actual duration at the time the risk analysis was run.
Actual Duration (Risk Analysis)
Actual Duration
The activity actual duration at the time the risk analysis was run.
Actual Effective Date (Program)
Actual Effective Date
The month in which an actuals value was last added to the program
Actual Finish (Activity Assignment)
Actual Finish
The date on which the assignment was completed.
Actual Finish (Activity)
Actual Finish
The date when the activity was completed.
Actual Finish (Program)
Actual Finish
The Actual Finish displays the date on which a program is considered complete.
This value can be entered manually or can be imported.
Actual Finish (Project)
Actual Finish
The Actual Finish displays the date on which a project is considered complete.
This value can be entered manually or can be imported.
Actual Finish (Risk Analysis)
Actual Finish
The activity actual finish at the time the risk analysis was run.
Actual Finish Date (Risk Analysis)
Actual Finish Date
The project actual finish date at the time the risk analysis was run.
Actual Hours to Date (Scope Assignment)
Actual Hours to Date
The actual hours spent on the scope assignment. This tracks the VOWD (Value of Work Done).
Actual Hours to Date (Work Package)
Actual Hours to Date
The actual hours spent on the scope assignment. This tracks the VOWD (Value of Work Done).
This is the cumulative value for all scope assignments in the work package.
Actual Labor Cost (Activity)
Actual Labor Cost
The actual costs for all labor resource assignments on the activity.
Actual Labor Units (Activity)
Actual Labor Units
The number of units expended for all labor resources assigned to the activity.
Actual Material Cost (Activity)
Actual Material Cost
The actual costs for all material resource assignments on the activity.
Actual Nonlabor Cost (Activity)
Actual Nonlabor Cost
The actual costs for all nonlabor resource assignments on the activity.
Actual Nonlabor Units (Activity)
Actual Nonlabor Units
The number of nonlabor units that have been expended on the activity.
Actual Over Time Units (Activity Assignment)
Actual Over Time Units
The actual overtime units worked by the resource on the activity.
Actual Quantity to Date (Scope Assignment)
Actual Quantity to Date
The Installed Quantity for the scope assignment.
Actual Quantity to Date (Scope Item)
Actual Quantity to Date
The total amount of the scope item installed.
Calculated as the sum of Installed Quantity for all scope assignments.
Actual Risk Response (Cost Sheet)
Actual Risk Response
The actual cost of responding to a risk.
Actual Schedule Impact (Risk)
Actual Schedule Impact
The actual schedule impact due to the risk occurring.
Actual Start (Activity Assignment)
Actual Start
If the activity has started, the date work began on the activity.
Actual Start (Activity)
Actual Start
The date work on the activity began.
Actual Start (Program)
Actual Start
The Actual Start indicates the date work on the program began.
This value can be entered manually or can be imported.
Actual Start (Project)
Actual Start
The Actual Start indicates the date work on the project began.
This value can be entered manually or can be imported.
Actual Start (Risk Analysis)
Actual Start
The activity actual start at the time the risk analysis was run.
Actual Start Date (Risk Analysis)
Actual Start Date
The project actual start date at the time the risk analysis was run.
Actual This Period Cost (Activity Assignment)
Actual This Period Cost
The labor, nonlabor, and material costs incurred during the current financial period.
Actual This Period Cost (Activity)
Actual This Period Cost
The labor, nonlabor, and material costs incurred during the current financial period.
Actual This Period Units (Activity Assignment)
Actual This Period Units
The labor, nonlabor, and material units used during the current financial period.
Actual This Period Units (Activity)
Actual This Period Units
The labor, nonlabor, and material units used during the current financial period.
Actual Total Cost (Activity)
Actual Total Cost
The actual total cost for all resource assignments and direct activity costs (expenses) on the activity.
Actual Units (Activity Assignment)
Actual Units
The sum of the actual non-overtime and the overtime units worked by the resource on the activity.
Actual Units
The units of work performed by the resource on the activity.
Actual Units (Activity Assignment)
Actual Units
The units of work performed by the resource on the activity.
Actuals (Present Value) (Program Budget)
Actuals (Present Value)
The present value, also known as discounted value, of the overall program actuals. Future cash flows are discounted using the program's annual discount rate. Portfolio managers can use present value of a program's expected cash flow as a metric during program prioritization and selection.
Actuals (Present Value) (Project Budget)
Actuals (Present Value)
The present value, also known as discounted value, of the overall project actuals. Future cash flows are discounted using the project's annual discount rate. Portfolio managers can use present value of a project's expected cash flow as a metric during project prioritization and selection. This value is based on the base currency with specified exchange rate.
Actuals (Program Budget)
Actuals
The total amount incurred on a program throughout its lifecycle, such as the costs of invoices, payments, or accruals.
Actuals cannot be edited if a program has a status of Proposal.
Actuals (Project Budget)
Actuals
The total amount incurred on a project throughout its lifecycle, such as the costs of invoices, payments, or accruals.
Actuals cannot be edited if a project has a status of Proposal. This value is based on the base currency with specified exchange rate.
Actuals Effective Date (Project)
Actuals Effective Date
The month in which an actuals value was last added to the project.
Actuals Finish (Project)
Actuals Finish
The finish date for the project actuals.
Actuals Start (Project)
Actuals Start
The start date for the project actuals.
Additional Approver (Payment Application)
Additional Approver
A company other than the project owner or general contractor that can approve the payment application.
Additional Approver Contact (Payment Application)
Additional Approver Contact
A contact at any company other than the project owner or general contractor that can approve the payment application.
Adjusted Cost (Scope Assignment)
Adjusted Cost
The amount the scope assignment work that is not yet accounted for. For example, you might enter a value to represent pending change requests that are likely to be approved.
Adjusted Cost (Work Package)
Adjusted Cost
The amount the scope assignment work that is not yet accounted for. For example, you might enter a value to represent pending change requests that are likely to be approved.
This is the cumulative value for all scope assignments in the work package.
Adjusted Hours (Scope Assignment)
Adjusted Hours
The amount of scope assignment work that is not yet accounted for. For example, you might enter a value to represent pending change requests that are likely to be approved.
Adjusted Hours (Work Package)
Adjusted Hours
The amount of scope assignment work that is not yet accounted for. For example, you might enter a value to represent pending change requests that are likely to be approved.
This is the cumulative value for all scope assignments in the work package.
Adjusted Quantity (Scope Assignment)
Adjusted Quantity
The scope assignment quantity that is not yet accounted for. For example, you might enter a value to represent pending change requests that are likely to be approved.
Adjusted Quantity (Scope Item)
Adjusted Quantity
The scope item quantity that is not yet accounted for. For example, you might enter a value to represent pending change requests that are likely to be approved.
This is a manual entry field.
Agreement Current Value (Payment Application)
Agreement Current Value
The current value of the payment application, plus all approved changes.
Agreement Original Value (Payment Application)
Agreement Original Value
The original value of the contract or commitment.
Allocated (Funds)
Allocated
The portion of the fund that has been distributed to projects, programs, or other workspaces.
Allocated
The portion of all funds in the workspace that has been reserved for work on projects, programs and other workspaces.
Allocated (Funds)
Allocated
The portion of all funds in the workspace that has been reserved for work on projects, programs and other workspaces.
Allocated Funds (Funds)
Allocated Funds
The portion of the fund that has been distributed to projects or other workspaces.
Amount (Budget Transaction)
Amount
The amount that the budget row has changed as the result of transactions.
Amount (Program Budget Transaction)
Amount
The amount that the budget row has changed as the result of transactions.
Amount Approved (Payment Application)
Amount Approved
The total amount approved for the payment application.
Amount Approved
The total amount approved for the payment application.
Amount Approved (Payment Application)
Amount Approved
The total amount approved for the payment application.
Annual Discount Rate (Program Budget)
Annual Discount Rate
The interest rate associated with the cost of an investment from your commercial bank or another funding source.
For example, an annual growth rate of an investment such as 4.75% can be used as an annual discount rate. This rate is used when a future value is assumed and you are trying to find the required Net Present Value.
This value can be entered manually or can be imported.
Annual Discount Rate (Project Budget)
Annual Discount Rate
The interest rate associated with the cost of an investment from your commercial bank or another funding source.
For example, an annual growth rate of an investment such as 4.75% can be used as an annual discount rate. This rate is used when a future value is assumed and you are trying to find the required Net Present Value.
This value can be entered manually or can be imported.
Answer (Potential Change Order)
Answer
The answer that was marked as accepted.
Answered By (Potential Change Order)
Answered By
The user who submitted the accepted answer to the question.
Application Administrator
Application Administrator
Indicates a user with full access to the application.
Appropriated (Funds)
Appropriated
The portion of the fund that has been committed to work on a project.
Appropriated Funds (Funds)
Appropriated Funds
The portion of the fund that has been committed to work on a project.
Approval Date (Budget Change Request)
Approval Date
Date the item was approved.
Approval Date (Budget Transfer)
Approval Date
Date the item was approved.
Approval Date (Change Order)
Approval Date
The date the commitment change order was approved.
Approval Date (Program Budget Change Request)
Approval Date
Date the item was approved.
Approved Budget (Budget Planning)
Approved Budget
The total approved budget currently allocated to the portfolio.
Current Approved Budget values are derived from the Proposed Budget set by the budget planner.
A Proposed Budget becomes a Current Approved Budget after the budget scenario has undergone the approval process.
Approved Budget (Present Value) (Project Budget)
Approved Budget (Present Value)
The present value, also known as discounted value, of the portfolio approved budget. Future cash flows are discounted using the project's annual discount rate. This value is based on the base currency with specified exchange rate.
Approved Budget Finish Date (Project)
Approved Budget Finish Date
The finish date for the Current Approved Budget set by the budget planner.
Approved Budget Start Date (Project)
Approved Budget Start Date
The start date for the Current Approved Budget set by the budget planner.
Approved Change Cost (Scope Assignment)
Approved Change Cost
The sum of all approved cost changes in the change records for the scope assignment.
Approved Change Cost (Work Package)
Approved Change Cost
The sum of all approved cost changes in the change records for the scope assignment.
This is the cumulative value for all scope assignments in the work package.
Approved Change Hours (Scope Assignment)
Approved Change Hours
The sum of all approved change hours in the change and transfer records for the scope assignment.
Approved Change Hours (Work Package)
Approved Change Hours
The sum of all approved change hours in the change and transfer records for the scope assignment.
This is the cumulative value for all scope assignments in the work package.
Approved Change Orders (Payment Application)
Approved Change Orders
The sum of approved change orders for the payment application.
Approved Change Quantity (Scope Assignment)
Approved Change Quantity
Calculated as the sum of all approved change quantities in the change records for the scope assignment.
Approved Commitment Changes (Actual Risk Response Cost)
Approved Commitment Changes
The sum of all approved cost changes in the change records for the commitment.
Approved Commitment Changes (Cost Sheet)
Approved Commitment Changes
The total value of all approved commitment change orders.
Approved Commitment Potential Change Orders (Actual Risk Response Cost)
Approved Commitment Potential Change Orders
The sum of all approved potential change orders for commitments.
Approved Commitment Potential Change Orders (Cost Sheet)
Approved Commitment Potential Change Orders
The sum of all approved potential change orders for commitments.
Approved Commitments (Actual Risk Response Cost)
Approved Commitments
The total cost of all approved commitments.
Approved Commitments (Cost Sheet)
Approved Commitments
The total value of all approved and closed commitments in the project.
Approved Contract Changes (Actual Risk Response Cost)
Approved Contract Changes
The total cost for all approved changes in contracts.
Approved Contract Changes (Cost Sheet)
Approved Contract Changes
The total cost for all approved changes in contracts.
Approved Contract Potential Change Orders (Actual Risk Response Cost)
Approved Contract Potential Change Orders
The sum of all approved potential change orders for contracts.
Approved Contract Potential Change Orders (Cost Sheet)
Approved Contract Potential Change Orders
The sum of all approved potential change orders for contracts.
Approved Contracts (Actual Risk Response Cost)
Approved Contracts
The total cost for all approved contracts.
Approved Contracts (Cost Sheet)
Approved Contracts
The total cost for all approved contracts.
Approved Date (Budget Transaction)
Approved Date
The date the transaction was approved.
Approved Revenue (Actual Risk Response Cost)
Approved Revenue
Revenue that has been submitted and approved by an authorized reviewer.
Approved Revenue (Cost Sheet)
Approved Revenue
Revenue that has been submitted and approved by an authorized reviewer.
Approved Spends (Actual Risk Response Cost)
Approved Spends
Spends that have been submitted and approved by an authorized reviewer.
Approved Spends (Cost Sheet)
Approved Spends
Spends that have been submitted for review and approved by an authorized reviewer.
Assigned Quantity (Scope Item)
Assigned Quantity
The total quantity distributed to work packages by way of scope assignments. After the original baseline is set, this number is updated to also reflect scope assignments that are created from approved quantity changes of the scope item.
Assigned To (Potential Change Order)
Assigned To
The user who is assigned to answer the question.
Associated Agreement (Change Order)
Associated Agreement
The contract associated with the change order.
Associated Agreement (Payment Application)
Associated Agreement
The agreement associated with the payment application.
Associated Agreement (Potential Change Order)
Associated Agreement
The link to the associated agreement.
Associated Commitment (Contracts and Commitments)
Associated Commitment
The name and ID of the commitment associated with the commitment change order.
Associated Contract (Commitment)
Associated Contract
The contract associated with the commitment.
At Completion (Project Budget)
At Completion
The At Completion Total Cost from a cost-loaded P6 EPPM schedule.
At Completion data is only available when the application is connected to P6 EPPM and is not editable.
The At Completion field is populated with the At Completion Total Cost from the project's P6 EPPM schedule. This value is based on the base currency with specified exchange rate.
At Completion Cost (Activity Assignment)
At Completion Cost
The sum of the actual costs plus remaining costs for the resource assignment on the activity.
At Completion Cost (Scope Assignment)
At Completion Cost
The total cost at the completion of the scope assignment.
Calculated as Revised Cost plus Adjusted Cost.
At Completion Cost (Work Package)
At Completion Cost
The total cost at the completion of the scope assignment.
Calculated as Revised Cost plus Adjusted Cost.
This is the cumulative value for all scope assignments in the work package.
At Completion Duration - Deterministic (Risk Analysis)
At Completion Duration - Deterministic
The activity at completion duration at the time the risk analysis was run.
At Completion Duration (Activity Assignment)
At Completion Duration
The total working time from the assignment's current start date to the current finish date.
At Completion Duration (Activity)
At Completion Duration
The total working time from the activity's current start date to the current finish date.
The current start date is the planned start date until the activity is started, and then it is the actual start date. The current finish date is the activity planned finish date while the activity is not started, the remaining finish date while the activity is in progress, and the actual finish date once the activity is completed. The total working time is calculated using the activity's calendar.
At Completion Hours (Scope Assignment)
At Completion Hours
The total hours expected for the scope assignment.
Calculated as Revised Hours plus Adjusted Hours.
At Completion Hours (Work Package)
At Completion Hours
The total hours expected to be spend at the completion of the scope assignment.
Calculated as Revised Hours plus Adjusted Hours.
This is the cumulative value for all scope assignments in the work package.
At Completion Labor Cost (Activity)
At Completion Labor Cost
The sum of the actual costs plus remaining costs for all labor resource assignments on the activity.
At Completion Labor Units (Activity)
At Completion Labor Units
The sum of the actual plus remaining units for all labor resources assigned to the activity.
It is the same as the planned labor units if the activity is not started, and the actual labor units after the activity is completed.
Calculated as Actual Labor Units plus Remaining Labor Units.
At Completion Material Cost (Activity)
At Completion Material Cost
The sum of the actual costs plus remaining costs for all material resource assignments on the activity.
At Completion Nonlabor Cost (Activity)
At Completion Nonlabor Cost
The sum of the actual costs plus remaining costs for all nonlabor resource assignments on the activity.
At Completion Nonlabor Units (Activity)
At Completion Nonlabor Units
The sum of the actual plus remaining units for all nonlabor resources assigned to the activity.
It is the same as the planned nonlabor units if the activity is not started, and the actual nonlabor units after the activity is completed.
Calculated as Actual Nonlabor Units plus Remaining Nonlabor Units.
At Completion Quantity (Scope Assignment)
At Completion Quantity
The total amount of the scope item to be installed for the scope assignment.
Calculated as Revised Quantity plus Adjusted Quantity.
At Completion Quantity (Scope Item)
At Completion Quantity
The total amount of the scope item to be installed for the project.
Calculated as Revised Quantity plus Adjusted Quantity.
At Completion Total Cost - Deterministic (Risk Analysis)
At Completion Total Cost - Deterministic
The activity at completion total cost at the time the risk analysis was run.
At Completion Total Cost (Activity)
At Completion Total Cost
The sum of the actual costs plus remaining costs for all resource assignments and direct activity costs (expenses) on the activity.
At Completion Units (Activity Assignment)
At Completion Units
The sum of the actual units and remaining units for the resource assignment on the activity.
Calculated as Actual Units plus Remaining Units.
Available Hours (Scope Assignment)
Available Hours
The number of hours available for scope assignment.
Calculated as Revised Hours minus Installed Hours.
Available Quantity (Scope Assignment)
Available Quantity
The amount of material or product available for scope assignment.
Calculated as Revised Quantity minus Installed Quantity.
BAC Cost (Scope Assignment)
BAC Cost
The Revised Cost or At Completion Cost at the time the current baseline was set, depending on the selection for the Budget at Completion Method. The Revised Cost of the current project if no baseline is set.
BAC Cost (Work Package)
BAC Cost
The Revised Cost or At Completion Cost at the time the current baseline was set, depending on the selection for the Budget at Completion Method. The Revised Cost of the current project if no baseline is set.
This is the cumulative value for all scope assignments in the work package.
BAC Hours (Scope Assignment)
BAC Hours
The Revised Hours or At Completion Hours at the time the current baseline was set, depending on the selection for the Budget At Completion Method. The Revised Hours of the current project if no baseline is set.
BAC Hours (Work Package)
BAC Hours
The Revised Hours or At Completion Hours at the time the current baseline was set, depending on the selection for the Budget At Completion Method. The Revised Hours of the current project if no baseline is set.
This is the cumulative value for all scope assignments in the work package.
BAC Quantity (Scope Assignment)
BAC Quantity
The Revised Quantity or At Completion Quantity at the time the current baseline was set, depending on the selection for the Budget at Completion Method. The Revised Quantity of the current project if no baseline is set.
Balance Remaining (Change Order)
Balance Remaining
The amount of money you expect to spend to complete work on this item.
Balance Remaining (Commitment)
Balance Remaining
The balance of work remaining to complete the line item.
Balance Remaining (Contract)
Balance Remaining
The remaining balance of the schedule of values cost.
Balance To Finish + Retainage (Payment Application)
Balance To Finish + Retainage
The total of the balance required to finish work represented by the agreement, plus the amount of retainage to be paid when work is complete.
Ball in Court (Potential Change Order)
Ball in Court
The user responsible for the current step of the potential change order.
Ball in Court
The user who is responsible for the current step of the potential change order proposal.
Ball in Court (Potential Change Order)
Ball in Court
The user who is responsible for the current step of the potential change order proposal.
Baseline Cost (Scope Assignment)
Baseline Cost
The Revised Cost at the time the current baseline was set.
Baseline Cost (Work Package)
Baseline Cost
The Revised Cost at the time the current baseline was set.
This is the cumulative value for all scope assignments in the work package.
Baseline Finish (Work Package)
Baseline Finish
The planned finish date for the work package as is set in the current baseline.
This field is populated with the Revised Finish date at the time that the current baseline is set.
Baseline Hours (Scope Assignment)
Baseline Hours
The Revised Hours at the time the baseline was set.
Baseline Hours (Work Package)
Baseline Hours
The Revised Hours at the time the baseline was set.
This is the cumulative value for all scope assignments in the work package.
Baseline Quantity (Scope Item)
Baseline Quantity
The Revised Quantity at the time the current baseline was set.
Baseline Start (Scope Assignment)
Baseline Start
The planned start date for the scope assignment as is set in the current baseline.
This field is used to spread baseline data fields.
This field is populated with the Revised Start date at the time that the current baseline is set.
If there is an activity link, this field is populated with the activity's Current BL Start date.
Baseline Start (Work Package)
Baseline Start
The planned start date for the work package as is set in the current baseline.
This field is populated with the Revised Start date at the time that the current baseline is set.
Benefits (Present Value) (Project Budget)
Benefits (Present Value)
The present value, also known as the discounted value, of the overall project benefits. Future cash flows are discounted using the project's annual discount rate. Portfolio managers can use the present value of a project's expected cash flow as a metric during project prioritization and selection. This value is based on the base currency with specified exchange rate.
Benefits (Project Budget)
Benefits
Project benefits is the income or positive cash flow from which all charges, costs, and expenses are subtracted to arrive at the net income. Also called sales, turnover, or revenue. This value is based on the base currency with specified exchange rate.
Benefits Finish Date (Program)
Benefits Finish Date
The date benefits on the program finished.
