Use Swimlanes on the Planning Board

When you add or open a task plan on the Work Plan page, the planning board rearranges task cards by swimlanes, and the name of the open task plan displays above the planning board. Swimlanes arrange task cards on the planning board using horizontal lanes by any combination of assigned users, company, or WBS depending on task plan settings applied to the Work Plan page. Organizing the planning board by swimlane categories enables you to track tasks based on the most relevant attributes for your project and to visualize responsibility in the workflow. Display a task plan with swimlane categories on the Work Plan page planning board, and save the task plan to evaluate different plan versions later. Select and highlight specific swimlanes to help draw attention to task cards in specific swimlanes during planning sessions with other project members.

You can move existing tasks freely among swimlanes in the planning board or to and from the hopper. Add a new task directly to a swimlane using its right-click menu, then modify the details directly from the Work Plan page.

Note: You must have the Add Configure Task Plan privilege enabled in Project permissions to add task plans to a project.

To move existing task and activity data into or out of swimlanes on the planning board:

To declutter tasks, activities, or swimlanes on the planning board:

Tips