Specify Project-level Calendar Availability for Assignment
Schedule Overview > Get Started with Schedule > Project Settings > Dictionaries (Project) > Calendars (Project-level)
Before calendars can be assigned, they must be made available to supporting objects. Each project-level calendar can be made available for assignment to the project or to project resources and roles.
Making project-level calendars available to the project enables you to set it as the default project calendar or to individual activities in the project. The option is selected by default when a calendar is created.
To specify project-level calendar availability:
- Navigate to the project Calendars dictionary page
- In the object selector, select a project.
- In the sidebar, select Summary & Settings.
- On the Summary & Settings menu, select Dictionaries, and then select Calendars.
- Select a calendar.
- Select the Summary tab.
- In the Available To section, select Project, Resource/Role, or both.
- Save your changes:
- Select Save.
- In the Summary & Settings panel, select Close.
Tips
- If you assign a project-level calendar to a project-level resource or role, then the resource or role can't be promoted to the workspace unless you remove the calendar assignment or promote the project calendar to the workspace.