Benefits Start Date (Program)
Benefits Start Date
The date benefits on the program began.
BL Activity Percent Complete (Activity)
BL Activity Percent Complete
In the baseline, the activity percent complete, manually entered by a user.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Activity Status (Activity)
BL Activity Status
Determines the status of the activity in the baseline. Valid values are Not Started, In Progress, and Completed.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Actual Duration (Activity)
BL Actual Duration
In the baseline, the total working time from the activity BL Actual Start date to the BL Actual Finish date for completed activities, or the total working time from the BL Actual Start date to the data date for in-progress activities.
The actual working time is computed using the activity's calendar.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Actual Finish (Activity)
BL Actual Finish
The completion date of the activity in the baseline.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Actual Labor Cost (Activity)
BL Actual Labor Cost
The actual cost for all labor resources assigned to the activity as stored in the associated project baseline.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Actual Labor Units (Activity)
BL Actual Labor Units
The number of units expended for all labor resources assigned to the activity in the baseline.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Actual Material Cost (Activity)
BL Actual Material Cost
The actual cost for all material resources assigned to the activity as stored in the associated project baseline.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Actual Nonlabor Cost (Activity)
BL Actual Nonlabor Cost
The actual cost for all nonlabor resources assigned to the activity as stored in the associated project baseline.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Actual Nonlabor Units (Activity)
BL Actual Nonlabor Units
The number of nonlabor units expended for all nonlabor resources assigned to the activity in the baseline.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Actual Start (Activity)
BL Actual Start
The start date of the activity in the baseline.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Actual Total Cost (Activity)
BL Actual Total Cost
The actual total cost for all labor, nonlabor and material resources assigned to the activity as stored in the associated project baseline.
Calculated as BL Actual Labor Cost plus BL Actual Nonlabor Cost plus BL Actual Material Cost.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Duration Percent Complete (Activity)
BL Duration Percent Complete
The duration percent complete for the activity in the baseline. Calculated as Planned Duration minus Remaining Duration divided by Planned Duration multiplied by 100.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Early Finish (Activity)
BL Early Finish
The earliest possible finish date of the activity in the baseline.
This date is calculated based on network logic, schedule constraints, and resource availability.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Early Start (Activity)
BL Early Start
The earliest possible start date of the remaining work for the activity in the baseline.
This date is calculated based on network logic, schedule constraints, and resource availability.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Finish (Activity)
BL Finish
The current finish date for the activity in the baseline.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Free Float (Activity)
BL Free Float
The amount of time the activity in the baseline can be delayed before delaying the start date of any successor activity.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Late Finish (Activity)
BL Late Finish
In the baseline, the latest possible date the activity can finish without delaying the project finish date.
This date is calculated based on activity relationships, schedule constraints, and resource availability.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Late Start (Activity)
BL Late Start
In the baseline, the latest possible date the remaining work for the activity can begin without delaying the project finish date.
This date is calculated based on activity relationships, schedule constraints, and resource availability.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Percent Complete Type (Activity)
BL Percent Complete Type
Determines the way in which the application calculates the percent complete for the activity in the baseline. Valid values are Physical, Duration, and Units.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Planned Duration (Activity)
BL Planned Duration
The expected amount of time required to complete the activity in the baseline.
The planned working time is calculated using the activity's calendar. The duration is measured from the activity's planned start date to its planned finish date.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Planned Labor Cost (Activity)
BL Planned Labor Cost
The planned cost for all labor resources assigned to the activity as stored in the associated project baseline.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Planned Labor Units (Activity)
BL Planned Labor Units
The planned units for all labor resources assigned to the activity in the baseline.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Planned Material Cost (Activity)
BL Planned Material Cost
The planned cost for all material resources assigned to the activity as stored in the associated project baseline.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Planned Nonlabor Cost (Activity)
BL Planned Nonlabor Cost
The planned cost for all nonlabor resources assigned to the activity as stored in the associated project baseline.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Planned Nonlabor Units (Activity)
BL Planned Nonlabor Units
The planned units for all nonlabor resources assigned to the activity in the baseline.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Planned Total Cost (Activity)
BL Planned Total Cost
The planned total cost for all labor, nonlabor, and material resources assigned to the activity as stored in the associated project baseline.
Calculated as BL Planned Labor Cost plus BL Planned Nonlabor Cost plus BL Planned Material Cost.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Remaining Duration (Activity)
BL Remaining Duration
In the baseline, the total working time from the activity remaining start date to the remaining finish date.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Start (Activity)
BL Start
The current start date of the activity in the baseline.
For started activities, this is the actual start date. For not started activities, this is the planned start date until the project is scheduled. When scheduled, the start date field is set to the remaining early start date.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Total Float (Activity)
BL Total Float
In the baseline, the amount of time the activity can be delayed before delaying the project finish date. Calculated as BL Late Start minus BL Early Start or as BL Late Finish minus BL Early Finish.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Units Percent Complete (Activity)
BL Units Percent Complete
The percent complete of units for all labor and nonlabor resources assigned to the activity in the baseline. Calculated as Actual Units divided by At Completion Units multiplied by 100.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Variance - Duration (Activity)
BL Variance - Duration
The duration difference between the activity At Completion Duration and BL Duration.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Variance - Finish (Activity)
BL Variance - Finish
The duration difference between the activity Finish date and BL Finish date.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Variance - Labor Cost (Activity)
BL Variance - Labor Cost
The difference between the associated project baseline planned labor cost and the current schedule at completion labor cost.
Calculated as BL Planned Labor Cost minus At Completion Labor Cost.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Variance - Labor Units (Activity)
BL Variance - Labor Units
The difference between the activity At Completion Labor Units and the BL Planned Labor Units.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Variance - Material Cost (Activity)
BL Variance - Material Cost
The difference between the associated project baseline planned material cost and the current schedule at completion material cost.
Calculated as BL Planned Material Cost minus At Completion Material Cost.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Variance - Nonlabor Cost (Activity)
BL Variance - Nonlabor Cost
The difference between the associated project baseline planned nonlabor cost and the current schedule at completion nonlabor cost.
Calculated as BL Planned Nonlabor Cost minus At Completion Nonlabor Cost.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Variance - Nonlabor Units (Activity)
BL Variance - Nonlabor Units
The difference between the activity At Completion Nonlabor Units and the BL Planned Nonlabor Units.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Variance - Start (Activity)
BL Variance - Start
The duration difference between the activity Start date and BL Start date.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
BL Variance - Total Cost (Activity)
BL Variance - Total Cost
The difference between the associated project baseline planned labor cost and the current schedule at completion labor cost.
Calculated as BL Planned Total Cost minus At Completion Total Cost.
The following baselines have unique names and values for this field: Current, Original, Supplementary, User 1, User 2, User 3.
Budget Approval Date (Project Budget)
Budget Approval Date
The date the project budget was approved.
Budget Approved By (Project Budget)
Budget Approved By
The user who approved the budget.
Budget At Completion (Activity)
Budget At Completion
The budgeted or planned total cost through activity completion.
Calculated as Planned Labor Cost plus Planned Nonlabor Cost plus Planned Material Cost.
Budget At Completion
The budgeted or planned total cost through activity completion.
Budget At Completion (Activity)
Budget At Completion
The budgeted or planned total cost through activity completion.
Budget At Completion (Schedule)
Budget At Completion
The budgeted or planned total cost through activity completion.
Budget At Completion Labor Units (Activity)
Budget At Completion Labor Units
The planned total labor units through activity completion.
Budget At Completion Method (Work Package)
Budget At Completion Method
The setting allows users to select which value to use for populating BAC fields when a baseline is set. Choose At Completion to include adjusted values.
Budget At Completion Units (Activity)
Budget At Completion Units
The budgeted or planned units through activity completion.
Budget Change ID (Budget Transaction)
Budget Change ID
This is an intermediary field that the system uses to calculate other values. It does not correspond to any field users can see in the user interface.
Budget Planning Horizon (Portfolio)
Budget Planning Horizon
The Planning Horizon defines the duration of budget planning within the portfolio.
For example, the U.S. government plans six years of capital spending, in this case their planning horizon would be six years.
The Planning Horizon is separated by yearly Planning Periods, during which budget values allocated to yearly projects, and planning for the year takes place.
Returning to the example, the U.S. Government would establish a Planning Period budget six times, as they have a Planning Horizon of six years.
Planning Horizon can be edited at any point in time during the planning process.
Budget Planning Period (Budget Planning)
Budget Planning Period
The period during which budget is allocated to projects within the plan.
This value determines the year in which budget planning timescales start.
You can set the planning period to either the current or following year. For example, if the year is 2020 the latest planning period you can set is 2021.
After the planning period for a budget plan has been set it cannot be changed.
Budget Review Status (Budget Planning)
Budget Review Status
The current status of a shared budget proposal for a project within a portfolio budget plan.
The project manager can accept the proposed budget or request changes to it. The budget planner is notified of the project manager's requests, and can use budget feedback to adjust the current budget allocation for the budget plan.
Accepted: The proposed budget for the project was accepted by the project manager.
Pending: The project manager is currently reviewing the project's proposed budget.
Changes Requested: The project manager has requested changes to the project's proposed budget.
Budget Status (Budget Planning)
Budget Status
The current budget status of a portfolio. The status is set based on the status of the scenarios and cannot be edited manually.
In Planning: The portfolio is currently going through the budget planning process and contains one or more scenarios in planning. In planning is the default budget status.
Revising: The portfolio currently has one scenario with a status of approved, and another with a status of Under Review, Shared, or Under Approval.
Approved: The portfolio contains a scenario that has gone through the approval process and has been approved.
Budget Status (Project Budget)
Budget Status
The status of the budget.
Budget Transfer ID (Budget Transaction)
Budget Transfer ID
This is an intermediary field that the system uses to calculate other values. It does not correspond to any field users can see in the user interface.
Business Impact (Program)
Business Impact
A detailed description of the business impact of the program.
Calculate Costs from Units (Activity Assignment)
Calculate Costs from Units
Indicates whether to calculate costs based on units for an assignment.
Change Amount (Change Order)
Change Amount
The difference between the original value of the cost and its current value.
Change Amount
The change in cost represented by the commitment change order.
Change Amount (Change Order)
Change Amount
The change in cost represented by the commitment change order.
Change Estimate (Change Order)
Change Estimate
The change estimate of the change order.
Change Estimate (Potential Change Order)
Change Estimate
The change estimate of the potential change order.
Change Order (Change Order)
Change Order
The change order associated with the line item.
Change Order Additions (Previous) (Payment Application)
Change Order Additions (Previous)
The sum of all additions made to the change order during the previous period.
Change Order Additions (This Period) (Payment Application)
Change Order Additions (This Period)
The sum of all additions made to the change order during this period.
Change Order Deductions (Previous) (Payment Application)
Change Order Deductions (Previous)
The sum of all deductions made to the change order during the previous period.
Change Order Deductions (This Period) (Payment Application)
Change Order Deductions (This Period)
The sum of all deductions made to the change order during this period.
Change Reference (Change Order)
Change Reference
The change event of the change order.
Change Reference
The name and ID of the change record associated with the commitment change order.
Change Reference (Change Order)
Change Reference
The name and ID of the change record associated with the commitment change order.
Change Reference (Potential Change Order)
Change Reference
The change of the potential change order.
Collected Commitment Total (Change Order)
Collected Commitment Total
The total value represented by the collected line item. If necessary, this value is converted to the currency of the contract into which it is collected.
Collected from Commitment (Change Order)
Collected from Commitment
The ID of the commitment change order from which the contract change order line item was collected.
Collected into Change Order (Change Order)
Collected into Change Order
The name and ID of the change order into which the commitment change order was collected.
Commitment (Commitment)
Commitment
The commitment associated with the line item.
Commitment
The commitment associated with the line item.
Commitment (Commitment)
Commitment
The commitment associated with the line item.
Commitment Manager (Commitment)
Commitment Manager
The person who is responsible for managing the commitment.
Commitment Status (Task)
Commitment Status
The status of the commitment. Valid values are Committed and Recommitted.
Completed and Stored to Date (Payment Application)
Completed and Stored to Date
The total quantity completed and stored by the current date.
Confirmed Actuals (Cost Sheet)
Confirmed Actuals
Actuals that have been confirmed.
Constraint Count (Task)
Constraint Count
The number of constraints assigned to the selected task or task milestone.
Constraint Impact (Task)
Constraint Impact
Indicates whether the selected task or task milestone has any constraints assigned.
Construction Value (Project Budget)
Construction Value
Construction Value is the total of all project-related costs incurred by the constructing company (usually a General Contractor) over the period of construction. This would generally include cost of materials, subcontract totals, overhead costs, general conditions and tax.
Consumed
Consumed
The portion of the fund that has been spent to complete work on a project.
Consumed (Funds)
Consumed
The portion of the fund that has been spent to complete work on a project.
Contingency (Risk)
Contingency
The allowable risk cost should the risk occur.
Contract (Contract)
Contract
The contract associated with the line item.
Contract
The contract associated with the schedule of values.
Contract (Contract)
Contract
The contract associated with the schedule of values.
Contract Manager (Contract)
Contract Manager
The person in your organization who is responsible for managing the contract.
Cost Category (Budget Item)
Cost Category
The type of cost associated with the budget item.
Cost Category (Budget Transaction)
Cost Category
The type of cost associated with the budget line item.
Cost Category (Change Order)
Cost Category
The type of expense described by the line item. Typical categories include Material, Other, Equipment, and Labor.
Cost Category
The type of cost represented by the line item.
Cost Category (Change Order)
Cost Category
The type of cost represented by the line item.
Cost Category (Commitment)
Cost Category
The kind of cost represented by the line item.
Cost Category
The type of cost associated with the line item.
Cost Category (Commitment)
Cost Category
The type of cost associated with the line item.
Cost Category (Contract)
Cost Category
The type of cost represented by the schedule of values.
Cost Category
The type of cost represented by the line item.
Cost Category (Contract)
Cost Category
The type of cost represented by the line item.
Cost Category (Potential Change Order)
Cost Category
The cost category of the proposal line item.
Cost Performance Index (CPI) (Schedule)
Cost Performance Index (CPI)
The ratio of the approved budget for work performed to what you actual spent for the work accomplished.
Cost Performance Index (CPI) Labor Units (Activity)
Cost Performance Index (CPI) Labor Units
Measures the work efficiency on an activity.
A value less than 1 indicates that the actual units have exceeded the planned units.
Calculated as Earned Value Labor Units divided by Actual Labor Units.
Cost Performance Index (Project Budget)
Cost Performance Index
The measure of a project's cost efficiency.
A value of less than 1 indicates the project is over budget, while a value greater than 1 indicates the project is under budget.
This value can be entered manually or can be imported.
Cost Performance Index Labor Units (Schedule)
Cost Performance Index Labor Units
Measures the work efficiency on an activity, WBS, or project.
Cost Variance (Activity)
Cost Variance
A measure of activity cost performance. The difference between the budgeted cost of work performed minus the actual cost of work performed.
Indicates how much you are under or over your approved budget. A negative value indicates that the actual cost has exceeded the planned value.
Calculated as Earned Value minus Actual Total Cost.
Cost Variance (Project Budget)
Cost Variance
The measure of cost performance on a project.
A negative value indicates that the Actual Cost has exceeded the planned value.
This value can be entered manually or can be imported. This value is based on the base currency with specified exchange rate.
Cost Variance (Schedule)
Cost Variance
The difference between the amounts budgeted for the work you actually performed and the work you planned to do.
Cost Variance Index (Activity)
Cost Variance Index
The ratio of the cost variance and the earned value of work performed on the activity.
Calculated as Cost Variance divided by Earned Value.
Cost Variance Index (Schedule)
Cost Variance Index
The ratio of the cost variance and the earned value of work performed on the WBS, activity, or project.
Cost Variance Index Labor Units (Activity)
Cost Variance Index Labor Units
The ratio of the cost variance labor units and the earned value labor units for the activity.
Calculated as Cost Variance Labor Units divided by Earned Value Labor Units.
Cost Variance Index Labor Units (Schedule)
Cost Variance Index Labor Units
The ratio of the cost variance labor units and the earned value labor units for the activity, WBS, or project.
Cost Variance Labor Units (Schedule)
Cost Variance Labor Units
The difference between the earned value labor units and the actual labor units.
Cost Weight (Scope Assignment)
Cost Weight
This value is used to calculate Scope Percent Complete at the work package level if Scope Percent Complete Weight Method is set to Cost.
Calculated as Scope Percent Complete times Revised Cost.
Critical - Deterministic (Risk Analysis)
Critical - Deterministic
The activity critical value at the time the risk analysis was run.
Critical (Activity Relationship)
Critical
Determines whether the activity is critical. An activity is critical when its total float is below the critical duration specified for the project.
Current Committed Due Date (Task)
Current Committed Due Date
The current due date of the task commitment.
Current Cost (Budget Item)
Current Cost
The current cost of the budget line item.
Current Cost (Budget Transaction)
Current Cost
The current cost of the associated budget line item.
Current Cost (Program Budget Item)
Current Cost
The current cost of the budget line item.
Current Cost (Program Budget Transaction)
Current Cost
The current cost of the associated budget line item.
Current Payment Due (Payment Application)
Current Payment Due
The original value of the contract or commitment.
Current Payment Due
The original value of the contract or commitment.
Current Payment Due (Payment Application)
Current Payment Due
The original value of the contract or commitment.
Current Value (Commitment)
Current Value
The present value of the cost.
Current Value (Contract)
Current Value
The present value of the cost.
Curve (Activity Assignment)
Curve
The resource's units and costs distributed over the duration of an activity.
Data Date (Project)
Data Date
The progress point, or "as-of date", for activities in the project. Project status is up-to-date as of the data date. You can set the data date when you schedule the project, or you can set it manually.
The data date is also used for updating the dates of scope assignments and work packages when they are not linked to activities.
Date Identified (Task Constraint)
Date Identified
The date the constraint was first identified as an impediment to completing a task.
Date Needed (Task Constraint)
Date Needed
The date the constraint needs to be resolved by to prevent a delay in the completion of the tasks or task milestones that are dependent on it.
Date Submitted (Potential Change Order)
Date Submitted
The date the question was submitted.
Delivered Date (Task Constraint)
Delivered Date
The date the responsible party actually resolved the constraint.
Distributed (Funds)
Distributed
The amount of money that has been distributed for the fund.
Distributed Approved Budget (Budget Planning)
Distributed Approved Budget
The amount of approved budget currently allocated across the project timescale.
Distributed Approved Budget
The amount of approved budget currently allocated to projects included in the portfolio's budget plan.
Distributed Approved Budget (Budget Planning)
Distributed Approved Budget
The amount of approved budget currently allocated to projects included in the portfolio's budget plan.
Distributed Approved Budget (Project Budget)
Distributed Approved Budget
The amount of approved budget currently allocated across the project timescale. This value is based on the base currency with specified exchange rate.
Distributed Benefits (Project Budget)
Distributed Benefits
The amount of benefits currently allocated across the project timescale. This value is based on the base currency with specified exchange rate.
Distributed Forecast (Project Budget)
Distributed Forecast
The amount of forecast cost currently allocated across the project timescale. This value is based on the base currency with specified exchange rate.
Distributed Planned Budget (Project Budget)
Distributed Planned Budget
The amount of planned budget allocated across the project timescale. This value is based on the base currency with specified exchange rate.
Distributed Proposed Budget (Budget Planning)
Distributed Proposed Budget
The amount of proposed budget currently allocated across the project timescale.
Distributed Proposed Budget
The amount of proposed budget currently allocated to projects included in the portfolio's budget plan.
Distributed Proposed Budget (Budget Planning)
Distributed Proposed Budget
The amount of proposed budget currently allocated to projects included in the portfolio's budget plan.
Distributed Proposed Budget (Project Budget)
Distributed Proposed Budget
The amount of proposed budget currently allocated across the project timescale. This value is based on the base currency with specified exchange rate.
Distributed Target Budget (Budget Planning)
Distributed Target Budget
The amount of target budget currently allocated to projects included in the portfolio's budget plan.
Drive Activity Dates (Activity Assignment)
Drive Activity Dates
Determines whether new resource or role assignments determine activity dates.
Driving (Activity Relationship)
Driving
Determines whether the relationship is driving. A relationship is driving when the predecessor activity influences the start date of its successor.
Due Date (Task)
Due Date
The date by which the task is expected to be completed.
Duration Percent Complete (Activity)
Duration Percent Complete
The duration percent complete for the activity. Calculated as Planned Duration minus Remaining Duration divided by Planned Duration multiplied by 100.
Duration Percent of Planned (Activity)
Duration Percent of Planned
The actual duration percent of planned duration for the activity. Calculated as Actual Duration divided by Original BL Duration multiplied by 100.
EAC Cost (Scope Assignment)
EAC Cost
Calculated as ETC Cost plus Actual Cost to Date.
EAC Cost (Work Package)
EAC Cost
The total cost estimated to be earned as the completion of the work package.
Calculated as ETC Cost plus Actual Cost to Date.
This is the cumulative value for all scope assignments in the work package.
