Configure Schedule Settings for a Project

Configure project schedule settings to set planned project start and finish dates, as well as a date by which the project must finish. These dates are also used to drive the project scheduler during the scheduling process.

To configure schedule settings for your project:

  1. Navigate to the project Details page
  2. In the Schedule section, in the Project Planned Start field, select the start date.
  3. In the Project Planned Finish field, select a planned finish date.
  4. In the Schedule Must Finish By Date field, select the date the project must finish by.
  5. Save your changes:
    1. Select Save.
    2. In the Summary & Settings panel, select Close.

This setting is used in the following apps:

Resources
Risk
Schedule
Scope
Tasks