Assign a Task to a Constraint on the Constraints Page

Identify the tasks that will be impacted by each constraint on the Constraints page.If a task can't begin before a constraint is resolved, then it should be associated with that constraint. You can assign multiple tasks to a single constraint, and the same task can be assigned to multiple constraints. Task data on the Constraints page is read-only.

To assign a task to a constraint on the Constraints page:

  1. In the object selector, select a project.
  2. In the sidebar, hover over Tasks, and select Constraints.
  3. In the table, select a constraint, and then select the Impacted Tasks detail window.
  4. In the detail window, select Assign, and then select one or more tasks to associate with the current task constraint.
  5. Select Select.
  6. All changes made to this page are saved automatically.

Tips