EAC Hours (Scope Assignment)
EAC Hours
Calculated as ETC Hours plus Actual Hours to Date.
EAC Hours (Work Package)
EAC Hours
The total hours estimated to be earned at the completion of the work package.
Calculated as ETC Hours plus Actual Hours to Date.
This is the cumulative value for all scope assignments in the work package.
EAC Quantity (Scope Assignment)
EAC Quantity
The estimate of how much material or product will be installed at completion of the scope assignment work.
Calculated as ETC Quantity plus Actual Quantity to Date.
Early Finish - Deterministic (Risk Analysis)
Early Finish - Deterministic
The activity early finish at the time the risk analysis was run.
Early Finish (Activity)
Early Finish
The earliest possible date the activity can finish.
This date is calculated based on network logic, schedule constraints, and resource availability.
Early Start - Deterministic (Risk Analysis)
Early Start - Deterministic
The activity early start at the time the risk analysis was run.
Early Start (Activity)
Early Start
The earliest possible date the remaining work for the activity can begin.
This date is calculated based on network logic, schedule constraints, and resource availability.
Earned Cost (Scope Assignment)
Earned Cost
Calculated as Performance Percent Complete multiplied by BAC Cost.
Earned Cost (Work Package)
Earned Cost
The portion of the budgeted cost that is currently earned for the work package.
Calculated as Performance Percent Complete multiplied by BAC Cost.
This is the cumulative value for all scope assignments in the work package.
Earned Hours (Scope Assignment)
Earned Hours
Calculated as Performance Percent Complete multiplied by BAC Hours.
Earned Hours (Work Package)
Earned Hours
The portion of budgeted hours that is currently earned for the work package.
Calculated as Performance Percent Complete multiplied by BAC Hours.
This is the cumulative value for all scope assignments in the work package.
Earned Percent Complete (Work Package)
Earned Percent Complete
Calculated as Earned Hours divided by BAC Hours for all scope assignments in the work package.
Earned Quantity (Scope Assignment)
Earned Quantity
The amount of material or product that has been installed based on the Performance Percent Complete of the scope assignment and the Budget At Completion Quantity.
Calculated as Performance Percent Complete multiplied by BAC Quantity.
Earned Value Cost (Activity)
Earned Value Cost
The approved budget for work actually completed by the specified project data date.
Calculated as Budget At Completion multiplied by Performance Percent Complete. The method for computing performance percent complete depends on the Earned Value technique defined in the project settings.
Earned Value Cost
The approved budget for work actually completed by the specified project data date.
Earned Value Cost (Activity)
Earned Value Cost
The approved budget for work actually completed by the specified project data date.
Earned Value Cost (Project Budget)
Earned Value Cost
The value of work performed on a project in reference to the approved budget for the project.
The cost value used for the Earned Value Management of a project.
Earned Value Management allows project managers to quantify project progress and objectively measure a project's success.
This value can be entered manually or can be imported. This value is based on the base currency with specified exchange rate.
Earned Value Cost (Schedule)
Earned Value Cost
The approved budget for work actually completed by the specified project data date.
Earned Value Labor Units (Activity)
Earned Value Labor Units
The portion of baseline labor units that are actually completed as of the project data date.
Calculated as Budget At Completion Labor Units multiplied by Performance Percent Complete. The performance percent complete will be calculated using the activity percent complete.
Earned Value Labor Units (Schedule)
Earned Value Labor Units
The portion of baseline labor units that are complete as of the project data date.
Earned Value Period Cost (Activity)
Earned Value Period Cost
The incremental value of the approved budget for work actually completed by the specified project data date.
Earned Value Period Units (Activity)
Earned Value Period Units
The incremental value of the earned value units for work actually completed by the specified project data date.
Earned Value Units (Activity)
Earned Value Units
The earned value units for work actually completed by the specified project data date.
Effective Finish (Scope Assignment)
Effective Finish
The latest date of all Actual to Date and Actual Cost to Date values for the scope assignment.
This is a read-only field.
Effective Finish (Scope Item)
Effective Finish
The latest Effective Finish date for Actual to Date values of all scope item's scope assignments.
Effective Finish (Work Package)
Effective Finish
The latest Effective Finish date of all scope assignments in the work package.
This is a read-only field.
Effective Start (Scope Assignment)
Effective Start
The earliest date of all Actual Hours to Date and Actual Cost to Date values for the scope assignment.
This is a read-only field.
Effective Start (Scope Item)
Effective Start
The earliest Effective Start date for Actual to Date values of all the scope item's scope assignments.
Effective Start (Work Package)
Effective Start
The earliest Effective Start date of all scope assignments in the work package.
This is a read-only field.
Effective Start Date (Resource/Role)
Effective Start Date
The date that the corresponding units/time period and rates go into effect for the resource or role.
Effective Start Date
The start date of the work rate.
Effective Start Date (Resource/Role)
Effective Start Date
The start date of the work rate.
End Date (Funds)
End Date
The date when money in the fund will no longer be available.
Estimate At Completion (EAC) (Activity)
Estimate At Completion (EAC)
The forecasted cost of the project as the project progresses.
Estimate At Completion (EAC) Labor Units (Activity)
Estimate At Completion (EAC) Labor Units
The estimated labor units at completion.
Calculated as Actual Labor Units plus Estimate To Complete Labor Units. Estimate To Complete Labor Units is calculated based off of the Earned Value setting.
Estimate At Completion (EAC) Labor Units (Schedule)
Estimate At Completion (EAC) Labor Units
The estimated labor units at completion of the activity. Calculated as Actual Labor Units plus Estimated to Completion Labor Units.
Estimate at Completion (Project Budget)
Estimate at Completion
The expected total cost of the project when the defined scope of work will be completed.
This value can be entered manually or can be imported. This value is based on the base currency with specified exchange rate.
Estimate To Complete (ETC) (Activity)
Estimate To Complete (ETC)
The estimated cost to complete the activity.
Estimate To Complete (ETC) Labor Units (Schedule)
Estimate To Complete (ETC) Labor Units
The estimated quantity to complete the activity, WBS, or project.
Estimate to Complete (Project Budget)
Estimate to Complete
The estimated cost needed to complete the project.
This value can be entered manually or can be imported. This value is based on the base currency with specified exchange rate.
Estimate To Complete (Schedule)
Estimate To Complete
The estimated cost to complete the Activity, WBS or Project.
Estimate To Complete Performance Index (TCPI) (Activity)
Estimate To Complete Performance Index (TCPI)
The cost performance index value that must be achieved in order to complete the remaining work on budget.
This is a measure of the efficiency required on the future performance of the project. A value greater than 1 indicates that the work is over budget and more effort will be required to reduce costs or increase earned value. A value less than 1 indicates the work is under budget and that the current effort is sufficient enough to meet the budget at completion.
Calculated as (Budget At Completion - Earned Value) / (Estimate At Completion - Actual Cost).
Estimate To Complete Performance Index (TCPI) (Schedule)
Estimate To Complete Performance Index (TCPI)
The Estimate To Complete Performance Index is calculated as (Budget at Completion - Earned Value) / (Estimate at Completion - Actual Cost).
Estimated Commitment Changes (Actual Risk Response Cost)
Estimated Commitment Changes
The sum of all estimates for commitments.
Estimated Commitment Changes (Cost Sheet)
Estimated Commitment Changes
The sum of all estimates for commitments.
Estimated Contract Changes (Actual Risk Response Cost)
Estimated Contract Changes
The sum of all estimates for contracts.
Estimated Contract Changes (Cost Sheet)
Estimated Contract Changes
The sum of all estimates for contracts.
ETC Cost (Scope Assignment)
ETC Cost
The estimate of the cost needed to complete the work.
Calculated as BAC Cost minus Earned Cost.
ETC Cost (Work Package)
ETC Cost
The estimate of the cost needed to complete the work.
Calculated as BAC Cost minus Earned Cost.
This is the cumulative value for all scope assignments in the work package.
ETC Hours (Scope Assignment)
ETC Hours
The estimated number of hours needed to complete the work.
Calculated as BAC Hours minus Earned Hours.
ETC Hours (Work Package)
ETC Hours
The estimated number of hours needed to complete the work.
Calculated as BAC Hours minus Earned Hours.
This is the cumulative value for all scope assignments in the work package.
ETC Quantity (Scope Assignment)
ETC Quantity
The estimate of how much quantity is needed to complete the work.
Calculated as BAC Quantity minus Earned Quantity.
Evaluation Score
Evaluation Score
The quantitative score of an idea based on the qualitative ranking of ideas against different evaluation categories. This value is used by workspace managers to prioritize ideas.
Evaluation Score (Program)
Evaluation Score
The quantitative score of a program based on the qualitative ranking of programs against different evaluation categories. This value is used by portfolio managers to prioritize programs.
Evaluation Score (Project)
Evaluation Score
The quantitative score of a project based on the qualitative ranking of projects against different evaluation categories. This value is used by portfolio managers to prioritize projects.
Exchange Rate (Change Order)
Exchange Rate
The rate of exchange between the currency of the change order line item and the base currency, if the currencies are different. If the currencies are the same, this field is disabled.
Exchange Rate
The rate of exchange between the currency of the change order line item and the base currency, if the currencies are different. If the currencies are the same, this field is disabled.
Exchange Rate (Change Order)
Exchange Rate
The rate of exchange between the currency of the change order line item and the base currency, if the currencies are different. If the currencies are the same, this field is disabled.
Exchange Rate (Commitment)
Exchange Rate
The rate of exchange between the currency of the commitment line item and the base currency, if the currencies are different. If the currencies are the same, this field is disabled.
Exchange Rate
The rate of exchange between the currency of the commitment and the base currency, if the currencies are different. If the currencies are the same, this field is disabled.
Exchange Rate (Commitment)
Exchange Rate
The rate of exchange between the currency of the commitment and the base currency, if the currencies are different. If the currencies are the same, this field is disabled.
Exchange Rate (Contract)
Exchange Rate
The rate of exchange between the currency of the contract and the base currency, if the currencies are different. If the currencies are the same, this field is disabled.
Exchange Rate
The rate of exchange between the currency of the contract line item and the base currency, if the currencies are different. If the currencies are the same, this field is disabled.
Exchange Rate (Contract)
Exchange Rate
The rate of exchange between the currency of the contract line item and the base currency, if the currencies are different. If the currencies are the same, this field is disabled.
Exchange Rate (Payment Application)
Exchange Rate
The rate of exchange between the currency of the payment application and the base currency, if the currencies are different. If the currencies are the same, this field is disabled.
Exchange Rate (Potential Change Order)
Exchange Rate
The exchange rate of the potential change order.
Exposure Finish Date (Risk)
Exposure Finish Date
The latest finish date of the activities the risk is mapped to. If the risk is not mapped to any activities, it is the project scheduled finish date.
Exposure Start Date (Risk)
Exposure Start Date
The earliest start date of the activities that the risk is mapped to. If the risk is not mapped to any activities, it is the date at which the schedule is progressed (Data Date).
Financial Impact (Potential Change Order)
Financial Impact
The financial impact of the potential change order proposal.
Financial Impact
The financial impact of the potential change order.
Financial Impact (Potential Change Order)
Financial Impact
The financial impact of the potential change order.
Finish - Deterministic (Risk Analysis)
Finish - Deterministic
The activity finish date at the time the risk analysis was run.
Finish (Activity Assignment)
Finish
The finish date for the assignment.
Finish (Activity)
Finish
The current finish date for the activity.
Finish (Budget Planning)
Finish
The finish date for each cost curve row.
The Finish displays the end date of the corresponding cost curve type.
For example, the Finish for a Current Approved Budget row is the Current Approved Budget Finish date.
Finish Date (Activity)
Finish Date
The reporting period finish date.
Finish Date (Commitment)
Finish Date
The date when the work represented by the commitment is expected to be finished.
Finish Date (Contract)
Finish Date
The date by which the work contracted is scheduled to be finished. The Finish Date value is not affected by project calendars.
Float Path (Activity)
Float Path
A number calculated by the scheduler which identifies the float path that each activity is on. The number starts from 1 (where 1 is most critical) to the max number of float paths identified by the scheduler.
Float Path Order (Activity)
Float Path Order
Order that the activities were processed within each float path.
Forecast (Present Value) (Project Budget)
Forecast (Present Value)
The present value, also known as the discounted value, of the overall project forecast. Future cash flows are discounted using the project's annual discount rate. Portfolio managers can use the present value of a project's expected cash flow as a metric during project prioritization and selection. This value is based on the base currency with specified exchange rate.
Forecast (Project Budget)
Forecast
The total estimation of a project's remaining costs.
Once projects have begun, project managers update the project forecast to represent remaining cost estimates for the duration of the project's life cycle. This value is based on the base currency with specified exchange rate.
Forecast Finish (Project)
Forecast Finish
The planned finish date of a project's remaining Forecast cost.
Forecast Finish Date (Program)
Forecast Finish Date
The planned finish date of a program's remaining Forecast cost.
Forecast Start (Project)
Forecast Start
The planned start date of a project's remaining Forecast cost.
Forecast Start Date (Program)
Forecast Start Date
The planned start date of a program's remaining Forecast cost.
Free Float - Deterministic (Risk Analysis)
Free Float - Deterministic
The activity free float at the time the risk analysis was run.
Free Float (Activity)
Free Float
The amount of time the activity can be delayed before delaying the start date of any successor activity.
From Budget Change (Budget Item)
From Budget Change
Indicates whether the budget item originated in a budget change.
From Company (Change Order)
From Company
The company that awarded the change order.
From Company (Commitment)
From Company
The company that awarded the commitment.
From Company (Contract)
From Company
The company that awarded the contract.
From Company (Payment Application)
From Company
The company that awarded the payment application.
From Company (Potential Change Order)
From Company
The company that awarded the potential change order.
From Contact (Change Order)
From Contact
The person in the Awarded From company who is officially responsible for communications about the associated agreement.
From Contact (Commitment)
From Contact
The person at the Awarded From Company who is officially responsible for communications about the commitment.
From Contact (Contract)
From Contact
The person in the Awarded By company who is officially responsible for communications about the contract.
From Contact (Payment Application)
From Contact
The user at the company that awarded the payment application who is responsible for communications about the payment application.
From Contact (Potential Change Order)
From Contact
The person at the Awarded From company who is officially responsible for communications about the potential change order.
From Contact Title (Change Order)
From Contact Title
The title of the person in the Awarded From company who is officially responsible for communications about the associated agreement.
High Value (Thresholds)
High Value
The cost measured by the threshold.
Use threshold operators to compare this value to the values in projects and portfolios.
High Value
The High Value is only editable if Value is selected and the threshold operator is set to "within range" or "not within range".
High Value allows you to set a maximum value other threshold values can be measured against.
High Value
The High Value is only editable if Value is selected and the threshold operator is set to "within range" or "not within range".
High Value allows you to set a maximum value other threshold values can be measured against.
High Value (Thresholds)
High Value
The High Value is only editable if Value is selected and the threshold operator is set to "within range" or "not within range".
High Value allows you to set a maximum value other threshold values can be measured against.
High Value
The High Value is only editable if Value is selected and the threshold operator is set to "within range" or "not within range".
High Value allows you to set a maximum value other threshold values can be measured against.
High Value (Thresholds)
High Value
The High Value is only editable if Value is selected and the threshold operator is set to "within range" or "not within range".
High Value allows you to set a maximum value other threshold values can be measured against.
Hours (Budget Item)
Hours
The number of hours needed to complete the budget item. Calculated as Production Rate multiplied by Quantity.
Hours (Budget Transaction)
Hours
The number of hours needed to complete the budget details line item. Calculated as Production Rate multiplied by Quantity.
Hours Weight (Scope Assignment)
Hours Weight
This value is used to calculate Scope Percent Complete at the work package level if Scope Percent Complete Weight Method is set to Hours.
Calculated as Scope Percent Complete times Revised Hours.
Impacted Date (Risk)
Impacted Date
The date the risk impacted the project.
Incremental Actual Cost To Date (Scope Assignment)
Incremental Actual Cost To Date
The cost incurred on the scope assignment since the last progress date. This amount is added to the value for Cumulative Actual Cost to Date.
Incremental Actual Hours To Date (Scope Assignment)
Incremental Actual Hours To Date
The number of hours spent on this scope assignment since the last progress date. This value is added to Cumulative Actual Hours to Date.
Incremental Installed Cost (Scope Assignment)
Incremental Installed Cost
The total cost incurred on the scope assignment as of the current date.
If Rate By is set to Hours, then Installed Cost equals Revised Cost Rate multiplied by Installed Hours.
If Rate By is set to Quantity, then Installed Cost equals Revised Cost Rate multiplied by Installed Quantity.
Incremental Installed Hours (Scope Assignment)
Incremental Installed Hours
Hours spent on the scope assignment.
Calculated as Installed Quantity multiplied by Revised Productivity Rate.
Incremental Installed Quantity (Scope Assignment)
Incremental Installed Quantity
That amount of material or product that has been installed since the last progress date.
Installed Cost (Scope Assignment)
Installed Cost
The total cost incurred on the scope assignment as of the current date.
If Rate By is set to Hours, then Installed Cost equals Revised Cost Rate multiplied by Installed Hours.
If Rate By is set to Quantity, then Installed Cost equals Revised Cost Rate multiplied by Installed Quantity.
Installed Cost (Work Package)
Installed Cost
The total cost incurred on the scope assignment as of the current date.
If Rate By is set to Hours, then Installed Cost equals Revised Cost Rate multiplied by Installed Hours.
If Rate By is set to Quantity, then Installed Cost equals Revised Cost Rate multiplied by Installed Quantity.
This is the cumulative value for all scope assignments in the work package.
Installed Finish (Scope Assignment)
Installed Finish
The date work on the scope assignment completed.
The latest date of all Installed Quantity values for the scope assignment when Scope Percent Complete equals 100%.
This field is used to spread Installed data fields.
Installed Finish (Work Package)
Installed Finish
The date work on the work package is complete.
This is the latest Installed Finish date of all scope assignments in the work package.
Installed Hours (Scope Assignment)
Installed Hours
Hours spent on the scope assignment.
Calculated as Installed Quantity multiplied by Revised Productivity Rate.
Installed Hours (Work Package)
Installed Hours
Hours spent on the scope assignment.
Calculated as Installed Quantity multiplied by Revised Productivity Rate.
This is the cumulative value for all scope assignments in the work package.
Installed Quantity (Scope Assignment)
Installed Quantity
The amount of material or product that has been installed to date.
If the Progress Measure on the work package is set to Milestone Percent Complete, then Installed Quantity equals Revised Quantity multiplied by Milestone Progress Percent Complete.
This field can be manually overridden if the Progress Measure is set to Physical Percent Complete, then Installed Quantity is manually entered and not calculated.
Installed Quantity (Scope Item)
Installed Quantity
The amount of material or product that has been installed to date.
This is the cumulative value for all scope assignments created for the scope item.
Installed Start (Scope Assignment)
Installed Start
The date work on the scope assignment began.
This is the earliest date of all Installed Quantity values for the scope assignment.
This field is used to spread Installed data fields.
Installed Start (Work Package)
Installed Start
The date work on the work package began.
This is the earliest Installed Start date of all scope assignments in the work package.
Internal Rate of Return (Program Budget)
Internal Rate of Return
The quantitative measurement used to compare the profitability of program investments.
The rate at which investors will receive returns on their investments in a program.
This value can be entered manually or can be imported.
Internal Rate of Return (Project Budget)
Internal Rate of Return
The quantitative measurement used to compare the profitability of project investments.
The rate at which investors will receive returns on their investments in a project.
This value can be entered manually or can be imported.
Iteration Combined Schedule Risk Factor
Iteration Combined Schedule Risk Factor
For the iteration, the combined schedule impact percentage for all risk factors impacting the activity. Stored for first 50 iterations only.
Iteration Remaining Duration - Uncertainty Only
Iteration Remaining Duration - Uncertainty Only
For the iteration, the activity remaining duration after any duration uncertainty impact prior to any other schedule impacts. Stored for first 50 iterations only.
Iteration Risk Factor Cost Impact
Iteration Risk Factor Cost Impact
For the iteration, the activity cost change due to any risk factor cost impacts. This does not include any cost impacts caused by schedule impacts. Stored for first 50 iterations only.
Iteration Risk Factor Schedule Cost Impact
Iteration Risk Factor Schedule Cost Impact
For the iteration, the activity cost change due to any risk factor schedule impacts. Stored for first 50 iterations only.
Iteration Risk Factor Schedule Impact
Iteration Risk Factor Schedule Impact
For the iteration, the change in the activity remaining duration due to risk factors impacting the activity. Stored for the first 50 iterations only.
Labor Rate (Budget Item)
Labor Rate
The cost per labor hour of the budget line item.
Labor Rate (Budget Transaction)
Labor Rate
The cost per labor hour of the budget line item detail.
Labor Rate (Program Budget Item)
Labor Rate
The cost per labor hour of the budget line item.
Labor Rate (Program Budget Transaction)
Labor Rate
The cost per labor hour of the budget line item detail.
