Assign a CBS Code and Cost Category to a Risk

By assigning a CBS code and a CBS cost category, both pre-response and post-response cost impacts are made available on the project's cost sheet.

You cannot assign a CBS code or cost category to program risks, but you can assign them to project risks in the program context.

To assign a CBS code and a cost category to a risk:

  1. In the object selector, select a project or program.
  2. In the sidebar, hover over Risk, and select Risk Register.
  3. In the table, select a risk.
  4. In the CBS Code and Cost Category columns, select a CBS code and a cost category for the risk.
  5. Select Save.

Tips