Commit to a Task on the Task List Page

Video

Commit to tasks to agree to perform their work by a specified date. In the Commitments detail window, you can track the commitment history of a task, including committed dates, due dates, reasons missed, and comments. You cannot commit to private tasks, task milestones, or completed tasks. If a proposed due date exists for a task, it will be displayed in the Commit Task dialog box. This enables you to review the proposed due date before selecting the same or a different due date for the commitment. When a task is committed, the proposed due date is removed from the task, and the current due date is updated to match the committed due date.

To learn more about task commitments, see Understanding Tasks App Concepts.

To commit to a task on the Task List page:

  1. In the object selector, select a project or program.
  2. In the sidebar, hover over Tasks, and select Task List.
  3. Commit to a task using one of the following methods:
    • In the table, select a task, select the Context menu, and then select Commit. In the Commit Task dialog box, select a Due Date for the commitment. Select Commit.
    • Commit to one or more tasks by right-clicking a selection and selecting Commit Tasks. Only tasks in the selection without an existing commitment will be committed. For pending tasks, the committed due date is set to the task's current due date. For new tasks, the committed due date is set to today's date.
    • In the table, select a task, in the Hand-off Flow detail window, right-click a task and select Commit.
  4. All changes made to this page are saved automatically.

Tips



Last Published Tuesday, May 21, 2024