Labor Units Percent Complete (Activity)
Labor Units Percent Complete
The percent complete of units for all labor resources for the activity. Calculated as Actual Labor Units divided by At Completion Labor Units multiplied by 100.
Lag - Use Only Work Days (Task)
Lag - Use Only Work Days
Allows user to set whether or not lag can fall on project calendar's nonwork days.
Lag (Activity Relationship)
Lag
The amount of time the predecessor activity was delayed, affecting the ability of its successor activity to start or finish.
Lag (Risk Analysis)
Lag
The relationship lag at the time the risk analysis was run.
Lag (Task)
Lag
The amount of time a successor task is required to be delayed with respect to a predecessor task in a hand-off, in hours.
Last Status Action (Contracts and Commitments)
Last Status Action
The last status of the agreement, change, or payment application.
Late Finish - Deterministic (Risk Analysis)
Late Finish - Deterministic
The activity late finish at the time the risk analysis was run.
Late Finish (Activity)
Late Finish
The latest possible date the activity can finish without delaying the project finish date.
This date is calculated based on activity relationships, schedule constraints, and resource availability.
Late Start - Deterministic (Risk Analysis)
Late Start - Deterministic
The activity late start at the time the risk analysis was run.
Late Start (Activity)
Late Start
The latest possible date the remaining work for the activity can begin without delaying the project finish date.
This date is calculated based on activity relationships, schedule constraints, and resource availability.
Line Item ID (Commitment)
Line Item ID
The unique identifier for the line item.
Link Forecast to Actuals (Program)
Link Forecast to Actuals
Enables you to link program Forecast data to program Actuals data.
When linked, any updates to the program's Actuals values will automatically be applied to the program's Forecast values.
Longest Path - Deterministic (Risk Analysis)
Longest Path - Deterministic
The activity longest path value at the time the risk analysis was run.
Manual Completed Weight (Scope Assignment)
Manual Completed Weight
Calculated as Scope Percent Complete multiplied by Manual Weight.
Manual Weight (Scope Assignment)
Manual Weight
The value used to calculate manual completed weight when progress needs to be weighed against a factor other than quantity, hours, or cost.
This is a manual entry field when Scope Percent Complete Weight Method is set to Manual.
Max Units/Time (Resource/Role)
Max Units/Time
The maximum work units per time the resource or role can perform on all their assigned activities
For example, if the selected resource is one person, a reasonable value may be 8 hours (units) per day (duration). In this case, the Max Units/Time would be 8.00h/d, or 8 hours of work per day. Similarly, if the selected resource is a department with 5 people, then the Max Units/Time may be 40.00h/d. This means that 5 people can perform 40 hours of work per day, rather than 1 person performing 8 hours of work per day.
Max Units/Time
Maximum units per time for the work rate.
Max Units/Time (Resource/Role)
Max Units/Time
Maximum units per time for the work rate.
Maximum Duration (Risk Analysis)
Maximum Duration
The activity maximum duration at the time the risk analysis was run.
Milestone Percent Complete (Scope Assignment)
Milestone Percent Complete
The user entered percentage complete for the individual milestones for the scope assignment.
Milestone Progress Percent Complete (Scope Assignment)
Milestone Progress Percent Complete
The percentage complete for all milestones for the scope assignment. The calculation is based on the user entered percentage complete for the milestone and the rules defined for the milestone calculations.
Minimum Duration (Risk Analysis)
Minimum Duration
The activity minimum duration at the time the risk analysis was run.
Most Likely Duration (Risk Analysis)
Most Likely Duration
The activity most likely duration at the time the risk analysis was run.
Net Present Value (Project Budget)
Net Present Value
The difference between the present value (PV) of the future cash flows from current investments and project costs.
The Net Present Value accounts for changes in inflation and returns when calculating the difference in value of incoming and outgoing capital.
Positive Net Present Value (NPV) is an indicator of projects that should be pursued.
This value can be entered manually or can be imported. This value is based on the base currency with specified exchange rate.
Nonlabor Units Percent Complete (Activity)
Nonlabor Units Percent Complete
The percent complete of units for all nonlabor resources for the activity. Calculated as Actual Nonlabor Units divided by At Completion Nonlabor Units multiplied by 100.
Non-Working Percentage (Risk Weather)
Non-Working Percentage
The percentage of non-working days in the period.
Non-Working Persistence (Risk Weather)
Non-Working Persistence
The probability of a non-working day following another non-working day in the period.
Non-Working Time Definition (Risk Weather)
Non-Working Time Definition
The method used to define the weather risk's non-working time. Valid values are Percentage and Distribution.
Operator (Thresholds)
Operator
The logical operator for the threshold.
Values are measured against this logic.
For example, a threshold with an operator of Equals will only display an indicator if the budget plan or project value it measures equals the value set in the threshold.
Original Committed Due Date (Task)
Original Committed Due Date
The original due date of the task commitment.
Original Cost (Budget Item)
Original Cost
The original cost of the budget line item.
Original Cost (Program Budget Item)
Original Cost
The original cost of the budget line item.
Original Cost (Scope Assignment)
Original Cost
The original cost of the scope assignment.
If Rate By is set to Hours, then Original Cost equals Original Hours multiplied by Original Cost Rate. If this value is entered manually, then Original Cost Rate is recalculated to equal Original Cost divided by Original Hours.
If Rate By is set to Quantity, then Original Cost equals Original Quantity multiplied by Original Cost Rate. If this value is entered manually, then Original Cost Rate is recalculated to equal Original Cost divided by Original Quantity.
Original Cost (Work Package)
Original Cost
The original cost of the scope assignment.
If Rate By is set to Hours, then Original Cost equals Original Hours multiplied by Original Cost Rate. If this value is entered manually, then Original Cost Rate is recalculated to equal Original Cost divided by Original Hours.
If Rate By is set to Quantity, then Original Cost equals Original Quantity multiplied by Original Cost Rate. If this value is entered manually, then Original Cost Rate is recalculated to equal Original Cost divided by Original Quantity.
This is the cumulative value for all scope assignments in the work package.
Original Cost Rate (Scope Assignment)
Original Cost Rate
The cost rate used in the cost calculation of the scope assignment.
If Rate By is set to Hours and the Original Cost value is entered manually, then Original Cost Rate equals Original Cost divided by Original Hours.
If Rate By is set to Quantity and the Original Cost value is entered manually, then Original Cost Rate equals Original Cost divided by Original Quantity.
Original Finish (Scope Assignment)
Original Finish
The date the work on the scope assignment is scheduled to finish.
This field is populated with the work package's Original Finish date, but it can be manually modified until the original baseline is set.
If there is no activity link, the field is locked when the original baseline is set.
If there is an activity link, before the original baseline is set the field is populated with the activity's Planned Finish. After the baseline is set, the field is locked.
If the Data Date is specified after the Original Finish date is set and the Original Start date is before the Data Date, the application sets the Original Finish date to be the same date relative to Original Start before the Data Date was modified when the Modify Dates feature is run.
Original Finish (Work Package)
Original Finish
The date the work on the work package is scheduled to finish.
This field is populated with the Data Date plus 4 days when the work package is created, but it can be manually modified until the Original Baseline is set.
If the Data Date is specified after the Original Finish date is set and the Original Start date is before the Data Date, the application sets the Original Finish date to be the same date relative to Original Start before the Data Date was modified when the Modify Dates feature is run.
If there is no activity link, the field is locked when the original baseline is set.
If there is an activity link, before the original baseline is set the field is populated with the earliest Planned Finish date of all linked activities. After the baseline is set, the field is locked.
Original Hours (Scope Assignment)
Original Hours
The original expected hours needed to complete all the work required to install the material quantity on the scope assignment.
Calculated as Original Quantity multiplied by Original Productivity Rate.
Before the baseline is set, this field can be entered manually. A manual entry recalculates the Original Productivity Rate to equal Original Hours divided by Original Quantity.
Original Hours (Scope Item)
Original Hours
The original expected hours needed to complete all the work on a scope item.
Calculated as Original Quantity multiplied by Original Productivity Rate.
Original Hours (Work Package)
Original Hours
The original expected hours needed to complete all the work required to install the material quantity on the scope assignment.
Calculated as Original Quantity multiplied by Original Productivity Rate.
Before the baseline is set, this field can be entered manually. A manual entry recalculates the Original Productivity Rate to equal Original Hours divided by Original Quantity.
This is the cumulative value for all scope assignments in the work package.
Original Productivity Rate (Scope Assignment)
Original Productivity Rate
The number of hours it takes to install or assemble the product or material per unit. Defaults to the scope item's Original Productivity Rate, but can be updated for each scope item assignment.
Calculated as Original Hours divided by Original Quantity.
If this field is updated, Original Hours is recalculated to equal Original Quantity multiplied by Original Productivity Rate.
Original Productivity Rate (Scope Item)
Original Productivity Rate
The number of hours required to install or assemble a single quantity of the scope item material or product.
For example, if the product is 1,000 feet of cable it may be estimated to take 2 hours install one foot of cable.
Calculated as Original Hours divided by Original Quantity.
Original Quantity (Scope Assignment)
Original Quantity
The expected amount of material or product required.
Original Quantity
The expected amount of material or product required.
Original Quantity (Scope Assignment)
Original Quantity
The expected amount of material or product required.
Original Quantity (Scope Item)
Original Quantity
The original expected amount of material or product required for a scope item.
Original Start (Scope Assignment)
Original Start
The date the work on the scope assignment is scheduled to begin.
This field is populated with its work package's Original Start, but can be manually modified until the original baseline is set.
If there is no activity link, the field is locked when the original baseline is set.
If there is an activity link, before the original baseline is set the field is populated with the activity's Planned Start. After the baseline is set, the field is locked.
If the Data Date is specified, the date cannot be set to a date earlier than the Data Date.
If the Data Date is specified after the Original Start date is set and the Original Start date is before the Data Date, the Original Start date inherits the Data Date when the Modify Dates feature is run.
Original Start (Work Package)
Original Start
The date the work on the work package is scheduled to begin.
This field is populated with the Data Date with the work package is created, but it can be manually modified until the Original Baseline is set.
If the Data Date is specified, Original Start cannot be set to a date earlier than the Data Date. If the Data Date is specified after the Original Start date is set and the Original Start date is before the Data Date, the Original Start is populated with the Data Date when the Modify Dates feature is run.
If there is no activity link, this field is locked when the original baseline is set.
If there is an activity link, before the original baseline is set this field is populated with the earliest Planned Start dates of all linked activities. After the baseline is set, the field is locked.
Original Value (Commitment)
Original Value
The value of the cost the first time it was saved.
Original Value (Contract)
Original Value
The value of the cost the first time it was saved.
Parent Schedule of Values (Change Order)
Parent Schedule of Values
The unique identifier for the parent schedule of values.
Parent Schedule of Values (Contract)
Parent Schedule of Values
The unique identifier for the parent schedule of values.
Payback Period (Project Budget)
Payback Period
The estimate of the length of time that will transpire before net profits recover the initial and periodic costs of an investment to carry out the selected project.
This value can be entered manually or can be imported.
Pending Actuals (Cost Sheet)
Pending Actuals
The total of all actuals values with a status of Pending.
Pending Change Cost (Scope Assignment)
Pending Change Cost
Calculated as the sum of all pending cost changes in the change records for the scope assignment.
Pending Change Cost (Work Package)
Pending Change Cost
Calculated as the sum of all pending cost changes in the change records for the scope assignment.
This is the cumulative value for all scope assignments in the work package.
Pending Change Hours (Scope Assignment)
Pending Change Hours
Calculated as the sum of all pending hour changes in the change records for the scope assignment.
Pending Change Hours (Scope Item)
Pending Change Hours
The total number of hours waiting for approval on a scope item.
Pending Change Hours (Work Package)
Pending Change Hours
Calculated as the sum of all pending hour changes in the change and transfer records for the scope assignment.
This is the cumulative value for all scope assignments in the work package.
Pending Change Quantity (Scope Assignment)
Pending Change Quantity
The sum of all pending change quantities in the change records for the scope assignment.
Pending Change Quantity (Scope Item)
Pending Change Quantity
The total quantity waiting for approval on a scope item.
Pending Commitment Changes (Actual Risk Response Cost)
Pending Commitment Changes
The sum of all pending cost changes in the change records for the commitment.
Pending Commitment Changes (Cost Sheet)
Pending Commitment Changes
The total value of all pending commitment change orders except for rejected and canceled change orders.
Pending Commitment Potential Change Orders (Actual Risk Response Cost)
Pending Commitment Potential Change Orders
The sum of all pending potential change orders for commitments.
Pending Commitment Potential Change Orders (Cost Sheet)
Pending Commitment Potential Change Orders
The sum of all pending potential change orders for commitments.
Pending Commitments (Actual Risk Response Cost)
Pending Commitments
The total cost of all pending commitments.
Pending Commitments (Cost Sheet)
Pending Commitments
The total value of all pending commitment line items in the project.
Pending Contract Changes (Actual Risk Response Cost)
Pending Contract Changes
The total cost for all pending changes in contracts.
Pending Contract Changes (Cost Sheet)
Pending Contract Changes
The total cost for all pending changes in contracts.
Pending Contract Potential Change Orders (Actual Risk Response Cost)
Pending Contract Potential Change Orders
The sum of all pending potential change orders for contracts.
Pending Contract Potential Change Orders (Cost Sheet)
Pending Contract Potential Change Orders
The sum of all pending potential change orders for contracts.
Pending Contracts (Actual Risk Response Cost)
Pending Contracts
The total cost for all pending contracts.
Pending Contracts (Cost Sheet)
Pending Contracts
The total cost for all pending contracts.
Pending Revenue (Actual Risk Response Cost)
Pending Revenue
Revenue that has been submitted for review but has not been approved or rejected.
Pending Revenue (Cost Sheet)
Pending Revenue
The total of all This Period values from all payment applications with a status of Pending.
Pending Spends (Actual Risk Response Cost)
Pending Spends
Spends that have been submitted for review but not approved or rejected.
Pending Spends (Cost Sheet)
Pending Spends
Sum of the Current Payment Due values of all commitment payment applications that have a status of Pending and that are linked to a commitment record associated with the contract.
Percent Complete (Commitment)
Percent Complete
The percent of work completed on the line item based on the completed and stored to date value in the payment application.
Percent Complete (Contract)
Percent Complete
The completion status of the schedule of values.
Percent Complete (Project)
Percent Complete
The estimated percentage of work that has been completed on the project. This value is entered by the user.
Percent Complete Type (Activity)
Percent Complete Type
Determines the way in which the application calculates the percent complete for the activity.
Physical: Percent complete is manually entered by a user based on the amount of physical work completed on the activity.
Duration: Percent complete is calculated from the actual and remaining duration.
Units: Percent complete is calculated from the actual and remaining units.
Scope: The percent complete for the activity is derived from the scope percent complete of the linked scope assignments.
Performance Percent Complete (Schedule)
Performance Percent Complete
The percentage of the activity planned work that is currently complete.
Performance Percent Complete (Scope Assignment)
Performance Percent Complete
Calculated as Installed Quantity divided by At Completion Quantity.
Performance Period (Commitment)
Performance Period
The period between the commitment start and finish dates. If this value is changed, the Finished Date value adjusts automatically. If the Start Date or Finish Date changes, this value adjusts automatically.
Performance Period (Contract)
Performance Period
The period between the contract start and finish dates. If this value is changed, the Finished Date value adjusts automatically. If the start or finish dates are changed, this value adjusts automatically.
Period Actual Labor Cost (Schedule)
Period Actual Labor Cost
The aggregation of all labor costs incurred during the current financial period.
Period Actual Labor Units (Schedule)
Period Actual Labor Units
The number of labor units used during this financial period.
Period Actual Material Cost (Schedule)
Period Actual Material Cost
The aggregation of all material costs incurred during the current financial period.
Period Actual Nonlabor Cost (Schedule)
Period Actual Nonlabor Cost
The aggregation of all nonlabor costs incurred during the current financial period.
Period Actual Nonlabor Units (Schedule)
Period Actual Nonlabor Units
The nonlabor units used during this financial period.
Period Actual Total Cost (Schedule)
Period Actual Total Cost
The aggregation of all labor, nonlabor, material and direct activity costs (expenses) incurred during this financial period.
Period Applied (Change Order)
Period Applied
The billing period of the payment application to which the change order schedule of values is applied.
Period Applied
The billing period of the payment application to which the change order schedule of values is applied.
Period Applied (Change Order)
Period Applied
The billing period of the payment application to which the change order schedule of values is applied.
Period Applied (Commitment)
Period Applied
The billing period of the payment application to which the change order schedule of values is applied.
Period Applied (Contract)
Period Applied
The billing period of the payment application to which the change order schedule of values is applied.
Period Earned Value Cost (Schedule)
Period Earned Value Cost
The incremental value of the approved budget for work actually completed by the specified project data date.
Period Earned Value Labor Units (Schedule)
Period Earned Value Labor Units
The incremental value of the portion of baseline labor units that are complete as of the project data date.
Period Planned Value Cost (Schedule)
Period Planned Value Cost
The incremental value of the approved budget for the work scheduled to be completed by a specified date.
Period Planned Value Labor Units (Schedule)
Period Planned Value Labor Units
The incremental value of the portion of baseline labor units that are scheduled to be complete as of the project data date.
Period To (Payment Application)
Period To
The end date for the payment application.
Pessimistic Remaining Cost Variance Percentage (Risk Analysis)
Pessimistic Remaining Cost Variance Percentage
The percentage difference between the Pre-Response and Post-Response remaining cost values.
Pessimistic Remaining Duration Variance (Risk Analysis)
Pessimistic Remaining Duration Variance
The duration difference between the Pre-Response and Post-Response remaining duration values.
Pessimistic Remaining Duration Variance Percentage (Risk Analysis)
Pessimistic Remaining Duration Variance Percentage
The percentage difference between the Pre-Response and Post-Response remaining duration values.
Pessimistic Start Variance (Risk Analysis)
Pessimistic Start Variance
The duration difference between the pre-response and post-response pessimistic start date values.
Physical Percent Complete (Activity)
Physical Percent Complete
The activity percent complete, manually entered by a user.
Planned Budget (Present Value) (Project Budget)
Planned Budget (Present Value)
The present value, also known as the discounted value, of the overall project planned budget. Future cash flows are discounted using the project's annual discount rate. Portfolio managers can use present value of a project's expected cash flow as a metric during project prioritization and selection. This value is based on the base currency with specified exchange rate.
Planned Budget (Project Budget)
Planned Budget
The planned total cost of a project as defined by the project manager.
Planners can use Planned Budgets to determine how to allocate a plan's Proposed Budget values to projects, as well as what projects are reasonable to include in the current portfolio budget plan. This value is based on the base currency with specified exchange rate.
Planned Cost (Activity Assignment)
Planned Cost
The expected total cost of the item, such as an assignment, expense, or response plan.
Planned Duration (Activity Assignment)
Planned Duration
The resource's total working time on the activity from the Planned Start date to the Planned Finish date.
Planned Duration (Activity)
Planned Duration
The expected amount of time required to complete an activity.
The planned working time is calculated using the activity's calendar. The duration is measured from the activity's planned start date to its planned finish date.
Planned Duration (Project)
Planned Duration
The duration between Project Planned Start and Project Planned Finish.
This value can be entered manually or can be imported.
Planned Finish (Activity Assignment)
Planned Finish
The date the assignment is scheduled to be finished.
Planned Finish (Activity)
Planned Finish
The date the activity is scheduled to finish if the activity has not started.
This date is calculated by the project scheduler but can be updated manually by the project manager. This date is not changed by the project scheduler after the activity has started.
Planned Finish (Scope Assignment)
Planned Finish
The date the work on the scope assignment is scheduled to finish.
This field is used to spread original data fields.
If there is no activity link, this field is populated with the Original Finish date until the original baseline is set. It can be manually modified after the original baseline is set.
If Data Date is specified after the Planned Finish date is set and the Planned Start date is before the Data Date, the application sets the Planned Finish date to be the same date relative to Planned Start before the Data Date was modified when the Modify Dates feature is run.
If there is an activity link, this field is populated with the activity's Planned Finish date.
Planned Finish (Work Package)
Planned Finish
The date the work on the work package is scheduled to finish.
If there is no activity link, this field is populated with the Original Finish date until the original baseline is set. It can be manually modified after the original baseline is set.
If Data Date is specified after the Planned Finish date is set and the Planned Start date is before the Data Date, the application sets the Planned Finish date to be the same date relative to Planned Start before the Data Date was modified when the Modify Dates feature is run.
If there is an activity link, this field is populated with the latest Planned Finish date of all activities in the work package.
Planned Labor Cost (Activity)
Planned Labor Cost
The planned cost for all labor resources assigned to the activity.
Planned Labor Units (Activity)
Planned Labor Units
The planned number of units for all labor resources assigned to the activity.
Planned Lag (Activity Assignment)
Planned Lag
The planned time lag between the activity's planned start date and the resource's planned start date on the activity.
Planned Material Cost (Activity)
Planned Material Cost
The planned cost for all material resources assigned to the activity.
