Enter Activity Duration Information

Activity durations are automatically calculated using the activity start and end dates and the project calendar. You can also manually enter activity duration information using the Status detail window.

To configure activity duration information:

  1. Navigate to the Activities page
  2. In the table, select the activity.
  3. On the Layout menu, select Activity Details, and then select the Status detail window.
  4. Set the activity durations by completing the following fields:
    • Planned Duration: The expected amount of time required to complete the activity.
    • Remaining Duration: The total working time from the activity remaining start date to the remaining finish date.
    • At Completion Duration: The total working time from the activity's current start date to the current finish date.
  5. All changes made to this page are saved automatically.