Update Progress of an Activity

You can update the progress of your activities after you have marked them as started.

To update the progress of an activity:

  1. In the header, select your username, and then select My Activities.
  2. Select List to enter the List view.
  3. In the activity list, select the activity that you want to update.
  4. In the activity details area, use the available status fields to update the status of the activity.

    Your manager determines which fields are available to view and edit.

    Some fields are automatically updated to reflect changes to other fields. For example, Time Left is automatically updated when you update Time Spent.

    Activities that have asterisks (*) next to their names have been modified, but their changes have not been saved.

  5. Select Save.

Tips



Last Published Tuesday, May 21, 2024