Planned Nonlabor Cost (Activity)
Planned Nonlabor Cost
The planned cost for all nonlabor resources assigned to the activity.
Planned Nonlabor Units (Activity)
Planned Nonlabor Units
The planned units for all nonlabor resources assigned to the activities in the project.
Planned Response Cost (Risk)
Planned Response Cost
The estimated cost associated with implementing the response action.
Planned Risk Response (Actual Risk Response Cost)
Planned Risk Response
The estimated cost associated with implementing the response action.
Planned Risk Response (Cost Sheet)
Planned Risk Response
The planned value required to respond to a risk.
Planned Start (Activity Assignment)
Planned Start
The planned start date for the assignment on the activity.
Planned Start (Activity)
Planned Start
The date the activity is scheduled to start.
This date the activity is scheduled to begin is calculated by the project scheduler but can be updated manually by the project manager. This date cannot be changed by the project scheduler after the activity has started.
Planned Start (Scope Assignment)
Planned Start
The date the work on the scope assignment is scheduled to begin.
This field is used to spread original data fields.
If there is no activity link, this field is populated with the Original Start date until the original baseline is set. It can be manually updated after the original baseline is set.
If the Data Date is specified, the date cannot be set to a date earlier than the Data Date.
If the Data Date is specified after the Planned Start date is set, the Planned Start date is before the Data Date, and the work package's Scope Percent Complete is equal to 0%, that is Installed Quantity is zero, then the date inherits the Data Date when the Modify Dates feature is run.
If there is an activity link, this field is populated with the activity's Planned Start date.
Planned Start (Work Package)
Planned Start
The date the work on the work package is scheduled to begin.
If there is no activity link, this field is populated with the Original Start date until the original baseline is set. It can be manually updated after the original baseline is set.
If the Data Date is specified, the date cannot be set to a date earlier than the Data Date.
If the Data Date is specified after the Planned Start date is set, the Planned Start date is before the Data Date, and the work package's Scope Percent Complete is equal to 0%, that is Installed Quantity is zero, then the date inherits the Data Date when the Modify Dates feature is run.
If there is an activity link, this field is populated with the earliest Planned Start date of all the activities in the work package.
Planned Total Cost (Activity)
Planned Total Cost
The expected total cost of the activity and includes all resources and direct activity costs (expenses).
Planned Units (Activity Assignment)
Planned Units
The planned units of work for the resource assignment on the activity.
Planned Units/Time (Activity Assignment)
Planned Units/Time
The planned units per time at which the resource is to perform work on the activity.
Planned Value Cost (Activity)
Planned Value Cost
The approved budget for the work scheduled to be completed by a specified date.
Calculated as Budget At Completion multiplied by Schedule Percent Complete.
When an activity has assignments, the Planned Value Cost is calculated as Budget At Completion multiplied by (Data Date of Current Project - Baseline Assignment Start Date) divided by (Baseline Assignment Finish Date - Baseline Assignment Start Date). Each assignment is then summed to the activity-level planned value.
Planned Value Cost
The approved budget for the work scheduled to be completed by a specified date.
Planned Value Cost (Activity)
Planned Value Cost
The approved budget for the work scheduled to be completed by a specified date.
Planned Value Cost (Project Budget)
Planned Value Cost
The amount of approved capital spent on a scheduled portion of work on a project.
Planned Value Cost is often used for Earned Value Management.
This value can be entered manually or can be imported. This value is based on the base currency with specified exchange rate.
Planned Value Cost (Schedule)
Planned Value Cost
The approved budget for the work scheduled to be completed by a specified date.
Planned Value Labor Units (Activity)
Planned Value Labor Units
The portion of baseline labor units that are scheduled to be completed as of the project data date.
Calculated as Budget At Completion Labor Units multiplied by Schedule Percent Complete.
Planned Value Labor Units (Schedule)
Planned Value Labor Units
The portion of baseline labor units that are scheduled to be complete as of the project data date.
Planned Value Period Cost (Activity)
Planned Value Period Cost
The incremental value of the approved budget for the work scheduled to be completed by a specified date.
Planned Value Period Units (Activity)
Planned Value Period Units
The incremental value of the planned units for the work scheduled to be completed by a specified project data date.
Planned Value Units (Activity)
Planned Value Units
The planned units for the work scheduled to be completed by a specified project data date.
Portfolio Approved Budget (Project Budget)
Portfolio Approved Budget
The budget currently approved for the project.
Current Approved Budget values are derived from the Proposed Budget set by the budget planner.
A Proposed Budget becomes the Approved Budget after the budget scenario has undergone the approval process. This value is based on the base currency with specified exchange rate.
Portfolio Proposed Budget (Project Budget)
Portfolio Proposed Budget
The Proposed Budget for the project as allocated by the budget planner.
Project managers can measure the proposed budget for their projects against their own planned budgets and project forecasts.
If necessary, managers can request the planner make changes to the proposed budget allocated to their projects during budget plan scenario reviews.
Proposed Budget becomes the project's Approved Budget after the portfolio budget plan scenario is approved. This value is based on the base currency with specified exchange rate.
Post-Response Cost (Risk)
Post-Response Cost
The estimated impact size that the risk will have on the project cost after implementing a response action.
Post-Response Exposure (Risk)
Post-Response Exposure
The mean post-response probability of the risk multiplied by the mean post-response cost impact of the risk.
Pre-Response At-Completion Cost Mean Contribution (Risk Analysis)
Pre-Response At-Completion Cost Mean Contribution
The total amount the activity contributes to the project total mean at-completion cost
Pre-Response At-Completion Cost Standard Deviation (Risk Analysis)
Pre-Response At-Completion Cost Standard Deviation
How much the distribution of sampled at-completion costs deviates from the calculated mean at-completion cost.
Pre-Response At-Completion Cost Variance (Risk Analysis)
Pre-Response At-Completion Cost Variance
The at-completion cost variance.
Pre-Response Cost (Risk)
Pre-Response Cost
The estimated impact size that the risk will have on the project cost before implementing a response action.
Pre-Response Cost Variance (Risk Analysis)
Pre-Response Cost Variance
The measure of project cost performance sampled during a risk analysis. It is calculated as the difference between the project's actual cost and the planned cost.
Pre-Response Criticality Index (Risk Analysis)
Pre-Response Criticality Index
During risk analysis, tasks can join or leave the critical path. The criticality index expresses as a percentage, how often a particular task was on the critical path during the analysis.
Pre-Response Deterministic At-Completion Cost Probability (Risk Analysis)
Pre-Response Deterministic At-Completion Cost Probability
The probability of achieving the deterministic at-completion cost.
Pre-Response Deterministic Finish Probability (Risk Analysis)
Pre-Response Deterministic Finish Probability
The probability of the project finishing on or before the deterministic finish date.
Pre-Response Deterministic Remaining Cost Probability (Risk Analysis)
Pre-Response Deterministic Remaining Cost Probability
The probability of achieving the project deterministic remaining cost.
Pre-Response Deterministic Remaining Duration Probability (Risk Analysis)
Pre-Response Deterministic Remaining Duration Probability
The probability of the project's remaining duration being less than or equal to the project remaining duration, calculated using fixed duration and date values.
Pre-Response Deterministic Start Probability (Risk Analysis)
Pre-Response Deterministic Start Probability
The probability of the project starting on or before the deterministic start date.
Pre-Response Exposure (Risk)
Pre-Response Exposure
The mean pre-response probability of the risk multiplied by the mean pre-response cost impact of the risk.
Pre-Response Finish Standard Deviation (Risk Analysis)
Pre-Response Finish Standard Deviation
How much the project finish dates deviate from the calculated mean finish date.
Pre-Response Maximum At-Completion Cost (Risk Analysis)
Pre-Response Maximum At-Completion Cost
The maximum at-completion cost sampled during the risk analysis.
Pre-Response Maximum Finish (Risk Analysis)
Pre-Response Maximum Finish
The latest project finish date sampled during the risk analysis.
Pre-Response Maximum Remaining Cost (Risk Analysis)
Pre-Response Maximum Remaining Cost
The maximum project remaining cost sampled during the risk analysis.
Pre-Response Maximum Remaining Duration (Risk Analysis)
Pre-Response Maximum Remaining Duration
The maximum project remaining duration sampled during the risk analysis.
Pre-Response Maximum Start (Risk Analysis)
Pre-Response Maximum Start
The latest project start date sampled during the risk analysis.
Pre-Response Mean At-Completion Cost (Risk Analysis)
Pre-Response Mean At-Completion Cost
The average at-completion cost sampled during the risk analysis.
Pre-Response Mean Finish (Risk Analysis)
Pre-Response Mean Finish
The average project finish date sampled during the risk analysis.
Pre-Response Mean Remaining Cost (Risk Analysis)
Pre-Response Mean Remaining Cost
The average project cost sampled during the risk analysis.
Pre-Response Mean Remaining Duration (Risk Analysis)
Pre-Response Mean Remaining Duration
The average project remaining duration sampled during risk analysis.
Pre-Response Mean Start (Risk Analysis)
Pre-Response Mean Start
The average project start date sampled during the risk analysis.
Pre-Response Minimum At-Completion Cost (Risk Analysis)
Pre-Response Minimum At-Completion Cost
The minimum at-completion cost sampled during the risk analysis.
Pre-Response Minimum Finish (Risk Analysis)
Pre-Response Minimum Finish
The earliest project finish date sampled during the risk analysis.
Pre-Response Minimum Remaining Cost (Risk Analysis)
Pre-Response Minimum Remaining Cost
The minimum project remaining cost sampled during the risk analysis.
Pre-Response Minimum Remaining Duration (Risk Analysis)
Pre-Response Minimum Remaining Duration
The minimum project remaining duration sampled during the risk analysis.
Pre-Response Minimum Start (Risk Analysis)
Pre-Response Minimum Start
The earliest project start date sampled during the risk analysis.
Pre-Response Optimistic At-Completion Cost (Risk Analysis)
Pre-Response Optimistic At-Completion Cost
The optimistic at-completion cost sampled during the risk analysis.
Pre-Response Optimistic Finish (Risk Analysis)
Pre-Response Optimistic Finish
The calculated project finish date that corresponds to the defined optimistic percentile.
Pre-Response Optimistic Remaining Cost (Risk Analysis)
Pre-Response Optimistic Remaining Cost
The optimistic remaining cost sampled during the risk analysis.
Pre-Response Optimistic Remaining Duration (Risk Analysis)
Pre-Response Optimistic Remaining Duration
The optimistic remaining duration calculated using the optimistic percentile.
Pre-Response Optimistic Start (Risk Analysis)
Pre-Response Optimistic Start
The calculated project start date that corresponds to the defined optimistic percentile.
Pre-Response P50 At-Completion Cost (Risk Analysis)
Pre-Response P50 At-Completion Cost
The P50 or median at-completion cost sampled during the risk analysis.
Pre-Response P50 Finish (Risk Analysis)
Pre-Response P50 Finish
The calculated project finish date that corresponds to the P50 or median percentile.
Pre-Response P50 Remaining Cost (Risk Analysis)
Pre-Response P50 Remaining Cost
The P50 or median remaining cost sampled during the risk analysis.
Pre-Response P50 Remaining Duration (Risk Analysis)
Pre-Response P50 Remaining Duration
The calculated median remaining duration.
Pre-Response P50 Start (Risk Analysis)
Pre-Response P50 Start
The calculated project start date that corresponds to the P50 or median percentile.
Pre-Response Pessimistic At-Completion Cost (Risk Analysis)
Pre-Response Pessimistic At-Completion Cost
The pessimistic at-completion cost calculated using the pessimistic percentile.
Pre-Response Pessimistic At-Completion Cost Contingency (Risk Analysis)
Pre-Response Pessimistic At-Completion Cost Contingency
The difference between the pessimistic at-completion cost and the deterministic at-completion cost.
Pre-Response Pessimistic Finish (Risk Analysis)
Pre-Response Pessimistic Finish
The calculated project finish date that corresponds to the defined pessimistic percentile.
Pre-Response Pessimistic Finish Contingency (Risk Analysis)
Pre-Response Pessimistic Finish Contingency
The difference between the project pessimistic percentile finish date and the project deterministic finish date.
Pre-Response Pessimistic Remaining Cost (Risk Analysis)
Pre-Response Pessimistic Remaining Cost
The pessimistic remaining cost calculated using the pessimistic percentile.
Pre-Response Pessimistic Remaining Cost Contingency (Risk Analysis)
Pre-Response Pessimistic Remaining Cost Contingency
The difference between the project pessimistic remaining cost and the project deterministic remaining cost.
Pre-Response Pessimistic Remaining Duration (Risk Analysis)
Pre-Response Pessimistic Remaining Duration
The pessimistic remaining duration calculated using the pessimistic percentile.
Pre-Response Pessimistic Remaining Duration Contingency (Risk Analysis)
Pre-Response Pessimistic Remaining Duration Contingency
The difference between the project pessimistic percentile remaining duration and the project deterministic remaining duration.
Pre-Response Pessimistic Start (Risk Analysis)
Pre-Response Pessimistic Start
The calculated project start date that corresponds to the defined pessimistic percentile.
Pre-Response Pessimistic Start Contingency (Risk Analysis)
Pre-Response Pessimistic Start Contingency
The difference between the project pessimistic percentile start date and the project deterministic start date.
Pre-Response Project Mean Cost Contribution (Risk Analysis)
Pre-Response Project Mean Cost Contribution
The estimated average project cost impact before implementing a response action.
Pre-Response Project Mean Delay Contribution (Risk Analysis)
Pre-Response Project Mean Delay Contribution
The estimated average project delay duration before implementing a response action.
Pre-Response Remaining Duration Standard Deviation (Risk Analysis)
Pre-Response Remaining Duration Standard Deviation
How much the variation of remaining durations deviates from the calculated mean remaining duration.
Pre-Response Standard Deviation Remaining Cost (Risk Analysis)
Pre-Response Standard Deviation Remaining Cost
How much the distribution of sampled project costs deviates from the calculated mean project cost.
Pre-Response Start Standard Deviation (Risk Analysis)
Pre-Response Start Standard Deviation
How much the variation of project start dates deviate from the calculated mean start date.
Previous Amount Approved (Payment Application)
Previous Amount Approved
The amount approved for all previously submitted payment applications.
Price/Unit (Activity Assignment)
Price/Unit
The price per unit of time for the resource or role.
Prior Actual Cost (Activity Assignment)
Prior Actual Cost
The total actual costs incurred at the time of the last stored period performance. This represents the costs incurred from the last period closeout date.
Prior Actual Cost (Activity)
Prior Actual Cost
The total actual costs incurred at the time of the last stored period performance. This represents the costs incurred from the last period closeout date.
Prior Actual Labor Cost (Schedule)
Prior Actual Labor Cost
The sum of the actual stored period labor costs on the activity.
Prior Actual Labor Units (Schedule)
Prior Actual Labor Units
The sum of the actual stored period units for all labor resource assignments on the activity.
Prior Actual Material Cost (Schedule)
Prior Actual Material Cost
The sum of the actual stored period material costs on the activity.
Prior Actual Nonlabor Cost (Schedule)
Prior Actual Nonlabor Cost
The sum of the actual stored period nonlabor costs on the activity.
Prior Actual Nonlabor Units (Schedule)
Prior Actual Nonlabor Units
The sum of the actual stored period units for all nonlabor resource assignments on the activity.
Prior Actual Total Cost (Schedule)
Prior Actual Total Cost
The aggregated total of all labor, nonlabor and material costs on the activity.
Prior Actual Units (Activity)
Prior Actual Units
The total actual units incurred at the time of the last stored period performance. This represents the total units incurred from the last period closeout date.
Problem or Opportunity (Program)
Problem or Opportunity
A detailed description of the problem or opportunity the program addresses.
Production Rate (Budget Item)
Production Rate
The number of hours per unit of measure needed to complete the budget item.
Production Rate (Budget Transaction)
Production Rate
The number of hours per unit of measure needed to complete the budget line item.
Proficiency (Activity Assignment)
Proficiency
The skill level of the resource an activity is assigned to. The valid values are Master, Expert, Skilled, Proficient, and Inexperienced.
Profitability Index (Project Budget)
Profitability Index
The index based on the value of a project's present values divided by initial project investments.
Program Planned Finish (Program)
Program Planned Finish
The finish date for the time phased Planned Budget of the program.
Planned Budget cost spread will adjust when this date is changed.
Program Planned Start (Program)
Program Planned Start
The start date for the time phased Planned Budget of the program.
Planned Budget cost spread will adjust when this date is changed.
The Program Planned Start also represents the earliest date that activities can occur within a program schedule.
Project Actual Hours
Project Actual Hours
The actual hours spent on the scope assignment. This tracks the VOWD (Value of Work Done).
Project Actual Hours
The actual hours spent on the scope assignment. This tracks the VOWD (Value of Work Done).
Project Actual Hours
Project Actual Hours
The actual hours spent on the scope assignment. This tracks the VOWD (Value of Work Done).
Project CPI
Project CPI
The measure of a project's cost efficiency.
A value of less than 1 indicates the project is over budget, while a value greater than 1 indicates the project is under budget.
Project Currency (Project)
Project Currency
The currency used by the project. The project currency can differ from the base currency.
Project Current Actuals
Project Current Actuals
Total costs accrued on a project within a given time period.
The Actual Cost data for the project's life cycle is pulled from the P6 EPPM schedule.
Actual Cost data is only available when the application is connected with P6 EPPM and is not editable.
Project Current Budget
Project Current Budget
The total approved current manual budget of a project. Calculated as the sum of Approved Original Manual Budget plus Approved Manual Budget Changes plus Approved Manual Budget Transfers.
Project Current Budget (Project Budget)
Project Current Budget
The total cost of the project budget, including all transfers and changes. This value is based on the base currency with specified exchange rate.
Project Current Commitments
Project Current Commitments
The total cost of all approved commitments and approved change commitments on the project.
Project Current Commitments (Actual Risk Response Cost)
Project Current Commitments
The total cost of all approved commitments and approved change commitments on the project.
Project Current Commitments (Cost Sheet)
Project Current Commitments
The sum of the approved original commitments and the approved commitment changes.
Project Current Contracts
Project Current Contracts
The total cost of all approved contracts and approved change contracts for the project.
Project Current Contracts (Actual Risk Response Cost)
Project Current Contracts
The total cost for all current project contracts.
Project Current Contracts (Cost Sheet)
Project Current Contracts
The total of all approved contracts and approved contract changes.
Project Earned Cost
Project Earned Cost
The value of work performed on a project in reference to the approved budget for the project.
The cost value used for the Earned Value Management of a project.
Earned Value Management allows project managers to quantify project progress and objectively measure a project's success.
Project Earned Hours
Project Earned Hours
Calculated as Performance Percent Complete multiplied by BAC Hours.
Project Earned Hours
Calculated as Performance Percent Complete multiplied by BAC Hours.
Project Earned Hours
Project Earned Hours
Calculated as Performance Percent Complete multiplied by BAC Hours.
Project Finish (Project)
Project Finish
The date on which all project work is complete.
This value can be entered manually or can be imported.
Project HPI
Project HPI
Calculated as the total of Project Earned Hours divided by Project Actual Hours.
Project HPI
Calculated as the total of Project Earned Hours divided by Project Actual Hours.
Project HPI
Project HPI
Calculated as the total of Project Earned Hours divided by Project Actual Hours.
Project Mean Cost Increase (Risk Analysis)
Project Mean Cost Increase
Mean cost increase of the project.
Project Mean Cost Increase% (Risk Analysis)
Project Mean Cost Increase%
Percentage mean cost increase of the project.
Project Mean Delay % (Risk Analysis)
Project Mean Delay %
The average delay percentage of the remaining duration for the project.
Calculated as Project Mean Delay divided by Project Remaining Duration multiplied by 100.
Project Mean Delay (Risk Analysis)
Project Mean Delay
The average project delay duration sampled during the risk analysis.
Calculated as Mean Remaining Duration minus Project Remaining Duration.
Project Original Budget (Project Budget)
Project Original Budget
The total original cost of the project budget, before transfers and changes. This value is based on the base currency with specified exchange rate.
Project Planned Finish (Project)
Project Planned Finish
The finish date for the time phased Planned Budget of the project.
Planned Budget cost spread will adjust when this date is changed.
Project Planned Start (Project)
Project Planned Start
The start date for the time phased Planned Budget of the project.
Planned Budget cost spread will adjust when this date is changed.
The Project Planned Start also represents the earliest date that activities can occur within a project schedule.
Project Response Actual Cost (Risk Analysis)
Project Response Actual Cost
The project total direct response actual cost at the time the risk analysis as run.
Project Response Remaining Cost (Risk Analysis)
Project Response Remaining Cost
The project total direct response remaining cost at the time the risk analysis as run.
Project Start (Project)
Project Start
The date on which work on the project starts.
This value can be entered manually or can be imported.
Promised Date (Task Constraint)
Promised Date
The date by which the responsible party has agreed to resolve the constraint.
