Risk Analysis Prerequisites

Before you can run a risk analysis on a project, you must have the following prerequisites in place:

The Monte Carlo process uses activity uncertainty values, the schedule impact values from assigned threat or opportunities risks, and non-working estimates from weather risks to vary the duration of each activity during the risk analysis. As the analysis calculations are performed, duration changes in predecessor activities can impact the start dates of their successor activities, which can also lead to those successor activities being scheduled over additional non-working periods, thereby further delaying an activity's finish date. All of these values are captured for each iteration run during the risk analysis, resulting in probabilistic distributions of possible outcomes.



Last Published Monday, June 24, 2024