Proposed Budget (Budget Planning)
Proposed Budget
The total Proposed Budget for the portfolio as allocated by the budget planner.
Planners can plan proposed budgets in a bottom-up or top-down style.
Not all projects in the portfolio need to have Planned Budgets for planners to begin planning and setting proposed budget values.
Instead, by setting an overall plan Proposed Budget and allocating out its funds to included projects, planners can achieve top-down budget planning.
Similarly, project Planned Budgets and Forecast values can be linked to the Proposed Budget of a budget plan, allowing planners to establish project manager's budgets as a basis for their planning.
Becomes the portfolio's Current Approved Budget after the budget scenario is approved.
Proposed Budget
The Proposed Budget for the project as allocated by the portfolio budget planner.
Project managers can measure the proposed budget for their projects against their own planned budgets and project forecasts.
If necessary, managers can request the planner make changes to the proposed budget allocated to their projects during budget plan scenario reviews.
Becomes the projects Current Approved Budget after the portfolio budget plan scenario is approved.
Proposed Budget (Budget Planning)
Proposed Budget
The Proposed Budget for the project as allocated by the portfolio budget planner.
Project managers can measure the proposed budget for their projects against their own planned budgets and project forecasts.
If necessary, managers can request the planner make changes to the proposed budget allocated to their projects during budget plan scenario reviews.
Becomes the projects Current Approved Budget after the portfolio budget plan scenario is approved.
Proposed Budget (Present Value) (Project Budget)
Proposed Budget (Present Value)
The present value, also known as discounted value, of the portfolio proposed budget. Future cash flows are discounted using the project's annual discount rate. This value is based on the base currency with specified exchange rate.
Proposed Budget Finish (Project)
Proposed Budget Finish
The finish date for the Proposed Budget of the project.
Proposed Budget Start (Project)
Proposed Budget Start
The start date for the Proposed Budget of the project.
Proposed Due Date (Task)
Proposed Due Date
The date proposed for the task due date. Proposed Due Dates do not affect task Due Dates until they are accepted.
Proposed Role Allocation (Resource Demand)
Proposed Role Allocation
The total role allocation units proposed.
Quantity (Actual Line Item)
Quantity
The quantity of the actual line item.
If Total is entered, you cannot enter Quantity. If a Unit Price is entered, Quantity must be entered.
If a Unit of Measure is selected, the Quantity value is displayed as Quantity of Measure.
Quantity (Budget Item)
Quantity
The number of each budget item needed to complete the work.
Quantity (Budget Transaction)
Quantity
The number of each budget line item needed to complete the work.
Quantity (Change Order)
Quantity
The number of units represented by the line item.
Quantity
The number of units represented by the change order line item.
Quantity (Change Order)
Quantity
The number of units represented by the change order line item.
Quantity (Commitment)
Quantity
The number of units represented by the line item.
Quantity
The number of units represented by the line item.
Quantity (Commitment)
Quantity
The number of units represented by the line item.
Quantity (Contract)
Quantity
The number of units represented by the line item.
Quantity
The number of units represented by the schedule of values.
Quantity (Contract)
Quantity
The number of units represented by the schedule of values.
Quantity (Potential Change Order)
Quantity
The quantity of the proposal line item.
Quantity Weight (Scope Assignment)
Quantity Weight
This value is used to calculate Scope Percent Complete at the work package level if Scope Percent Complete Weight Method is set to Quantity.
Calculated as Scope Percent Complete multiplied by Revised Quantity.
Question (Potential Change Order)
Question
The question, which can only be modified while it is a draft.
Rate Source (Activity Assignment)
Rate Source
The value that indicates which Price/Unit will be used to calculate costs for the assignment. Valid options are Resource, Role, or Override.
Rate Type (Activity Assignment)
Rate Type
Identifies the Resource or Role rate to be used as a default when creating activity resource assignments.
Reasons Missed (Task)
Reasons Missed
The names of the reasons for recommitting to a task.
Reference Number (Commitment)
Reference Number
An optional value that can be used to sort and group commitments.
Reference Number (Contract)
Reference Number
An optional value that can be used to sort and group contracts.
Rejected By (Budget Change Request)
Rejected By
The username of the user that rejected the item.
Rejected By (Budget Transfer)
Rejected By
The username of the user that rejected the item.
Rejected By (Project Budget)
Rejected By
The user who rejected the budget.
Rejected Date (Budget Change Request)
Rejected Date
Date the item was rejected.
Rejected Date (Budget Transfer)
Rejected Date
Date the item was rejected.
Rejected Date (Project Budget)
Rejected Date
The date the budget was rejected.
Relationship Early Finish (Activity Relationship)
Relationship Early Finish
The first work period after the relationship Early Start plus any Relationship Lag. Calculated using the relationship calendar as Relationship Early Start plus Relationship Remaining Lag.
Relationship Early Start (Activity Relationship)
Relationship Early Start
The relationship's Early Start is the predecessor activity's Early Finish. Calculated using the relationship calendar as the first work period after either the predecessor's Early Finish date (Finish to Start and Finish to Finish relationship types) or the predecessor's Early Start date (Start to Finish and Start to Start relationship types).
Relationship Free Float (Activity Relationship)
Relationship Free Float
For predecessors, the Relationship Free Float is the Free Float on the relationship calculated using the predecessor activity's calendar as Relationship Successor Early Start minus Relationship Early Finish. For successors, the Relationship Free Float is the Free Float of the potential successor activity if the relationship is determined to be the driving relationship using the successor activity's calendar. Calculated using the successor activity's calendar as Relationship Successor Early Start minus Relationship Early Finish.
Relationship Late Finish (Activity Relationship)
Relationship Late Finish
Relationship Late Finish is calculated using the relationship calendar as the first work period before the successor activity's Late Start date.
Relationship Late Start (Activity Relationship)
Relationship Late Start
Relationship Late Start is calculated using the relationship calendar as the Relationship Late Finish minus Remaining Relationship Lag.
Relationship Successor Free Float (Activity Relationship)
Relationship Successor Free Float
The Relationship Successor Free Float is the free float of the potential successor activity if that specific relationship is the driving relationship. Calculated using the successor calendar as either Relationship Successor Early Start minus Relationship Early Finish (assuming a Finish to Start or Start to Start relationship type) or Relationship Successor Early Finish minus Relationship Early Finish (assuming a Start to Finish or Finish to Finish relationship type).
Relationship Successor Total Float (Activity Relationship)
Relationship Successor Total Float
The Relationship Successor Total Float is the total float of the potential successor activity if that specific relationship is the driving relationship. Calculated using the successor activity's calendar as the Relationship Late Finish minus Relationship Early Finish.
Relationship Total Float (Activity Relationship)
Relationship Total Float
For predecessors, the Relationship Total Float is the Total Float on the relationship calculated using the predecessor activity's calendar as Relationship Late Start minus Relationship Early Start. For successors, the Relationship Total Float is the Total Float of the potential successor activity if the relationship is determined to be the driving relationship using the successor activity's calendar. Calculated using the successor activity's calendar as successor activity's Relationship Late Date minus Relationship Successor Early Date.
Relationship Type (Activity Relationship)
Relationship Type
The relationship type defining the behavior between two activities. The valid values are Finish to Start, Finish to Finish, Start to Start, and Start to Finish.
Remaining (Funds)
Remaining
The portion of the fund that has not been consumed.
Remaining Cost - Deterministic (Risk Analysis)
Remaining Cost - Deterministic
The project remaining total cost plus unmapped response action remaining costs at the time the risk analysis as run.
Remaining Cost (Activity Assignment)
Remaining Cost
The remaining cost for the resource assignment on the activity.
Remaining Cost (Project Budget)
Remaining Cost
The remaining total cost for the project, including labor resources, nonlabor resources, and project expenses.
This value can be imported.
Remaining Cost (Scope Assignment)
Remaining Cost
The amount left to be spent.
If Rate By set to Hours, then Remaining Cost equals Remaining Hours multiplied by Revised Cost Rate.
If Rate By set to Quantity, then Remaining Cost equals Remaining Quantity multiplied by Revised Cost Rate.
Remaining Cost (Work Package)
Remaining Cost
The amount left to be spent.
If Rate By set to Hours, then Remaining Cost equals Remaining Hours multiplied by Revised Cost Rate.
If Rate By set to Quantity, then Remaining Cost equals Remaining Quantity multiplied by Revised Cost Rate.
This is the cumulative value for all scope assignments in the work package.
Remaining Duration - Deterministic (Risk Analysis)
Remaining Duration - Deterministic
The activity remaining duration at the time the risk analysis was run.
Remaining Duration (Activity Assignment)
Remaining Duration
The remaining working time for the resource assignment on the activity, from the resource's remaining start date to the remaining finish date.
Remaining Duration (Activity)
Remaining Duration
The total working time from the activity remaining start date to the remaining finish date.
Remaining Duration (Project)
Remaining Duration
The duration between the Project Start and Project Finish.
This value can be entered manually or can be imported.
Remaining Duration (Risk Analysis)
Remaining Duration
The project schedule remaining duration at the time the risk analysis was run.
Remaining Early Finish (Activity)
Remaining Early Finish
The date the remaining work for the activity is scheduled to finish.
If this activity is not started, this date is the planned finish. This date can be updated manually by the user, but it is overwritten when you schedule the project.
Remaining Early Finish (Project)
Remaining Early Finish
The earliest possible date the remaining work for the activity is scheduled to finish. This date is calculated by the project scheduler but can be updated manually by the user. Before the activity is started, the Remaining Finish is the same as the Planned Finish. When the activity is complete, the Remaining Finish is blank.
Remaining Early Finish (Scope Assignment)
Remaining Early Finish
The earliest date the work on the scope assignment is scheduled to finish.
If there is no activity link, before the original baseline is set, this field is populated with the Original Finish date. After the original baseline is set, this field is populated with the Revised Finish date.
This field is blank when the scope assignment's Scope Percent Complete becomes 100%.
If there is any activity linked, this field is populated with the activity's Remaining Early Finish date.
This field is used to spread Remaining data fields.
Remaining Early Finish (Work Package)
Remaining Early Finish
The earliest date the work on the work package is scheduled to finish.
If there is no activity link, this field is populated with the latest Remaining Early Finish date of all its scope assignments. If the work package does not have scope assignments, the field is populated the Original Finish date before the original baseline is set and the Revised Finish date after the original baseline is set.
This field is blank when the scope assignment's Scope Percent Complete becomes 100%.
If there is an activity linked, this field is populated with the latest Remaining Early Finish date of all linked activities.
Remaining Early Start (Activity)
Remaining Early Start
The date the remaining work for the activity is scheduled to begin.
This date can be updated manually by the user. Before the activity is started, this date is the same as the planned start.
Remaining Early Start (Project)
Remaining Early Start
The earliest possible date the remaining work for the activity is scheduled to begin. This date is calculated by the project scheduler but can be updated manually by the user. Before the activity is started, the Remaining Start is the same as the Project Planned Start. Once the activity has started, the Remaining Start is equal to the Data Date. When the activity is complete, the Remaining Start is blank.
Remaining Early Start (Scope Assignment)
Remaining Early Start
The earliest date the work on the scope assignment is scheduled to begin.
If there is no activity link, before the original baseline is set, this field is populated with the Original Start date. After the original baseline is set, this field is populated with the Data Date when the Modify Dates feature is run if the scope assignment's Scope Percent Complete is not equal to 100%.
This field is blank when the scope assignment's Scope Percent Complete becomes 100%.
If there is any activity linked, this field is populated with the activity's Remaining Early Start date.
This field is used to spread Remaining data fields.
Remaining Early Start (Work Package)
Remaining Early Start
The earliest date the work on the work package is scheduled to begin.
If the work package does not have scope assignments, before the original baseline is set, this field is populated with the Original Start date. After the original baseline is set, it inherits the Data Date when the Modify Dates feature is run if the work package's Scope Percent Complete is not equal to 100%.
This field is blank when the scope assignment's Scope Percent Complete becomes 100%.
If there is any activity linked, this field is populated with the earliest Remaining Early Start date of all linked activities.
Remaining Float (Activity)
Remaining Float
The amount of time remaining in which the activity can be delayed before delaying the project finish date. Calculated as Late Finish minus Remaining Finish.
Remaining Hours (Scope Assignment)
Remaining Hours
The number of hours left for the scope assignment.
Calculated as Remaining Quantity multiplied by Revised Productivity Rate.
Remaining Hours (Work Package)
Remaining Hours
The number of hours left for the scope assignment.
Calculated as Remaining Quantity multiplied by Revised Productivity Rate.
This is the cumulative value for all scope assignments in the work package.
Remaining Labor Cost (Activity)
Remaining Labor Cost
The remaining cost for all labor resource assignments on the activity.
Remaining Labor Units (Activity)
Remaining Labor Units
The remaining units for all labor resources assigned to the activity.
The Remaining Labor Units reflect the work remaining to be done for the activity. Before the activity is started, the remaining units are the same as the planned units. After the activity is completed, the remaining units are zero.
Remaining Lag (Activity Assignment)
Remaining Lag
The time lag between the activity's remaining start date and the resource's remaining start date on the activity.
Remaining Late Finish (Activity Assignment)
Remaining Late Finish
The latest possible date the assignment must be finished to not delay the project finish date.
Remaining Late Finish (Activity)
Remaining Late Finish
The latest possible date the activity must finish without delaying the project finish date.
This date is calculated by the project scheduler based on activity relationships, schedule constraints, and resource availability. When the activity is complete, this field is blank.
Remaining Late Finish (Scope Assignment)
Remaining Late Finish
The latest possible date work on the scope assignment must finish to not delay the finish date.
If there is no activity link, this field is always equal to the Remaining Early Finish date.
If there is any activity linked, this field is populated with the activity's Remaining Late Finish date.
This field is used to spread Remaining data fields.
Remaining Late Finish (Work Package)
Remaining Late Finish
The latest possible date work on the work package must finish to not delay the finish date.
If there is no activity link, this field is populated with the latest Remaining Late Finish date of all its scope assignments. If the work package does not have scope assignments, the field is populated with the Remaining Early Finish date.
If there is an activity linked, this field is populated with the latest Remaining Late Finish date of all linked activities.
Remaining Late Start (Activity Assignment)
Remaining Late Start
The latest possible date the assignment must begin to not delay the project finish date.
Remaining Late Start (Activity)
Remaining Late Start
The latest possible date the remaining work for the activity must begin without delaying the project finish date.
This date is calculated by the project scheduler based on activity relationship, schedule constraints, and resource availability.
Remaining Late Start (Scope Assignment)
Remaining Late Start
The latest possible date work on the scope assignment must begin without delaying the finish date.
If there is no activity link, this field is always equal to the Remaining Early Start date.
If there is any activity link, this field is populated with the activity's Remaining Late Start date.
This field is used to spread Remaining data fields.
Remaining Late Start (Work Package)
Remaining Late Start
The latest possible date work on the work package must begin without delaying the finish date.
If there is no activity link, this field is always equal to the Remaining Late Start date of all scope assignments in the work package. If the work package does not have scope assignments, this field is populated with the Remaining Early Start date.
If there is any activity linked, this field is populated with the earliest Remaining Late Start date of all activities.
Remaining Late Units (Activity Assignment)
Remaining Late Units
The number of units remaining to be worked on for the assignment distributed over the late start and late finish dates.
Remaining Material Cost (Activity)
Remaining Material Cost
The remaining cost for all material resource assignments on the activity.
Remaining Nonlabor Cost (Activity)
Remaining Nonlabor Cost
The remaining cost for all nonlabor resource assignments on the activity.
Remaining Nonlabor Units (Activity)
Remaining Nonlabor Units
The remaining units for all nonlabor resources assigned to the activity.
The remaining units reflect the work remaining to be done for the activity. Before the activity is started, the remaining units are the same as the planned units. After the activity is completed, there are zero remaining units.
Remaining Quantity (Scope Assignment)
Remaining Quantity
The quantity remaining for the scope assignment.
Calculated as Revised Quantity minus Installed Quantity.
Remaining Quantity (Scope Item)
Remaining Quantity
The quantity remaining for the scope item.
Calculated as Revised Quantity for the scope item minus the sum of Installed Quantity for the scope item's assignments.
Remaining Total Cost - Deterministic (Risk Analysis)
Remaining Total Cost - Deterministic
The activity remaining total cost at the time the risk analysis was run.
Remaining Total Cost (Activity)
Remaining Total Cost
The remaining cost for all resource assignments and direct activity costs (expenses) on the activity.
Remaining Units (Activity Assignment)
Remaining Units
The remaining units of work to be performed by the resource on the activity.
Remaining Units
The remaining units of work to be performed by the resource on the activity.
Calculated as Planned Units minus Actual Units.
Remaining Units (Activity Assignment)
Remaining Units
The remaining units of work to be performed by the resource on the activity.
Calculated as Planned Units minus Actual Units.
Remaining Units/Time (Activity Assignment)
Remaining Units/Time
The units per time required for the resource assignment to complete the activity.
Reopened By (Potential Change Order)
Reopened By
The user who reopened the question.
Resource Type (Activity Assignment)
Resource Type
The resource type. Valid values are Labor, Nonlabor, and Material.
Response Context (Risk Analysis)
Response Context
The type of risk analysis scenario run on the project.
Pre-Response: A quantitative risk analysis that doesn't take into account the impact of defined risk response plans.
Post-Response: A quantitative risk analysis that takes into account the impact of defined risk response plans.
Pre- and Post-Response: A quantitative risk analysis that uses both scenarios.
Responsible Company (Task Constraint)
Responsible Company
The company associated with the responsible party.
Responsible Party (Task Constraint)
Responsible Party
The user who is responsible for resolving the constraint.
Restricted User
Restricted User
Indicates that the user can only access records associated with the assigned company.
Resume Date (Activity)
Resume Date
The date when a suspended task or activity is resumed.
Resume Date (Risk Analysis)
Resume Date
The activity resume date at the time the risk analysis was run.
Retainage (Change Order)
Retainage
The amount of money retained by the payer for the work completed.
Retainage (Commitment)
Retainage
The amount of money retained for the work completed on the line item.
Retainage (Contract)
Retainage
The percentage of the cost that is retained until the associated contract is complete.
Return on Investment (Project Budget)
Return on Investment
The percentage resulting from division of the expected returns of an investment by the investment costs of a project or portfolio.
For example, a project is expected to cost 1.0 million dollars with a total benefit of 1.2 million dollars. Its Net Present Value is $200,000. The Return on Investment is 20%.
This value can be entered manually or can be imported.
Revised Cost (Scope Assignment)
Revised Cost
The Original Cost before the baseline is set. After the baseline is set, Revised Cost equals Original Cost plus Approved Change Cost.
Revised Cost (Work Package)
Revised Cost
The Original Cost before the baseline is set. After the baseline is set, Revised Cost equals Original Cost plus Approved Change Cost.
This is the cumulative value for all scope assignments in the work package.
Revised Cost Rate (Scope Assignment)
Revised Cost Rate
The cost rate used in the cost calculation of the scope assignment based on current values.
If Rate By set to Hours, then Revised Cost Rate equals Revised Cost divided by Revised Hours.
If Rate By set to Quantity, then Revised Cost Rate equals Revised Cost divided by Revised Quantity.
Revised Finish (Scope Assignment)
Revised Finish
The revised finish date for the scope assignment.
It is always the latest finish of the scope assignment's Planned Finish date and all approved Change Finish dates.
This field is used to spread Revised data fields.
Revised Finish (Work Package)
Revised Finish
The revised finish date for the work package.
If the work package does not have scope assignments, this field is populated with the Original Finish date until the original baseline is set.
When the Modify Dates feature is run after the original baseline is set, the Revised Start date is before the Data Date, and the work package's Scope Percent Complete is equal to 0%, the Revised Finish date is updated to be the same date relative to the Revised Start date as it was before the Data Date was modified.
If the work package has scope assignments, the date is always the latest finish of its scope assignments' Planned Finish dates and all approved Change Finish dates.
Revised Finish Date (Commitment)
Revised Finish Date
The revised date by which the work contracted is scheduled to be finished. The Finish Date value is not affected by project calendars.
Revised Finish Date (Contract)
Revised Finish Date
Calculated as the contract's Finish Date plus the sum of the Time Change for all approved change orders for the contract.
Revised Hours (Scope Assignment)
Revised Hours
Original Hours before the baseline is set. After the baseline is set, Revised Hours is equal to Original Hours plus Approved Change Hours.
Revised Hours
Original Hours before the baseline set. After the baseline, Revised Hours is equal to Original Hours plus Approved Change Hours.
Revised Hours (Scope Assignment)
Revised Hours
Original Hours before the baseline set. After the baseline, Revised Hours is equal to Original Hours plus Approved Change Hours.
Revised Hours (Scope Item)
Revised Hours
The total number of hours needed to complete all the work on a scope item, including any approved changes. This value equals the Original Hours before the original baseline is set.
Calculated as the sum of Original Hours plus Approved Changed Hours, if any.
Revised Hours (Work Package)
Revised Hours
Original Hours before the baseline is set. After the baseline is set, Revised Hours is equal to Original Hours plus Approved Change Hours.
This is the cumulative value for all scope assignments in the work package.
Revised Performance Period (Commitment)
Revised Performance Period
The period between when the performance period started and the latest approved change order against the commitment.
Revised Performance Period (Contract)
Revised Performance Period
The period between when the performance period started and the latest approved change order against the contract.
Revised Productivity Rate (Scope Assignment)
Revised Productivity Rate
The number of hours it will take to install or assemble the product or material per unit based on current values.
Calculated as Revised Hours divided by Revised Quantity.
This value is recalculated if Revised Quantity or Revised Hours are changed.
Revised Productivity Rate (Scope Item)
Revised Productivity Rate
The number of hours required to install a single quantity of the scope item material or product based on current values.
For example, if the product is 1,000 feet of cable it may be estimated to take 2 hours install one foot of cable.
This field is recalculated if Current Hours are changed.
Revised Quantity (Scope Assignment)
Revised Quantity
The total quantity that has been revised to account for approved changes for a scope assignment. This value equals the Original Quantity before the original baseline is set.
Calculated as Original Quantity plus Approved Change Quantity. Revised Quantity equals the Original Quantity before the original is baseline set.
Revised Quantity (Scope Item)
Revised Quantity
The total quantity that has been revised to account for approved changes for a scope item.
Calculated as Original Quantity plus Approved Change Quantity. Revised Quantity equals the Original Quantity before the original is baseline set.
Revised Start (Scope Assignment)
Revised Start
The revised start date for the scope assignment.
It is always the earliest start of the scope assignment's Planned Start date and all approved Change Start dates.
This field is used to spread Revised data fields.
Revised Start (Work Package)
Revised Start
The revised start date for the work package.
If the work package does not have scope assignments, this field is populated with the Original Start date until the original baseline is set.
This field is populated with the Data Date when the Modify Dates feature is run after the original baseline is set if the Revised Start date is before the Data Date and the work package's Scope Percent Complete is equal to 0%.
If the work package has scope assignments, is always the earliest start of its scope assignments' Planned Start dates and all approved Change Start dates.
Revised Start Date (Commitment)
Revised Start Date
The revised date by which work on the agreement is expected to start.
Revised Start Date (Contract)
Revised Start Date
The revised date by which the work contracted is scheduled to begin.
Risk Closed Post-Response Exposure (Actual Risk Response Cost)
Risk Closed Post-Response Exposure
The mean post-response probability of the risk multiplied by the mean post-response cost impact of the risk.
Risk Closed Pre-Response Exposure (Actual Risk Response Cost)
Risk Closed Pre-Response Exposure
The mean pre-response probability of the risk multiplied by the mean pre-response cost impact of the risk.
Risk Factor Cost Impact Option (Risk)
Risk Factor Cost Impact Option
The cost type the risk factor impacts.
Risk Factor Impact Activities Independently Option (Risk)
Risk Factor Impact Activities Independently Option
For a risk factor the option to impact activities independently.
Risk Level (Project)
Risk Level
The risk level assigned to the project.
Projects can have a risk level of very high, high, medium, low, or very low.
You can use risk level to determine what projects should be included in your plans, as well as which projects should be of priority.
Risk Open Post-Response Exposure (Actual Risk Response Cost)
Risk Open Post-Response Exposure
The mean post-response probability of the risk multiplied by the mean post-response cost impact of the risk.
Risk Open Pre-Response Exposure (Actual Risk Response Cost)
Risk Open Pre-Response Exposure
The mean pre-response probability of the risk multiplied by the mean pre-response cost impact of the risk.
Risk Score (Project)
Risk Score
The risk score value is based on the probability and impacts of a risk. It is derived from the probability impact matrix and any associated rules.
Role Committed (Resource Demand)
Role Committed
The sum of committed units for a given project - role demand.
Role Demand (Resource Demand)
Role Demand
The sum of the demand units entered for a single role.
Schedule Check - Dangling Finish (Activity)
Schedule Check - Dangling Finish
An activity with a dangling finish has only SF or SS successors and therefore could have an unrealistic finish date. To avoid dangling finishes, ensure each activity has at least one FS or SS relationship as its successor.
Schedule Check - Dangling Start (Activity)
Schedule Check - Dangling Start
An activity with a dangling start has only SF or FF predecessors and therefore could have an unrealistic start date. To avoid dangling starts, ensure each activity has at least one FS or SS relationship as its predecessor.
Schedule Check - FF Predecessor (Activity)
Schedule Check - FF Predecessor
Finish-to-Finish (FF) relationships are acceptable to use in moderation.
Schedule Check - FS Predecessor (Activity)
Schedule Check - FS Predecessor
Finish-to-Start (FS) relationships are the easiest to trace and understand. The majority of your relationships should be FS.
Schedule Check - Hard Constraint (Activity)
Schedule Check - Hard Constraint
Mandatory Start and Mandatory Finish are hard constraints that prevent activities from being scheduled according to logic and prevent delays from impacting succeeding activities. The effects of hard constraints become more noticeable as the schedule is progressed, and they generally should not be used.
Schedule Check - Invalid Progress Date (Activity)
Schedule Check - Invalid Progress Date
Progress should be recorded before the Data Date, and planned work should be recorded after. Activities with invalid dates can affect the accuracy of the project schedule.
Schedule Check - Large Duration (Activity)
Schedule Check - Large Duration
Large duration activities are harder to manage and may lack sufficient detail. Consider dividing these activities into shorter, more discrete activities, which provide better insight into cost and schedule.
Schedule Check - Large Float (Activity)
Schedule Check - Large Float
Large float values may indicate missing activity relationships. Provide activities with reasonable logic to ensure a more stable project plan.
Schedule Check - Late Activity (Activity)
Schedule Check - Late Activity
Late activities indicate how well the project is performing against the earned value baseline.
Schedule Check - Negative Float (Activity)
Schedule Check - Negative Float
Negative float usually indicates an activity constraint that cannot be met with the current schedule or progress has been made out of sequence. Corrective action should be taken to ensure activity dates are accurate and achievable.
Schedule Check - No Predecessors (Activity)
Schedule Check - No Predecessors
An activity with no predecessors could be scheduled to start immediately. This can negatively impact your project schedule and should be avoided.
Schedule Check - No Roles or Resources (Activity)
Schedule Check - No Roles or Resources
Roles and resources detail the cost and labor of the work to be performed. An activity without roles or resources may be insufficiently planned.
Schedule Check - No Successors (Activity)
Schedule Check - No Successors
An activity with no successor relationships could be delayed indefinitely without affecting project completion. Ensure all activities have at least one successor.
Schedule Check - Open Ends (Activity)
Schedule Check - Open Ends
An activity without a predecessor or successor relationship may negatively affect the quality of your schedule and should be avoided.
Schedule Check - Out of Sequence (Activity)
Schedule Check - Out of Sequence
Activities that progress out of sequence occur when a successor activity begins or completes before its predecessor finishes. This can lead to inaccurate timelines and project risks. Identify and correct out of sequence activities to ensure that the project schedule is accurate.
Schedule Check - Predecessor Lag (Activity)
Schedule Check - Predecessor Lag
Lag time between activities should not be used to control float or constrain dates. Consider representing the delay between two activities by adding another activity.
Schedule Check - Predecessor Negative Lag (Activity)
Schedule Check - Predecessor Negative Lag
The use of negative lags to overlap activities or adjust successor dates can affect the critical path and distort total float. It can also cause a successor to start before a predecessor. Negative lags can cause activities to be scheduled in unrealistic ways and generally should not be used.
Schedule Check - SF Predecessor (Activity)
Schedule Check - SF Predecessor
Start-to-Finish (SF) relationship logic says the successor occurs before the predecessor. SF relationships are a poor practice and generally should not be used.
Schedule Check - Soft Constraint (Activity)
Schedule Check - Soft Constraint
Soft constraints allow the schedule to be logic driven but can distort float and create negative float.
Schedule Check - SS Predecessor (Activity)
Schedule Check - SS Predecessor
Start-to-Start (SS) relationships are acceptable to use in moderation.
Schedule Finish Date (Risk Analysis)
Schedule Finish Date
The project schedule finish date at the time the risk analysis was run.
Schedule Health - Dangling Finish % (Project)
Schedule Health - Dangling Finish %
The percentage of activities in the project that only have Start-to-Finish or Start-to-Start successor relationships. If the activity type is Level of Effort, the activity is counted if all of the following are true: No Finish-to-Finish predecessor; No Finish-to-Finish successor; No Start-to-Finish predecessor; No Finish-to-Start successor. If the activity type is Milestone, the activity is not counted.
Schedule Health - Dangling Finish activity count (Project)
Schedule Health - Dangling Finish activity count
The number of activities in the project that only have Start-to-Finish or Start-to-Start successor relationships. If the activity type is Level of Effort, the activity is counted if all of the following are true: No Finish-to-Finish predecessor; No Finish-to-Finish successor; No Start-to-Finish predecessor; No Finish-to-Start successor. If the activity type is Milestone, the activity is not counted.
Schedule Health - Dangling Start % (Project)
Schedule Health - Dangling Start %
The percentage of activities in the project that only have Start-to-Finish or Finish-to-Finish predecessor relationships. If the activity type is Level of Effort, the activity is counted if all of the following are true: No Start-to-Start predecessor; No Start-to-Start successor; No Start-to-Finish successor; No Finish-to-Start predecessor. If the activity type is Milestone, the activity is not counted.
Schedule Health - Dangling Start activity count (Project)
Schedule Health - Dangling Start activity count
The number of activities in the project that only have Start-to-Finish or Finish-to-Finish predecessor relationships. If the activity type is Level of Effort, the activity is counted if all of the following are true: No Start-to-Start predecessor; No Start-to-Start successor; No Start-to-Finish successor; No Finish-to-Start predecessor. If the activity type is Milestone, the activity is not counted.
Schedule Health - FF Predecessor % (Project)
Schedule Health - FF Predecessor %
The percentage of predecessor relationships in the project with a type of Finish-to-Finish (FF).
Schedule Health - FF Predecessor activity count (Project)
Schedule Health - FF Predecessor activity count
The number of predecessor relationships in the project with a type of Finish-to-Finish (FF).
Schedule Health - FS Predecessor % (Project)
Schedule Health - FS Predecessor %
The percentage of predecessor relationships in the project with a type of Finish-to-Start (FS).
Schedule Health - FS Predecessor activity count (Project)
Schedule Health - FS Predecessor activity count
The number of predecessor relationships in the project with a type of Finish-to-Start (FS).
Schedule Health - Hard Constraint % (Project)
Schedule Health - Hard Constraint %
The percentage of activities in the project with a primary constraint of Mandatory Start or Mandatory Finish.
Schedule Health - Hard Constraint activity count (Project)
Schedule Health - Hard Constraint activity count
The number of activities in the project with a primary constraint of Mandatory Start or Mandatory Finish.
Schedule Health - Invalid Progress Date % (Project)
Schedule Health - Invalid Progress Date %
The percentage of activities in the project with invalid progress. An activity is included in the count if any of the following are true: Activity Planned Start less than Data Date; Activity Planned Finish less than or equal to Data Date; Activity Actual Start greater than or equal to Data Date; Activity Actual Finish greater than Data Date.
Schedule Health - Invalid Progress Date activity count (Project)
Schedule Health - Invalid Progress Date activity count
The number of activities in the project with invalid progress. An activity is included in the count if any of the following are true: Activity Planned Start less than Data Date; Activity Planned Finish less than or equal to Data Date; Activity Actual Start greater than or equal to Data Date; Activity Actual Finish greater than Data Date.
Schedule Health - Large Duration % (Project)
Schedule Health - Large Duration %
The percentage of activities in the project with an Activity Remaining Duration that meets or exceeds the given criteria value. The default value is 320h.
Schedule Health - Large Duration activity count (Project)
Schedule Health - Large Duration activity count
The number of activities in the project with an Activity Remaining Duration that meets or exceeds the given criteria value. The default value is 320h.
Schedule Health - Large Float % (Project)
Schedule Health - Large Float %
The percentage of activities in the project with an Activity Total Float that meets or exceeds the given criteria value. The default value is 320h.
Schedule Health - Large Float activity count (Project)
Schedule Health - Large Float activity count
The number of activities in the project with an Activity Total Float that meets or exceeds the given criteria value. The default value is 320h.
Schedule Health - Late Activity % (Project)
Schedule Health - Late Activity %
The percentage of activities in the project with an Activity Baseline Finish Variance less than 0 or without a set activity baseline.
Schedule Health - Late Activity activity count (Project)
Schedule Health - Late Activity activity count
The number of activities in the project with an Activity Baseline Finish Variance less than 0 or without a set activity baseline.
Schedule Health - Negative Float % (Project)
Schedule Health - Negative Float %
The percentage of activities in the project with a total float less than 0.
Schedule Health - Negative Float activity count (Project)
Schedule Health - Negative Float activity count
The number of activities in the project with a total float less than 0.
Schedule Health - No Predecessor % (Project)
Schedule Health - No Predecessor %
The percentage of activities in the project without predecessors.
Schedule Health - No Predecessor activity count (Project)
Schedule Health - No Predecessor activity count
The number of activities in the project without predecessors.
Schedule Health - No Roles or Resources % (Project)
Schedule Health - No Roles or Resources %
The percentage of activities in the project without role or resource assignments.
Schedule Health - No Roles or Resources activity count (Project)
Schedule Health - No Roles or Resources activity count
The number of activities in the project without role or resource assignments.
Schedule Health - No Successor % (Project)
Schedule Health - No Successor %
The percentage of activities in the project without successors.
Schedule Health - No Successor activity count (Project)
Schedule Health - No Successor activity count
The number of activities in the project without successors.
Schedule Health - Open Ends % (Project)
Schedule Health - Open Ends %
The percentage of activities in the project without predecessors or successors.
Schedule Health - Open Ends activity count (Project)
Schedule Health - Open Ends activity count
The number of activities in the project without predecessors or successors.
Schedule Health - Overall Health % (Project)
Schedule Health - Overall Health %
The weighted aggregation of active check values that represents the overall quality of your project. A higher schedule health score indicates a higher quality schedule. Calculated as 100% - (Sum of [Check Adjusted Percentage * Check Weighting] / Sum of all active check weighting values)
Schedule Health - Predecessor Lag % (Project)
Schedule Health - Predecessor Lag %
The percentage of predecessor relationships in the project with a lag greater than 0.
Schedule Health - Predecessor Lag activity count (Project)
Schedule Health - Predecessor Lag activity count
The number of predecessor relationships in the project with a lag greater than 0.
Schedule Health - Predecessor Negative Lag % (Project)
Schedule Health - Predecessor Negative Lag %
The percentage of predecessor relationships in the project with a lag less than 0.
Schedule Health - Predecessor Negative Lag activity count (Project)
Schedule Health - Predecessor Negative Lag activity count
The number of predecessor relationships in the project with a lag less than 0.
Schedule Health - SF Predecessor % (Project)
Schedule Health - SF Predecessor %
The percentage of predecessor relationships in the project with a type of Start-to-Finish (SF).
Schedule Health - SF Predecessor activity count (Project)
Schedule Health - SF Predecessor activity count
The number of predecessor relationships in the project with a type of Start-to-Finish (SF).
Schedule Health - Soft Constraint % (Project)
Schedule Health - Soft Constraint %
The percentage of activities in the project with a primary constraint of As Late As Possible, Finish On, Finish On or After, Finish On or Before, Start On, Start On or After, or Start On or Before.
Schedule Health - Soft Constraint activity count (Project)
Schedule Health - Soft Constraint activity count
The number of activities in the project with a primary constraint of As Late As Possible, Finish On, Finish On or After, Finish On or Before, Start On, Start On or After, or Start On or Before.
Schedule Health - SS Predecessor % (Project)
Schedule Health - SS Predecessor %
The percentage of predecessor relationships in the project with a type of Start-to-Start (SS).
Schedule Health - SS Predecessor activity count (Project)
Schedule Health - SS Predecessor activity count
The number of predecessor relationships in the project with a type of Start-to-Start (SS).
Schedule Impact (Potential Change Order)
Schedule Impact
The schedule impact of the potential change order proposal.
Schedule Impact
The schedule impact of the potential change order.
Schedule Impact (Potential Change Order)
Schedule Impact
The schedule impact of the potential change order.
Schedule Must Finish By Date (Project)
Schedule Must Finish By Date
The latest date on which the scheduled activities must be complete for a project.
Schedule Percent Complete (Activity)
Schedule Percent Complete
The activity schedule percent complete specifies how much of the activity's project baseline duration is complete so far.
With an earned value baseline selected, the schedule percent complete value is calculated based on where the current data date falls relative to the activity's project baseline start and finish dates.
Calculated as (Data Date - Baseline Start Date) / (Baseline Finish Date - Baseline Start Date).
If the data date is earlier than the baseline start, the schedule percent complete is 0. If the data date is later than the baseline finish, the schedule percent complete is 100.
Without an earned value baseline selected, the schedule percent complete value will use the activity planned dates and will be calculated based on where the current data date falls relative each activity's planned start and finish dates.
Calculated as (Data Date - Planned Start Date) / (Planned Finish Date - Planned Start Date).
If the data date is earlier than the planned start, the schedule percent complete is 0. If the data date is later than the planned finish, the schedule percent complete is 100.
Schedule Percent Complete (Schedule)
Schedule Percent Complete
The activity schedule percent complete, which specifies how much of the activity's project baseline duration is complete so far.
Calculated as Data Date minus Baseline Start divided by Baseline Finish minus Baseline Start.
If the data date is earlier than the baseline start, the schedule percent complete is 0. If the data date is later than the baseline finish, the schedule percent complete is 100. The schedule percent complete indicates how much of the activity duration should currently be complete, relative to the selected project baseline.
Schedule Performance Index (Project Budget)
Schedule Performance Index
The measure of the work accomplished as a percentage of the work scheduled on a project.
Schedule Performance Index indicates whether you are meeting earned and planned values within your project schedule.
A value less than 1 indicates that less work was performed than was scheduled. A value greater than 1 indicates the project is ahead of schedule.
This value can be entered manually or can be imported.
Schedule Performance Index (SPI) (Activity)
Schedule Performance Index (SPI)
The ratio of the approved budget for the work performed to the approved budget of the work planned. The SPI reflects the relative amount the project is ahead or behind schedule, and is also referred to as the project's schedule efficiency.
A value greater than 1 indicates you are ahead of schedule. A value equal to 1 indicates you are on schedule. A value less than 1 indicates you are behind schedule.
Calculated as Earned Value divided by Planned Value.
Schedule Performance Index (SPI) (Schedule)
Schedule Performance Index (SPI)
The ratio of the approved budget for the work performed for the approved budget of the work planned. The SPI shows the relative amount the project is ahead or behind schedule.
Schedule Performance Index (SPI) Labor Units (Activity)
Schedule Performance Index (SPI) Labor Units
The ratio of the earned value of labor units to the planned value of labor units.
Calculated as Earned Value Labor Units divided by Planned Value Labor Units.
Schedule Performance Index Labor Units (Schedule)
Schedule Performance Index Labor Units
The ratio of the earned value of labor units to the planned value of labor units.
Calculated as Earned Value Labor Units divided by Planned Value Labor Units.
Schedule Variance (Activity)
Schedule Variance
A measure of activity schedule performance. The difference between the amount budgeted for the work you actually did and the work you planned to do.
Indicates how much you are ahead or behind schedule. A negative value indicates that less work was actually performed than was scheduled.
Calculated as Earned Value minus Planned Value.
Schedule Variance (Project Budget)
Schedule Variance
The measure of schedule performance on a project.
A negative value indicates that less work was actually performed than was scheduled.
This value can be entered manually or can be imported. This value is based on the base currency with specified exchange rate.
Schedule Variance (Schedule)
Schedule Variance
The difference between the amounts budgeted for the work you actually did and the work you planned to do. The SV shows whether you are ahead or behind schedule and is indicative only. An SV calculated as greater than 0 shows you are good and ahead of schedule.
Schedule Variance Index (Activity)
Schedule Variance Index
The ratio of the schedule variance and the work scheduled to be performed.
Calculated as Schedule Variance divided by Planned Value.
Schedule Variance Labor Units (Activity)
Schedule Variance Labor Units
The difference between the earned value of work performed and the work scheduled to be performed.
Calculated as Earned Value Labor Units minus Planned Value Labor Units.
Scheduled Finish Date (Project)
Scheduled Finish Date
The calculated latest early finish date, which is based on the schedule most recently generated for the project.
Scheduled Value (Change Order)
Scheduled Value
The current value of the line item.
Scheduled Value (Commitment)
Scheduled Value
The total value of the line item.
Scheduled Value (Contract)
Scheduled Value
The total cost represented by the schedule of values.
Scope Percent Complete (Activity)
Scope Percent Complete
The percentage completion of the scope assignments linked to the activity.
Calculated as Installed Quantity divided by At Completion Quantity.
Scope Percent Complete (Scope Assignment)
Scope Percent Complete
Calculated as Installed Quantity divided by At Completion Quantity.
Scope Percent Complete (Scope Item)
Scope Percent Complete
Sum of Quantity Completed Weight for the scope items assigned to work packages divided by Revised Quantity for the scope item.
Scope Percent Complete (Work Package)
Scope Percent Complete
The weight is calculated using cost, quantity, hours, or manually entered values. Cost, Quantity, and Hours are represented as n in the equations that follow.
The n weight is first calculated for each scope assignment in the work package as Revised n multiplied by the scope assignment Scope Percent Complete.
Scope Percent Complete is calculated as Installed Quantity divided by At Completion Quantity.
The sum of the scope assignments Revised n and the sum of the scope assignments n Weight for all scope assignments in the work package are then used to compute the work package Scope Percent Complete. This is calculated as the n Weight divided by Revised n.
Weight for the Manual option is calculated as Manual Weight Factor multiplied by Scope Percent Complete.
Scope Percent Complete at the work package level for the manual option is calculated as the sum of Manual Weight divided by the sum of Manual Weight Factors for all scope assignments in the work package.
Scope Percent Complete Weight Method (Project)
Scope Percent Complete Weight Method
The weight for scope items is calculated using quantity.
Scope Percent Complete Weight Method (Work Package)
Scope Percent Complete Weight Method
The weight is calculated using cost, quantity, hours, or manually entered values. Cost, Quantity, and Hours are represented as n in the equations that follow.
The n weight is first calculated for each scope assignment in the work package as Revised n multiplied by the scope assignment Scope Percent Complete.
Scope Percent Complete is calculated as Installed Quantity divided by At Completion Quantity.
The sum of the scope assignments Revised n and the sum of the scope assignments n Weight for all scope assignments in the work package are then used to compute the work package Scope Percent Complete. This is calculated as the n Weight divided by Revised n.
Completed Weight for the Manual option is calculated as Manual Weight multiplied by Scope Percent Complete.
Scope Percent Complete at the work package level for the manual option is calculated as the sum of Manual Completed Weight divided by the sum of Manual Weight for all scope assignments in the work package.
Score (Project Evaluation)
Score
The evaluation score of a project per category and sub-category.
The sub-category score formula is calculated as the selected Rank Weight % multiplied by the given sub-category Weight % divided by 100.
The category score formula is calculated as the sum of the sub-category Scores. If a given sub-category does not have a score, its score is 0.
Slack (Task)
Slack
The amount of time between a predecessor task's due date and its successor task's start date. This is a read-only field.
Spend Finish Date (Program)
Spend Finish Date
The finish date for the program actuals.
Spend Start Date (Program)
Spend Start Date
The start date for the program actuals.
Staffed Remaining Cost (Activity Assignment)
Staffed Remaining Cost
The remaining cost for resource assignments that have a filled role.
Staffed Remaining Units (Activity Assignment)
Staffed Remaining Units
The remaining units for resource assignments that have filled a role.
Start - Deterministic (Risk Analysis)
Start - Deterministic
The activity start date at the time the risk analysis was run.
Start (Activity Assignment)
Start
The start date for the activity assignment.
Start (Activity)
Start
The current start date of the activity.
For started activities, this is the actual start date. For not started activities, this is the planned start date until the project is scheduled. When scheduled, the start date field is set to the remaining early start date.
Start (Budget Planning)
Start
The start date for each cost curve row.
The start displays the start date of the corresponding cost curve type.
For example, the start for a current approved budget row is the current approved budget start date.
Start Date (Activity)
Start Date
The reporting period start date.
Start Date (Commitment)
Start Date
The date by which the work represented by the commitment is scheduled to be started.
Start Date (Contract)
Start Date
The date by which the work contracted is scheduled to be started.
Start Date (Funds)
Start Date
The date when money in the fund will start being available.
Start Date (Risk Analysis)
Start Date
The project start date at the time the risk analysis was run.
Start Date (Task)
Start Date
The date when the task is set to begin.
If the task is set to allow non-work days, the date is calculated as Due Date minus Duration plus 1 day.
If the task is not set to allow non-work days, the date is calculated as Due Date minus the sum of Duration plus Non-Work Days, plus 1 day.
This is a read-only field.
Status
Status
The status of the idea. Valid values are Draft, Submitted, Owner Assigned, Accepted, Project Proposal, and Rejected.
Status
The current status of the strategy node. Active: The strategy node is available for use. Inactive: The strategy node is not available for use.
Status
Status
The current status of the strategy node. Active: The strategy node is available for use. Inactive: The strategy node is not available for use.
Status - Dates (Task)
Status - Dates
Indicates the overall date status of the activity's assigned tasks.
Outside Activity: A task's dates are outside of the activity's Start and Finish dates.
Inside Activity: All of the tasks' dates are within the activity's Start and Finish dates.
No Tasks Assigned: No tasks are assigned to the activity.
Status (Baseline)
Status
The status of the baseline process. Valid values are: In Progress, Failed, and Complete.
Status (Budget Change Request)
Status
The state of the project budget change request. Pending: The change request is awaiting a decision. Approved: The change request was approved. Rejected: The change request was not approved.
Status (Budget Transaction)
Status
The status of the transaction. Indicates whether the transaction is approved, pending, draft, or rejected.
Status (Budget Transfer)
Status
The state of the project budget transfer request. Pending: The change request is awaiting a decision. Approved: The change request was approved. Rejected: The change request was not approved.
Status (Change Order)
Status
The status of the change order.
Status (Commitment)
Status
The status of the commitment.
Status (Contract)
Status
The status of the contract.
Status (Funds)
Status
Either Active or Inactive. Inactive funds cannot be allocated or appropriated. They can only be consumed for projects or programs.
Status (Payment Application)
Status
The status of the payment application.
Status (Potential Change Order)
Status
The status of the question. Status values include Draft, Pending, Answered, and Withdrawn.
Status
The status of the potential change order proposal.
Status (Potential Change Order)
Status
The status of the potential change order proposal.
Status (Program Budget Change Request)
Status
The state of the program budget change request. Pending: The change request is awaiting a decision. Approved: The change request was approved. Rejected: The change request was not approved.
Status (Program)
Status
The current status of the program.
Status (Risk)
Status
The status of the risk.
Proposed: The risk is identified and awaits approval.
Open: The risk is approved as a valid risk and is awaiting management.
Monitoring: The risk has been managed and is being monitored.
Impacting: The risk is currently impacting the project.
Cannot Impact: The risk did not happen and can no longer happen.
Impacted: The risk occurred.
Rejected: The risk is not seen as a valid risk to the project and therefore will not be tracked and managed by the project.
Status (Schedule Scenario)
Status
The status of the scenario. A scenario can have a status of In Progress, Failed, or Complete.
Status (Task Constraint)
Status
The status of the task constraint. Valid values are Not Planned, Planned, and Delivered.
Status Change Date (Program)
Status Change Date
The date and time the program status was changed.
Strategic Objective (Program)
Strategic Objective
A detailed description of the strategic object of the program.
Strategic Priority (Project)
Strategic Priority
The project's priority in the strategic plan.
This priority value ranges from 1 to 10,000 with a default of 500. Use of the priority value, such as whether to place higher priority at the lower end of the scale, toward the endpoint 1, or at the higher end, toward 10,000, is at the discretion of the user. This field is not used for calculating data.
Suspend Date (Activity)
Suspend Date
The date work has temporarily stopped on a given activity.
Target Budget (Budget Planning)
Target Budget
The total Target Budget for the portfolio's Planning Horizon set by the portfolio manager.
Task Check - Commitments (Task)
Task Check - Commitments
Tasks that contain commitments to due dates.
Task Check - Due This Week (Task)
Task Check - Due This Week
Tasks that are due within the calendar week from Sunday to Saturday.
Task Check - Overdue (Task)
Task Check - Overdue
Tasks that have not been completed by their due date.
Task Check - Pending (Task)
Task Check - Pending
Tasks that have a due date but are not committed, or tasks that are committed but the due date has been changed.
Task Check - Planned Outside Activity Dates (Task)
Task Check - Planned Outside Activity Dates
Tasks with due dates that occur before the activity start date or after the activity end date.
Task Check - Scheduled on Non-work Days (Task)
Task Check - Scheduled on Non-work Days
Tasks that occur on non-work days as defined by the project calendar when Use Only Work Days is selected.
Task Check - Tasks with Slack (Task)
Task Check - Tasks with Slack
Task slack is the amount of time a task can be delayed before it impacts the start date of the most immediate hand-off successor.
Task Check - Unaccepted Proposed Due Date (Task)
Task Check - Unaccepted Proposed Due Date
Tasks that have a proposed due date value that has not yet been accepted.
Task Check - Unassigned (Task)
Task Check - Unassigned
Tasks that do not have a user assigned.
Task Check - Unplanned (Task)
Task Check - Unplanned
Tasks without a due date.
Task Status - Completion (Activity)
Task Status - Completion
The current status of the task assigned to the activity. Valid values are New, Pending, Committed, and Completed.
This is a read-only field.
Task Status - Dates (Activity)
Task Status - Dates
Indicates the overall date status of the activity's assigned tasks.
Outside Activity: A task's dates are outside of the activity's Start and Finish dates.
Inside Activity: All of the tasks' dates are within the activity's Start and Finish dates.
No Tasks Assigned: No tasks are assigned to the activity.
This is a read-only field.
Task Status - Indicator (Activity)
Task Status - Indicator
Indicates whether any of the activity's assigned tasks have dates or completion statuses that requires attention.
This is a read-only field.
Time Change (Change Order)
Time Change
The amount of time added to or subtracted from the commitment as a result of the change order.
Timesheet Actual Start (Activity Assignment)
Timesheet Actual Start
Actual Start Date derived from Timesheet at the time of timesheet approval.
Timesheet Actual Units (Activity Assignment)
Timesheet Actual Units
Timesheet actual hours logged from timesheet for the assignment.
Timing (Risk Response Action)
Timing
Indicates whether the response action start or finish is before today's date.
Total (Change Order)
Total
The total value of the change order line item cost.
Total (Commitment)
Total
The total value of the commitment line item cost.
Total (Contract)
Total
The total value of the line item cost.
Total (Funds)
Total
The amount of money granted for the fund.
Total Actual Response Cost (Risk)
Total Actual Response Cost
The total actual response cost of the risk.
Total Cost
Total Cost
The cost to be added or subtracted from the program budget.
Total Cost (Project Budget Change)
Total Cost
The cost to be added or subtracted from the project budget.
Total Earned Less Retainage (Payment Application)
Total Earned Less Retainage
The total amount earned for the associated agreement, minus all money withheld as retainage.
Total Float - Deterministic (Risk Analysis)
Total Float - Deterministic
The activity total float at the time the risk analysis was run.
Total Float (Activity)
Total Float
The amount of time the activity can be delayed before delaying the project finish date. Calculated as Late Start minus Early Start or as Late Finish minus Early Finish.
Total Retainage (Payment Application)
Total Retainage
The total amount of money that has been withheld as retainage for work on the agreement.
Transfer From Budget (Budget Transaction)
Transfer From Budget
The budget ID of the Transfer From Budget record.
Transfer From CBS Code (Budget Transaction)
Transfer From CBS Code
The cost code for the Transfer From Budget record.
Transfer From Cost Category (Budget Transaction)
Transfer From Cost Category
The category of the Transfer From Budget record.
Transfer To Budget (Budget Transaction)
Transfer To Budget
The budget ID of the Transfer To Budget record.
Transfer To CBS Code (Budget Transaction)
Transfer To CBS Code
The cost code for the Transfer To Budget record.
Transfer To Cost Category (Budget Transaction)
Transfer To Cost Category
The category of the Transfer To Budget record.
Transfer Type (Budget Transaction)
Transfer Type
Specifies whether the budget row is transfer from budget record or transfer to budget record.
Unallocated (Funds)
Unallocated
The portion of the fund that has not been reserved for work on projects, programs or in other workspaces.
Unappropriated (Funds)
Unappropriated
The portion of the fund that has not yet been committed to actual work.
Unassigned Quantity (Scope Item)
Unassigned Quantity
The total quantity that has not been distributed to work packages. This is the amount that is available for distribution to scope assignments. After the original baseline is set, this includes all approved quantity changes for scope items.
Undistributed (Funds)
Undistributed
The amount of money that has not been distributed for the fund.
Undistributed Approved Budget (Budget Planning)
Undistributed Approved Budget
The amount of approved budget unallocated across the project timescale.
Undistributed Approved Budget
The amount of approved budget unallocated to projects included in the portfolio's budget plan.
Undistributed Approved Budget (Budget Planning)
Undistributed Approved Budget
The amount of approved budget unallocated to projects included in the portfolio's budget plan.
Undistributed Approved Budget (Project Budget)
Undistributed Approved Budget
The amount of approved budget unallocated across the project timescale. This value is based on the base currency with specified exchange rate.
Undistributed Benefits (Program Budget)
Undistributed Benefits
The amount of benefits that have not been allocated across the program timescale.
Undistributed Benefits (Project Budget)
Undistributed Benefits
The amount of benefits that have not been allocated across the project timescale. This value is based on the base currency with specified exchange rate.
Undistributed Forecast (Project Budget)
Undistributed Forecast
The amount of forecast cost unallocated across the project timescale. This value is based on the base currency with specified exchange rate.
Undistributed Planned Budget (Project Budget)
Undistributed Planned Budget
The amount of planned budget unallocated across the project timescale. This value is based on the base currency with specified exchange rate.
Undistributed Proposed Budget (Budget Planning)
Undistributed Proposed Budget
The amount of a proposed budget unallocated to projects included in the portfolio's budget plan.
Undistributed Proposed Budget
The amount of planned budget unallocated across the project timescale.
Undistributed Proposed Budget (Budget Planning)
Undistributed Proposed Budget
The amount of planned budget unallocated across the project timescale.
Undistributed Proposed Budget (Project Budget)
Undistributed Proposed Budget
The amount of proposed budget unallocated across the project timescale. This value is based on the base currency with specified exchange rate.
Undistributed Target Budget (Budget Planning)
Undistributed Target Budget
The amount of target budget unallocated to projects included in the portfolio's budget plan.
Unit of Measure (Budget Item)
Unit of Measure
The Unit of Measure used for the budget item.
Unit of Measure (Budget Transaction)
Unit of Measure
The Unit of Measure used for the budget line item detail.
Unit Of Measure (Change Order)
Unit Of Measure
The units in which the line item is measured.
Unit Of Measure
The units in which the line item is measured.
Unit Of Measure (Change Order)
Unit Of Measure
The units in which the line item is measured.
Unit Of Measure (Commitment)
Unit Of Measure
The unit in which the line item quantity is measured.
Unit Of Measure
The unit in which the line item quantity is measured.
Unit Of Measure (Commitment)
Unit Of Measure
The unit in which the line item quantity is measured.
Unit Of Measure (Contract)
Unit Of Measure
The unit by which the line item quantity is measured.
Unit Of Measure
The unit by which the schedule of values quantities are measured.
Unit Of Measure (Contract)
Unit Of Measure
The unit by which the schedule of values quantities are measured.
Unit Of Measure (Potential Change Order)
Unit Of Measure
The unit of measure of the proposal line item.
Unit Price (Actual Line Item)
Unit Price
The price associated with the actual line item.
If a Unit of Measure is associated with the actual line item, the Unit Price is the unit price per measure.
Unit Price (Change Order)
Unit Price
The price of each unit of the line item.
Unit Price
The price per unit per line item.
Unit Price (Change Order)
Unit Price
The price per unit per line item.
Unit Price (Commitment)
Unit Price
The price of each unit represented by the line item.
Unit Price
The price of each unit represented by the commitment line item.
Unit Price (Commitment)
Unit Price
The price of each unit represented by the commitment line item.
Unit Price (Contract)
Unit Price
The price per unit of items represented by the line item.
Unit Price
The price of each unit represented by the schedule of values.
Unit Price (Contract)
Unit Price
The price of each unit represented by the schedule of values.
Unit Rate (Budget Item)
Unit Rate
The cost per Unit of Measure for the budget line item.
Unit Rate (Budget Transaction)
Unit Rate
The cost per Unit of Measure for the budget line item detail.
Unit Rate (Program Budget Item)
Unit Rate
The cost per Unit of Measure for the budget line item.
Unit Rate (Program Budget Transaction)
Unit Rate
The cost per Unit of Measure for the budget line item detail.
Units Percent Complete (Activity Assignment)
Units Percent Complete
The percent complete of units for the resource assignment on the activity.
Units Percent Complete (Activity)
Units Percent Complete
The percent complete of units for all labor and nonlabor resources assigned to the activity. Calculated as Actual Units divided by At Completion Units multiplied by 100.
Unstaffed Remaining Cost (Activity Assignment)
Unstaffed Remaining Cost
The remaining cost for resource assignments that do not have a filled role.
Unstaffed Remaining Units (Activity Assignment)
Unstaffed Remaining Units
The remaining units for resource assignments that have not filled a role.
Use Only Work Days (Task)
Use Only Work Days
Enables the user to allow only the project calendar's work days and ignore non-work days when determining the value for Start and Due Date.
Value (Thresholds)
Value
The numeric value measured by the threshold.
Use threshold operators to compare this value to the values in projects and portfolios.
Value
The value which other thresholds are measured against.
Value (Thresholds)
Value
The value which other thresholds are measured against.
Variance - Finish Date (Project)
Variance - Finish Date
The duration between the project's finish date and the baseline's finish date.
When the field value is generated through a P6 EPPM connection, then it represents the duration between the finish date in the current project and the baseline finish date.
This value can only be imported.
Variance - Start Date (Project)
Variance - Start Date
The duration between the project's start date and the baseline's start date.
When the field value is generated through a P6 EPPM connection, then it represents the duration between the start date in the current project and the baseline start date.
This value can only be imported.
Variance (Actuals - Forecast) (Project Budget)
Variance (Actuals - Forecast)
The total and time phased variance between the project's Actuals and Forecast. This value is based on the base currency with specified exchange rate.
Variance (Actuals - Planned Budget) (Project Budget)
Variance (Actuals - Planned Budget)
The total and time phased variance between the project's Actuals and Planned Budget. This value is based on the base currency with specified exchange rate.
Variance (Allocated Fund - Forecast) (Project Budget)
Variance (Allocated Fund - Forecast)
The total and time phased variance between the project's Allocated Fund and Forecast. This value is based on the base currency with specified exchange rate.
Variance (Allocated Fund - Planned Budget) (Project Budget)
Variance (Allocated Fund - Planned Budget)
The total and time phased variance between the project's Allocated Fund and Planned Budget. This value is based on the base currency with specified exchange rate.
Variance (Forecast - Portfolio Approved Budget) (Project Budget)
Variance (Forecast - Portfolio Approved Budget)
The total and time phased variance between the project's Forecast and Approved Budget. This value is based on the base currency with specified exchange rate.
Variance (Portfolio Approved Budget - Actuals) (Project Budget)
Variance (Portfolio Approved Budget - Actuals)
The total and time phased variance between the project's Approved Budget and Actuals. This value is based on the base currency with specified exchange rate.
Variance (Portfolio Proposed Budget - Forecast) (Project Budget)
Variance (Portfolio Proposed Budget - Forecast)
The total and time phased variance between the project's Proposed Budget and Forecast. This value is based on the base currency with specified exchange rate.
Variance (Proposed Budget - Planned Budget) (Project Budget)
Variance (Proposed Budget - Planned Budget)
The total and time phased variance between the project's Proposed Budget and Planned Budget. This value is based on the base currency with specified exchange rate.
Variance At Completion (Activity)
Variance At Completion
The difference between the baseline total cost and the current estimate of total cost. A negative value indicates an estimated cost overrun.
Calculated as Budget At Completion minus Estimate At Completion.
Variance At Completion (Schedule)
Variance At Completion
The difference between the baseline total cost and the current estimate of total cost. A negative value indicates an estimated cost overrun.
Variance At Completion Labor Units (Activity)
Variance At Completion Labor Units
The difference between the baseline planned total labor units and the estimate at completion labor units.
Calculated as Project Baseline Planned Total Labor Units minus Estimate At Completion Labor Units.
Withdraw Approval Date (Budget Change Request)
Withdraw Approval Date
Date the item was withdrawn.
Withdraw Approval Date (Budget Transfer)
Withdraw Approval Date
Date the item was withdrawn.
Withdraw Approval Date (Project Budget)
Withdraw Approval Date
The date the approval of the budget is withdrawn.
Withdraw Approval Date
The date the approval of the budget is withdrawn.
Withdraw Approval Date (Project Budget)
Withdraw Approval Date
The date the approval of the budget is withdrawn.
Year End Forecast (YEF) (Project Budget)
Year End Forecast (YEF)
Total forecast at the end of year actuals till date, with respect to the current year. This value is based on the base currency with specified exchange rate.
YTD Actuals (Project Budget)
YTD Actuals
A measurement of capital spent on a project starting from the beginning of the year up to the present date.
YTD Actuals provides an overview of the total amount of actuals accrued on a project over the current Period Year. This value is based on the base currency with specified exchange rate.